Can a Contractor be Liable to Second Buyers of Homes for Construction Defects?
November 05, 2014 —
Craig Martin - Construction Contractor AdvisorWhether a contractor will be liable to a second purchaser, even though the contractor never contracted with the second purchaser, varies state to state. The Pennsylvania Supreme Court, in Conway v. The Cutler Group, is the latest court to rule that a subsequent purchaser lacks privity and cannot pursue an action against the builder.
In that case, the Conways purchased a home from the original owner. After living in the home for about two years, the Conways discovered water leaking around the windows. The Conways sued the builder, alleging breach of the implied warranty of habitability.
The builder defended the claim, asserting that it had not contracted with the Conways and thus had not provided any warranties to the Conways. The trial court agreed and dismissed the claim. The first level of appellate court reversed the trial court, holding that the warranty of habitability was intended to level the playing field between the builder and purchaser of a home and it should be extended to subsequent purchasers. The Pennsylvania Supreme Court disagreed and refused to extend any warranties to subsequent purchasers.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
HB 20-1046 - Private Retainage Reform - Postponed Indefinitely
May 04, 2020 —
David M. McLain – Colorado Construction LitigationOn Tuesday, February 18th, the Colorado House Business Affairs & Labor Committee voted 10-0 to postpone indefinitely House Bill 1046. If it had been enacted, HB 1046 would have required, for all for all construction contracts of at least $150,000:
- A property owner to make partial payments to the contractor of any amount due under the contract at the end of each calendar month or as soon as practicable after the end of the month;
- A property owner to pay the contractor at least 95% of the value of satisfactorily completed work;
- A property owner to pay the withheld percentage within 60 days after the contract is completed satisfactorily;
- A contractor to pay a subcontractor for work performed under a subcontract within 30 calendar days after receiving payment for the work, not including a withheld percentage not to exceed 5%;
- A subcontractor to pay any supplier, subcontractor, or laborer who provided goods, materials, labor, or equipment to the subcontractor within 30 calendar days after receiving payment under the subcontract; and
- A subcontractor to submit to the contractor a list of the suppliers, sub-subcontractors, and laborers who provided goods, materials, labor, or equipment to the subcontractor for the work.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Lennar Profit Tops Estimates as Home Prices Increase
March 26, 2014 —
John Gittelsohn – BloombergLennar Corp. (LEN), the biggest U.S. homebuilder by market value, reported a fiscal first-quarter profit that beat analysts’ estimates as the company sold more homes at increased prices.
Net income climbed to $78.1 million, or 35 cents a share, in the three months through February, from $57.5 million, or 26 cents, a year earlier, the Miami-based company said in a statement today. Analysts expected earnings of 28 cents a share, the average of 17 estimates compiled by Bloomberg.
Publicly traded builders have been increasing prices to take advantage of a tight supply of new and existing homes while using their economies of scale to reduce costs and widen profit margins. Lennar’s profit, deliveries and orders grew even as inclement weather threatened home sales in much of the U.S. during the quarter, according to Drew Reading, a Bloomberg Industries analyst.
“Lennar followed KB Home (KBH) in reporting order trends indicating a strong start to the spring selling season,” Reading said in a note after the earnings were released.
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, BloombergMr. Gittelson may be contacted at
johngitt@bloomberg.net
Design Professionals Owe a Duty of Care to Homeowners
July 09, 2014 —
Stephen A. Sunseri - Gatzke Dillon & Ballance LLPToday, the California Supreme Court, in Beacon Residential Community Association v. Skidmore, Owings & Merrill LLP (Jul. 3, 2014, S208173) __Cal.4th__ [2014 WL 2988058], held that architects owe a duty of care to future homeowners of residential buildings, particularly if they act as principal architects on a project, and are not subordinate to any other design professional. Until now, design professionals were rarely held liable, if at all, for third-party claims for design deficiencies.
In Beacon, architectural and engineering firms provided sole design services for The Beacon residential condominium project, a 595 unit project located in San Francisco. The condominiums were initially leased after construction, but were eventually sold to individual owners. The design firms claimed their role was limited to only providing design recommendations to the project's owner, who ultimately controlled and directed which design elements to construct. Not long after completion of the project, the homeowners' association sued the design firms (among others) for construction defects and damages related to alleged water infiltration, inadequate fire separations, structural cracks, and other purported safety hazards. The claims included allegations under SB 800 (the "Right to Repair Act," Civil Code §895, et seq.) and common law negligence theories.
The design firms demurred to the complaint, which the trial court sustained. On appeal, however, the Court of Appeal reversed the trial court's ruling, concluding that the design firms owed a duty of care to third parties. The Supreme Court affirmed.
Historically, liability for deficient goods and services hinged on whether there is a contractual relationship between a buyer and seller. However, the Supreme Court recognized that in certain circumstances a contractual relationship is not required. In its ruling, the Supreme Court relied on fifty year old precedent, Biankanja v. Irving (1958) 49 Cal.2d 647. In Biankanja, the California Supreme Court outlined several factors to determine whether a duty of care is owed to non-contracting third parties. Although Biankanja analyzes many factors, emphasis was placed placed on whether a purported harm was foreseeable by a defendant's conduct and how close of a connection there is between that conduct and an injury.
Here, the Court recognized that even though the design firms did not actually build the project, they did conduct weekly inspections, monitored contractor compliance, altered design elements when issues arose, and advised the owners of any nonconforming work. In applying the Biankanja factors to these circumstances, the Supreme Court determined the homeowners were intended beneficiaries of the design work and the design firms' primary role in the project bore a close connection to the alleged injuries. As a result, the Supreme Court held that the allegations in the complaint were sufficient and, if proven, establishes the defendants owed a duty of care to the homeowners' association.
Interestingly, the Supreme Court sidestepped the issue of whether SB 800 was intended to exclusively capture design defects in its scope, even though the Court indicated it may. Nevertheless, the Supreme Court's ruling is significant. The case will affect how design professionals allocate risk on future residential projects, perhaps by raising design prices or insuring around the liability exposure. The likely outcome, however, is that design professionals are now targets in construction defect lawsuits.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen A. Sunseri, Gatzke Dillon & Ballance LLPMr. Sunseri may be contacted at
ssunseri@gdandb.com
Maximizing Contractual Indemnity Rights: Problems with Common Law
December 02, 2015 —
William Kennedy – White and Williams LLPAt its core, the concept of tort law is simple: you pay for the damages you negligently cause. In reality, tort law can sometimes require a party to pay far more than just its share of causal damages. Tort law can even require a party to pay when it was not actually negligent, but rather is related to the actually-negligent actor.
The vagaries of tort law suggest that the allocation of the “risk of loss” is a vital detail in any contract. Without effective contractual provisions, parties to a contract may find that common law tort principles yield harsh or unexpected results. Properly written contractual provisions can define which party bears the risk of which losses. Both the party receiving the financial protection (the Indemnitee) and the party providing the protection (the Indemnitor) have an interest in obtaining insurance to cover the risk that is being borne.
Read the court decisionRead the full story...Reprinted courtesy of
William Kennedy, White and Williams LLPMr. Kennedy may be contacted at
kennedyw@whiteandwilliams.com
COVID-19 and Mutual Responsibility Clauses
June 01, 2020 —
Joseph M. Leone - ConsensusDocsAs everyone knows, there is a tremendous amount of uncertainty in the construction industry due to the COVID-19 pandemic. Schedules, productivity, safety processes, and seemingly everything else are being affected. In these difficult times, most contractors are making every effort to work together to solve the problems caused by COVID-19. But what happens when differences arise between project owners, contractors, and subcontractors as to the effect of COVID-19 on a project? One party may want to continue pushing the schedule, others may want to slow down, or, more likely, not be able to keep up with the original schedule because of some reason related to COVID-19. As between a prime contractor and a subcontractor, a mutual responsibility clause can provide some clarity or, unfortunately, depending on how the subcontract is written, confusion.
Almost all subcontracts have a clause which flows down the prime contractor’s obligations on a project to the subcontractor as applicable to the subcontractor’s work. Known as “flow-down” clauses, this clause works in one direction; obligations of the prime contractor “flow-down” to the Subcontractor. A mutual responsibility clause, in essence, works in both directions. The subcontractor is required to perform its obligations consistent with the prime contractor’s obligations to the owner and the subcontractor is granted the same rights against the prime contractor which the prime contractor has against the owner. Obligations flow down and rights flow up. The rights and obligations flowing through the prime contractor include, the obligation to perform the work in accordance with the plans and specifications, the obligation to meet the schedule constraints in the prime agreement, and the right to extensions of time and change orders to the extent the prime contractor obtains the same.
Read the court decisionRead the full story...Reprinted courtesy of
Joseph M. Leone, Drewry Simmons Vornehm, LLP Mr. Leone may be contacted at
jleone@dsvlaw.com
Wisconsin Court Applies the Economic Loss Doctrine to Bar Negligence Claims for Purely Economic Losses
August 17, 2020 —
Rahul Gogineni - The Subrogation StrategistIn Mech. Inc. v. Venture Elec. Contrs., Inc., No. 2018AP2380, 2020 Wisc. App. LEXIS 170, the Court of Appeals of Wisconsin, District Two, considered whether a party may bring a negligence claim for purely economic damages. In upholding the lower court, the appellate court found that a party is barred by the Economic Loss Doctrine from bringing a negligence claim for purely economic damages.
Both parties involved in this action were subcontractors on a building project at the Great Lakes Research Facility for the University of Wisconsin-Milwaukee. As a result of Venture Electrical Contractors, Inc. (Venture) not paying for requested work, Mechanical, Inc. (Mechanical) sued Venture for $11,961.31. Venture, in turn, countersued in negligence for $1.1 million for costs incurred due to delays and untimely performance. Mechanical sought dismissal of the negligence claim based upon the Economic Loss Doctrine. Finding that the Economic Loss Doctrine applies to purely economic losses, the trial court dismissed Venture’s negligence claim. Venture appealed to the Court of Appeals of Wisconsin.
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com
Arizona Court of Appeals Awards Attorneys’ Fees in Quiet-Title Action
September 20, 2017 —
Kevin Walton - Snell & Wilmer Real Estate Litigation BlogIn Arizona, a party successfully quieting title to property may recover its attorneys’ fees if it satisfies three requirements: (1) the party requests a quitclaim deed from the party adversely claiming title twenty days before bringing the quiet-title action; (2) the party tenders five dollars for the execution and delivery of the deed; and (3) the adverse party fails to comply. Ariz. Rev. Stat. § 12-1103(B). Recently, in McCleary v. Tripodi, No. 2 CA-CV 2016-0145, 2017 WL 3723472 (Ariz. Ct. App. Aug. 29, 2017), the Arizona Court of Appeals awarded attorneys’ fees to the prevailing party under this statute.
In McCleary v. Tripodi, Mrs. Tripodi, who became the administrator of her husband’s estate upon his death, wrongfully recorded three deeds purporting to transfer property to herself. After unsuccessfully attempting to get Mrs. Tripodi to quitclaim the property, the plaintiffs filed a quiet-title action. The trial court agreed that the plaintiffs were the legal and rightful owners, granted summary judgment in plaintiffs’ favor, and awarded attorneys’ fees to the plaintiffs.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin Walton, Snell & Wilmer