MGM Seeks to Demolish Harmon Towers
September 01, 2011 —
CDJ STAFFCiting public safety concerns and the cost of repair, MGM Resorts International is seeking to demolish the unfinished hotel tower. The company has a few hurdles to go through before they start laying the charges to implode the structure. Any plans would have to be approved by not only Clark County officials, but also the district court has an order blocking any activity during litigation between MGM and the general contractor on the project, Perini Building Company.
Architectural Record reports that MGM states it would take “approximately 18 months to conduct test and come up with an approved, permitted design to fix the Harmon.” MGM feels that repairs would then take another two to three years. Perini contends that they could “provide stamped drawings detailing all necessary repairs within three months.” They attribute MGM’s desire to demolish the building as “buyer’s remorse.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Medical Center Builder Sues Contracting Agent, Citing Costly Delays
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Pennsylvania firm Bedwell Co. “has sued the Camden County Improvement Authority, saying it is owed $4.6 million for construction of [the Cooper Medical School of Rowan University]” in Camden, New Jersey, according to the Courier-Post. The Bedwell Co. alleges that its expenses exceeded fifty million, “but that it has been paid only $46 million.”
The lawsuit states, as quoted by the Courier-Post, “From its inception, the project was plagued by delays due to defects in the design document and other circumstances that were beyond Bedwell’s control.” Furthermore, there were “an abnormally large quantity of design changes, schedule disputes, schedule disruptions and work-activity interference.”
“Representatives of the CCIA and HDR could not be reached for comment Wednesday,” according to the Courier-Post. “Bedwell declined to comment on the allegations in the suit.”
Read the court decisionRead the full story...Reprinted courtesy of
Contractor Sues License Board
June 30, 2011 —
CDJ STAFFJudge Kendall J. Newman of the US District Court handed down a decision on June 24 on the case of Kent v California Department of Consumer Affairs. Mr. Kent, appearing as his own counsel, had brought the suit against the California Department of Consumer Affairs and the Contractors State Licensing Board after he was arrested in a sting operation and, as the plaintiff put it, “was absurdly arrested and uncooperatively detained for a time longer than necessary or allowed by law under the false pretense of contracting with out a license.” Mr. Kent’s alleged that Rick Lopez, one of the defendants, formed him to read allow from the California Business and Professions Code. He said he was later handcuffed and placed in an uncomfortable chair, “enduring physical pain and emotional agony.”
Although Kent was given a Notice to Appear, he alleged that a further defendant, Stuart Rind, “closed the plaintiff’s case marked citation A7773 without giving written notice to anyone.” As a result, the Placer County District Attorney’s Office had no record of his Notice to Appear.
Kent alleged that subsequently his firm was essentially shut down for two years and that he was prevented from “legally contracting or selling services for any other contractor or qualifying for any other licensed capacity governed by the CSLB.” After this, the CSLB suspended the license for his firm, DSI Construction. He was assessed a $1,500 fine, after which he claims he sent a letter to the CSLB demanding money damages. The judge noted that the letter was not included in the plaintiff’s Ninth Amended Complaint.
Judge Kendall recommended that the plaintiff’s Complaints be dismissed, although he did allow that sixth, and perhaps the eighth and ninth, could be amended with a tenth amended complaint.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Yet Another Reminder that Tort and Contract Don’t Mix
January 25, 2021 —
Christopher G. Hill - Construction Law MusingsI have stated on numerous occasions here at Musings that in Virginia, contract claims and tort claims (read fraud) don’t mix. A recent case from the Federal District Court for the Eastern District of Virginia presents another example of this principle. In Itility LLC v. The Staffing Resource Group, Judge Ellis of the Alexandria Division, considered ITility’s claims of fraud and breach of contract against SRG and one of its officers based upon SRG’s alleged violation of its duties under a teaming agreement. The claim by ITility was that TSRG provided false and misleading resumes and thus damaged ITility. SRG filed a Motion to Dismiss and the Court was therefore required to resolve the following issues: (1) whether plaintiff’s fraud claim is barred by Virginia’s “source of duty” rule; (2) whether plaintiff’s claim for tortious interference with a business expectancy is barred by SRG’s participation in the business expectancy, and (3) whether the teaming agreement between the parties bars plaintiff’s claims for consequential and punitive damages.
Reprinted courtesy of
The Law Office of Christopher G. Hill
Mr. Hill may be contacted at chrisghill@constructionlawva.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Insurer Not Required to Show Prejudice from an Insured’s Late Notice When the Parties Contract for a Specific Reporting Period
September 09, 2019 —
Christopher Raney - Gordon & Rees Insurance Coverage Law BlogThe Fifth Circuit Court of Appeals recently affirmed an order granting summary judgment in favor of the Firm’s insurer client on an issue of first impression in Texas. The issue before the trial court was whether, under Texas law, an insurer is required to demonstrate prejudice resulting from an insured’s failure to comply with an agreed term set in an endorsement to the parties’ insurance contract establishing a specific time limit for an insured to give the insurer notice of a claim.
The case involved alleged damage to an insured’s commercial property from a hailstorm. The insured did not report the alleged loss to its insurer until approximately 17 months after the date of loss. The insurer denied the claim based on a one-year notice requirement in a policy endorsement. The Texas Windstorm or Hail Loss Conditions Amendment Endorsement stated that:
In addition to your obligation to provide us with prompt notice of loss or damage, with respect to any claim where notice of the claim is reported to us more than one year after the reported date of loss or damage, this policy shall not provide coverage for such claims.
The insured sued the insurer in Houston federal court, alleging causes of action for breach of contract and violations of the Texas Insurance Code. The insured argued the insurer was required to show prejudice from the insured’s late notice; the insurer argued that a showing of prejudice was not required. The trial court recognized that this issue had not been decided by the Texas Supreme Court of the Fifth Circuit Court of Appeals.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Raney, Gordon & Rees Scully MansukhaniMr. Raney may be contacted at
craney@grsm.com
Contractor Definition Central to Coverage Dispute
July 22, 2024 —
Stacy R. Goldscher & Tracy M. Lewis - Wood Smith Henning & BermanHow do you define the term "contractor?" In the case of California Specialty Insulation Inc. v. Allied World Surplus Lines Insurance Company, No. B324805 (2024), the court ultimately honored the reasonable expectations of the insured and ordered that the insurer defend and indemnify in an underlying suit stemming from the policy. This case involves a commercial general liability insurance policy issued by Allied World Surplus Lines Insurance Company (Allied) to California Specialty Insulation, Inc. (CSI). The central issue is whether Allied World is obligated to defend and indemnify CSI against a negligence claim stemming from a construction site accident. The dispute hinges on the interpretation of a policy exclusion for bodily injury to employees of any "contractor," a term not defined in the policy.
Factual Background
In 2017 Air Control Systems. Inc. (Air Control) was contracted to perform improvement work at a Los Angeles building and subsequently hired CSI to install duct insulation. In 2019, Jason Standiford, and Air Control employee, filed a negligence lawsuit against CSI, alleging injuries from a 2017 incident where a CSI employee allegedly drove a scissor lift into a ladder Standiford was on, causing him to fall. CSI requested Allied World to defend it in the Standiford lawsuit. Initially, Allied World accepted the defense, but later withdrew, citing the Contractor Exclusion in the policy. CSI filed for declaratory relief, leading to cross-motions for summary judgment. The trial court ruled in favor of CSI, finding the term contractor ambiguous and construing it in CSI's favor. Allied World appealed the decision.
Reprinted courtesy of
Stacy R. Goldscher, Wood Smith Henning & Berman and
Tracy M. Lewis, Wood Smith Henning & Berman
Ms. Goldscher may be contacted at sgoldscher@wshblaw.com
Ms. Lewis may be contacted at tlewis@wshblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Apartment Building Damaged by Cable Installer’s Cherry Picker
November 20, 2013 —
CDJ STAFFThe owners of Oceana Apartments are suing Shentel Cable Co. and their subcontractors, CCI Systems, Inc. and Big Dog Communications, over the damage caused when a cherry picker rolled downhill and smacked into the building.
Kenneth Benn, an employee of Big Dog Communications, was installing utility wire when the cherry picker started moving. The suit alleges that Mr. Benn either failed to properly apply the brakes or immobilize the vehicle before staring work. Mr. Benn is also named as a defendant in the suit.
Read the court decisionRead the full story...Reprinted courtesy of
Out of the Black
May 30, 2022 —
John Drentlaw - Construction ExecutiveEven if you previously weren’t familiar with the term “black swan event,” you’ve likely become intimately familiar with what one looks like over the past two years. Coined by author Nassim Taleb in his book The Black Swan: The Impact of the Highly Improbable, the term refers to a rare, unpredictable event—perhaps, say, a pandemic—that has an extreme impact.
“Extreme” certainly seems to be an accurate description of the impact that the COVID-19 pandemic has had on the construction industry, at nearly every level. The Commercial Construction Index (CCI) fell from 74 to 56 during Q2 2020 and remained statistically unchanged through Q3 of that year. Recovery has been slow, with the CCI remaining eight points below pre-pandemic levels through the end of 2021. Prices for raw materials such as lumber and steel have been extremely volatile, reaching historic highs and dramatic lows. March and April of 2020 alone saw 1.1 million jobs disappear from the industry—roughly half as many jobs as were lost throughout the entire Great Recession (although many of these jobs have since returned).
While the industry has persevered through what should be the worst of these effects, many contractors and project owners are now wondering: How can we predict the next black swan event?
Reprinted courtesy of
John Drentlaw, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of