Indemnification Provisions Do Not Create Reciprocal Attorney’s Fees Provisions
November 21, 2018 —
CDJ STAFFIn a good, recent decision, the Eleventh Circuit in International Fidelity Insurance Co. v. Americabe-Moriarity, JV, 2018 WL 5306683 (11th Cir. 2018), held that Florida Statute s. 57.105(7) cannot be used to shift attorney’s fees in a contractual indemnification clause in a dispute between a general contractor and subcontractor’s performance bond surety, when the dispute does not involve an actual indemnification claim stemming from a third-party.
In this case, a prime contractor terminated a subcontractor and looked to the subcontractor’s performance bond surety to pay for the completion work. The subcontractor had a standard AIA A312 performance bond that requires the prime contractor to comply with the terms of the bond, as well as the incorporated subcontract, in order to trigger the surety’s obligations under the bond. The surety filed an action for declaratory relief against the prime contractor arguing that the prime contractor breached the terms of the performance bond through non-compliance thereby discharging the surety’s obligations. The trial court agreed and the surety moved for attorney’s fees.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Defect Claims Not Covered
May 10, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court found that the insured's negligent acts causing damage to only the structure of the home it built were not covered under the CGL policy. Westfield Ins. Co. v. Zaremba Builders II LLC, 2022 U.S. Dist. LEXIS 36189 (N.D. Ill. March 2, 2022).
Zaremba contracted to build a house for the Vrdolyak Trust. After completion of the home, the occupants found many problems, including painting defects such as bubbling and peeling, leaving the basement full of water for months, causing damage to ductwork, framing and piping in the house, etc. The Trust sued and Westfield denied a defense.
Westfield filed a declaratory judgment action for a ruling that it had no duty to defend or indemnify. On Westfield's motion for summary judgment, the court determined there was no property damage. Property damage included "physical injury to tangible property." When the alleged damage occurred in the course of a construction project, tangible property had to be property outside the scope of the contract for project.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Montana Trial Court Holds That Youths Have Standing to Bring Constitutional Claims Against State Government For Alleged Climate Change-Related Harms
September 18, 2023 —
Paul A. Briganti & Julia Castanzo - White and Williams LLPOn August 14, 2023, in a “landmark” ruling, a Montana state court held that youth plaintiffs had standing to assert constitutional claims against the State of Montana, its governor and state agencies for “ignoring” the impact of greenhouse gas (GHG) emissions on climate change. Held v. State of Montana, Cause No. CDV-020-307 (1st Judicial Dist. Ct., Lewis & Clark Cty., Mt.). Agreeing with the plaintiffs, the court concluded that a limitation in the Montana Environmental Policy Act (MEPA), which prohibited the state from considering climate impacts when issuing permits for energy projects, violated the plaintiffs’ right under the state constitution to a “clean and healthful environment.”
MEPA, enacted in 1971, states that its purposes include “provid[ing] for the adequate review of state actions in order to ensure that . . . environmental attributes are fully considered by the legislature in enacting laws to fulfill constitutional obligations . . . .” In 2011, the legislature amended the statute to curtail the scope of environmental reviews. Under the so-called MEPA limitation, Montana agencies cannot consider “an evaluation of greenhouse gas emissions and corresponding impacts to the climate in the state or beyond the state’s borders.” Mont. Code Ann. § 75-1-201(2)(a). In 2023, the legislature added a provision that eliminated equitable remedies (i.e., the ability to “vacate, void, or delay a lease, permit, license, certificate, authorization, or other entitlement or authority”) for litigants who “claim that [an] environmental review is inadequate based in whole or in part upon greenhouse gas emissions and impacts to the climate in Montana or beyond Montana’s borders . . . .” Id. § 75-1-201(6)(a)(ii).
Reprinted courtesy of
Paul A. Briganti, White and Williams LLP and
Julia Castanzo, White and Williams LLP
Mr. Briganti may be contacted at brigantip@whiteandwilliams.com
Ms. Castanzo may be contacted at castanzoj@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Final Thoughts on New Pay If Paid Legislation in VA
August 15, 2022 —
Christopher G. Hill - Construction Law MusingsThis past General Assembly session, and after a governor’s amendment and with the convening of a study group, a new statute banning so-called “pay-if-paid” clauses from enforcement was passed. Some of the key features of the legislation are as follows:
It does not take effect until January 1, 2023, and,
For those construction contracts in which there is at least one general contractor and one subcontractor:
- It requires payment within 60 days of receipt of an invoice following the satisfactory performance of the work or within 7 days of receipt of payment by the Owner
- It allows for retainage
- It allows the higher-tier contractor to withhold money for improper performance
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
When Business is Personal: Negligent and Intentional Interference Claims
October 24, 2023 —
Kathryne Baldwin & Jose L. Parra - Wilke FleuryThe nature of business is personal. Changes in personnel, project outlines, or business models cost businesses time and money to bring about, ward against, or stop. Any individual involved in business will likely have seen claims for interference with relationships, either prospective or contractual. But, what do those claims really mean and how viable are they in a capitalist society where free markets are held in such high esteem?
Defendants in lawsuits will typically see these claims pleaded as one of three major categories: intentional interference with prospective economic advantage, intentional interference with contractual relations or contract, or negligent interference with prospective economic advantage. As the name would suggest, the first two are more concrete and require a showing that the bad actor was aware of the existence of a contract or relationship and took affirmative steps to interfere with that relationship. The latter is more nebulous and looks at business relationships that were likely to occur and are based on a “should have known” standard.
Reprinted courtesy of
Kathryne E. Baldwin, Wilke Fleury and
José L. Parra, Wilke Fleury
Ms. Baldwin may be contacted at kbaldwin@wilkefleury.com
Mr. Parra may be contacted at jparra@wilkefleury.com
Read the court decisionRead the full story...Reprinted courtesy of
What’s in a Name? Trademarks and Construction
April 25, 2022 —
Carol Wilhelm and J.P. Vogel - Construction ExecutiveEvery company, no matter the industry, relies on its name and reputation to develop customers and generate revenue. Think about the brands that dominate American culture such as Nike, Wal-Mart, Amazon or McDonald’s, then imagine those businesses without the ability to adequately protect their names, slogans and logos. No doubt the vultures would circle and brand power would most likely become short lived or otherwise diluted to the point of non-existence. The construction industry is not exempt, and the industry leaders benefit from identifiable names and logos, built over years of reputation and brand building. While the tools necessary to protect your company’s brand exist at the state and federal level, many business owners or leaders are unfamiliar with the trademark process and unaware of the consequences of not utilizing those tools.
Trademark Registration
Trademarks are “concise and unequivocal identifiers” that provide potential customers with essential information about your business. With a single word, tagline, logo, color—essentially anything that can carry meaning—potential customers learn to associate particular product or service characteristics and expected quality level with a particular source. That is, your mark is the way that consumers connect your expertise and reputation to your business and nobody else’s. It serves a critical role in reducing consumer search costs and capturing your hard-earned business opportunities.
Reprinted courtesy of
Carol Wilhelm and J.P. Vogel, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Vogel may be contacted at jpvogel@grayreed.com
Ms. Wilhelm may be contacted at cwilhelm@grayreed.com
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Rejects Insurers' Bid for Horizontal Exhaustion Rule in New Montrose Decision
April 20, 2020 —
J. Kelby Van Patten - Payne & FearsIn Montrose Chemical Corp. v. Superior Court, 2020 WL 1671560 (April 6, 2020), the California Supreme Court held that, when one primary policy exhausts in a continuing injury claim, the excess insurer sitting above that policy must drop down and provide coverage for the entire claim (up to its policy limits), even if primary policies in other years remain unexhausted.
Montrose was sued for environmental contamination between 1947 and 1982. In many years, Montrose had primary insurance as well as multiple layers of excess coverage. Montrose’s excess insurers argued for a “horizontal exhaustion” rule, which would have required that all implicated primary policies exhaust before any excess insurers provide coverage. The California Supreme Court rejected the insurers’ arguments and found that Montrose was entitled to coverage from an excess insurer once the specific primary policy sitting below that insurer was exhausted. The Supreme Court also confirmed that, under California’s “all sums” rule, each excess insurer must provide coverage for the entire amount of the loss (up to its policy limits).
Read the court decisionRead the full story...Reprinted courtesy of
J. Kelby Van Patten, Payne & FearsMr. Van Patten may be contacted at
kvp@paynefears.com
Contractor Convicted of Additional Fraud
November 18, 2011 —
CDJ STAFFA Pennsylvania contractor in prison for fraud has been convicted with insurance fraud. The York Daily Record reports that Steven D. Gebhart was already in jail for fraud for about $350,000 for work he either failed to finish or even start or by using substandard materials and practices when he was convicted of insurance fraud. Gebbert’s offices were destroyed in a fire that was later determined to be arson. He was not charged with this, but instead for overestimating his losses to the insurance company. Sentencing for the fraud charge will be on December 21.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of