Late Progress Payments on Local Public Works Projects Are Not a Statutory Breach of Contract
May 10, 2022 —
Ted Senet & Christopher Trembley - Gibbs GidenCalifornia local public agencies and their contractors should take note of a recent appellate decision pertaining to late progress payments on public works projects. In Clark Bros., Inc. v. North Edwards Water Dist., 2022 Cal. App. LEXIS 331, filed on April 22, 2022, the Court of Appeal for the Fourth Appellate District held that a local agency’s late progress payments to a general contractor did not constitute breach of contract under the prompt payment penalty statute, Public Contract Code § 20104.50. Notwithstanding this holding, the contractor recovered damages, interest, fees, and costs in excess of its contract amount.
In 2013, the North Edwards Water District awarded a $6.2 million contract to Clark Bros., Inc. to construct a water treatment facility. The District’s water contained excessive levels of arsenic, and the project was sponsored by the State of California with funds earmarked to provide safe drinking water. The State agreed to disburse funds to the District during construction upon the State’s review and approval of the contractor’s progress payment applications. The contract required completion of the work within one year following the District’s issuance of a notice to proceed to the contractor.
As a result of factors arguably outside the control of the contractor, including unforeseen site conditions and the failure of the District’s equipment supplier to meet delivery deadlines, the project was significantly delayed beyond the deadline for completion. The District nonetheless terminated the contractor, which in turn filed suit against the District and the State. The contractor asserted claims for breach of contract, including breach of contract for the District’s failure to pay the contractor’s progress payment applications within the time specified under Public Contract Code § 20104.50. Subsection (b) of the statute provides:
Any local agency which fails to make any progress payment within 30 days after receipt of an undisputed and properly submitted payment request from a contractor on a construction contract shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
Reprinted courtesy of
Ted Senet, Gibbs Giden and
Christopher Trembley, Gibbs Giden
Mr. Senet may be contacted at tsenet@gibbsgiden.com
Mr. Trembley may be contacted at Ctrembley@gibbsgiden.com
Read the court decisionRead the full story...Reprinted courtesy of
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
John Boyden, Alison Kertis Named “Top Rank Attorneys” by Nevada Business Magazine
July 25, 2022 —
John Boyden & Alison Kertis - Lewis BrisboisReno, Nev. (June 16, 2022) – Reno Partner John Boyden and Associate Alison Kertis were recently named to Nevada Business Magazine's 2022 list of "Top Rank Attorneys." Formerly known as "Legal Elite," this annual list represents the top talent in the legal industry across the State of Nevada.
According to Nevada Business Magazine, thousands of attorneys are nominated for the list and then scored based on the number and type of votes they receive, with votes from outside an attorney's firm receiving more weight. Finally, before being added to the list, the attorneys, and the votes they receive, go through several levels of verification and scrutiny, with each ballot individually reviewed for eligibility and every voting attorney verified with the State Bar of Nevada. The magazine has published this list for the past 15 years.
Reprinted courtesy of
John Boyden, Lewis Brisbois and
Alison Kertis, Lewis Brisbois
Mr. Boyden may be contacted at John.Boyden@lewisbrisbois.com
Ms. Kertis may be contacted at Alison.Kertis@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Did You Get a Notice of Mechanic’s Lien after Project Completion? Don’t Panic!
October 20, 2016 —
Christopher G. Hill – Construction Law MusingsSo, you own a piece of property. You decided to have some work done and after what you thought was proper due diligence, you hire a general contractor to build a great office building on the property. Your architect designs the space, you sign the construction contract for a price you find fair and that the bank approves. Construction starts and with a few minor hiccups, a couple of written changes and one minor but slightly annoying change required by the local building inspector, completes relatively on schedule. You write the final check to the general contractor for its final draw and start the process of leasing the space out. All is right with the world as best you can tell.
A month later, you walk to your mailbox and lo and behold, you have a certified mailing containing a notice that the plumbing subcontractor has recorded a mechanic’s lien on your property. After counting to 10 to let the various emotions pass, you call the general contractor to see what is going on. You’re told that there is a dispute regarding a change order about which you knew nothing and that the general contractor feels it is in the right and should not have to pay the money represented in the memorandum of lien so it won’t be paying the subcontractor unless and until it is told to do so by a court or an arbitrator.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Congratulations to BWB&O for Ranking in The U.S. News – Best Lawyers ® as “Best Law Firms”!
November 19, 2021 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is proud to announce the firm has once again been regionally ranked by The U.S. News – Best Lawyers® with a “Best Law Firms” recognition in two practice areas, Family Law and Commercial Litigation. BWB&O is also honored to be included among many elite and extremely impressive groups of law firms! To read the Twelfth Edition of the “Best Law Firms” rankings, please click here.
Best Lawyers has a prominent reputation for being the most respected peer-review publication in the history of the legal profession. The “Best Law Firms” rankings are based on a rigorous evaluation process, which includes a combination of client feedback, information provided on the Law Firm Survey, the Law Firm Leaders Survey, and Best Lawyers peer review.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
2025 Construction Law Update
January 07, 2025 —
Garret Murai - California Construction Law BlogIt’s that time of year again.
The second half of the 2023-2024 legislative session saw the introduction of 2,124 bills, of which, 1418 were signed into law. Among the bills signed by the governor impacting contractors is an increase in the small work licensing exemption for $500 to $1,000, the licensing of Indian tribes by the CSLB, and a number of project-specific bills, as is typical, related to project-specific alternative project delivery methods.
Wishing you and yours a great 2025!
Licensing
AB 2622 – Increases the small work licensing exemption from $500 to $1,000 provided that the work: (1) does not require a building permit; and (2) does not involve the employment of others to perform or assist in the work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Toolbox Talk Series Recap – Considerations for Optimizing Dispute Resolution Clauses
June 05, 2023 —
Michael Filbin - The Dispute ResolverIn the April 27, 2023 edition of Division 1's Toolbox Talk Series moderated by Manuel del Valle, Sergio Andre Laclau (Partner at Mello Torres) and Liza Akins (Senior Assistant GC and Division Counsel at ARCO Design/Build) offered the following strategies for drafting effective ADR clauses in construction contracts:
- Define the ADR process for various types of disputes.
Not all disputes on a construction project are the same, and the parties can tailor the ADR process to different situations. For example, the parties could choose to arbitrate complex disputes and resolve minor claims through mediation. Differentiating the ADR process between complex and minor disputes can save parties time and money.
While Liza prefers arbitration for complex claims because you can get a quick and final decision from an arbitrator experienced with construction disputes, she noted that arbitration costs can add up quickly. Therefore, if the dollar amount in dispute is relatively small, arbitration may not make sense financially. Mediation tends to be a comparatively cheaper and faster option.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Filbin, Cozen O'ConnorMr. Filbin may be contacted at
mfilbin@cozen.com
A UK Bridge That Is a Lesson on How to Build Infrastructure
November 15, 2017 —
Cameron J. Bell - Engineering News-RecordThis country’s infrastructure—bridges, airports, dams and levees—needs wide-scale repair and renewal. The United Kingdom’s new Queensferry Crossing bridge, connecting Edinburgh to Fife in Scotland, sets a new standard for how to do it. The result speaks for itself: The Queensferry Crossing, a three-tower, 1.7-mile-long cable-stayed bridge, debuted in early September well within budget and a manageable eight-month time delay—a rare occurrence among bridges. According to research at the University of Oxford’s Saïd Business School, nine out of 10 fixed links (bridges and tunnels) suffer an average cost overrun of 34% and a time delay of roughly two years.
Read the court decisionRead the full story...Reprinted courtesy of
Cameron J. Bell, ENR ENR may be contacted at
ENR.com@bnpmedia.com