No Rest for the Weary: Project Completion Is the Beginning of Litigation
June 18, 2019 —
Albert Li & Bob Fitzsimmons - Construction ExecutiveIn today’s environment, most construction projects end up in some form of litigation. Construction is full-time employment for lawyers – from contract negotiation to project management, lien and payment issues. Years after project completion, a company still can face construction defect litigation and be served with a Notice of Opportunity to Repair, which in most states is now codified into statute. This is the beginning of what most likely will become a lawsuit, involving many of the subcontractors.
Watch Out for the Construction Contract Blame Game
The first phase of post construction litigation involves the review of contract and insurance policy language in an attempt to transfer responsibility in the litigation to other parties.
Before construction began, contract negotiation focused on budget and timeline. In the post-construction phase, two less noticed provisions of the contract are critical – indemnity and insurance.
Reprinted courtesy of
Albert Li & Bob Fitzsimmons, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Fitzsimmons may be contacted at rfitzsimmons@rumberger.com
Mr. Li may be contacted at ali@rumberger.com
Read the court decisionRead the full story...Reprinted courtesy of
Harlem Developers Reach Deal with Attorney General
February 25, 2014 —
Beverley BevenFlorez-CDJ STAFFJoseph Scarpinito and Shiraz Sanjana, developers of the Mirada condominium in Harlem, New York can avoid a contempt charge from state Attorney General Eric Schneiderman, “if they make the required repairs and obtain a permanent certificate of occupancy at the property,” according to The Real Deal.
Scarpinito and Sanjana “agreed to deposit $200,000 into an escrow account and make repairs to stop flooding and other defects at the 161 East 110th Street condo, which are required to obtain a certificate of occupancy from the city Department of Buildings.”
Last December, the Attorney General “filed suit against the developers, alleging they submitted false filings to his office in claiming that Scarpinito’s 83-year-old mother was the actual developer of the 68-unit condo.” Furthermore, the condo board lawyers submitted a complaint to Schneiderman “detailing extensive defects in the building, including water leaks entering the building from the roof and façade.”
The developers have been ordered “to submit weekly reports to the AG’s office detailing progress on the repairs and obtaining the certificate of occupancy.”
Read the court decisionRead the full story...Reprinted courtesy of
Make Your Business Great Again: Steven Cvitanovic Authors Construction Today Article
April 20, 2017 —
Steven M. Cvitanovic - Haight Brown & Bonesteel LLPThere is a lot of uncertainty regarding how President Trump’s immigration and trade policies will affect the construction industry. In his Construction Today article, Partner Steven Cvitanovic discusses how businesses can remain competitive and profitable during this period of uncertainty, including updating contract documents, recruiting and retaining employees, and increasing cybersecurity efforts.
“If you do not know when your contract documents were last updated, it’s probably been too long,” writes Cvitanovic. “Unlike wine, contract documents only get worse with age.” Cvitanovic advises teams to sit down together and review contracts to see if they still meet the firm’s needs.
Read the court decisionRead the full story...Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLPMr. Cvitanovic may be contacted at
scvitanovic@hbblaw.com
Ex-Engineered Products Firm Executive Convicted of Bid Rigging
March 06, 2022 —
James Leggate - Engineering News-RecordA federal jury convicted a former executive at an engineered construction products firm Feb. 1 for his role in a bid-rigging scheme that targeted the North Carolina Dept. of Transportation.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Update: Lawyers Can Be Bound to Confidentiality Provision in Settlement Agreement
January 13, 2020 —
Danielle Ward, Esq. - Balestreri Potocki & HolmesIn July 2019, the California Supreme Court ruled that an attorney’s signature under the often-used phrase “approved as to form and content” does not preclude a finding that the attorney could be bound to the terms of a settlement agreement. (Monster Energy Co. v. Schechter (2019) 7 Cal.5th 781.) This decision marks a reversal of the Fourth District Court of Appeal’s 2018 ruling that approval of a contract is not tantamount to an agreement to be bound by that contract.
The underlying action stemmed out of a wrongful death suit by Wendy Crossland and Richard Fournier, parents of the decedent, against Monster Energy Company. The parties negotiated a settlement, a critical of element of which was a confidentiality provision aimed at keeping the the settlement secret.
The confidentiality provision prohibited plaintiffs and their counsel of record from disclosing both the existence of the settlement, or the terms thereof, to any person, entity, or publication, including the legal website Lawyers & Settlements. The attorneys signed the agreement under the phrase “approved as to form and content.”
Shortly after the settlement agreement was executed, the Plaintiffs’ attorney Bruce Schechter disclosed his clients’ settlement with Monster in an interview with Lawyers & Settlements. Monster filed suit against Mr. Schechter for breach of contract, among other causes of action. Mr. Schechter challenged the lawsuit with a SLAPP motion, essentially arguing that the lawsuit was meritless and merely an attempt to thwart freedom of speech.
The trial court denied Mr. Schechter’s motion as to the breach of contract cause of action finding that the settlement clearly contemplated that the attorneys were subjected to the terms of the agreement, and Schechter’s claim that he was not a party because he merely approved as to form and content was “beyond reason.”
The Fourth District Court of Appeal reversed, concluding that Mr. Schechter was not a party to the agreement by virtue of his signature approving the form and content, and the Plaintiffs had no authority to bind their attorney to the terms of the agreement. The Court of Appeal found that by affixing his signature to the agreement Mr. Schechter was merely manifesting his “professional thumbs up” in line with legal industry’s customary understanding.
In its reversal, the California Supreme Court did not disturb the legal community’s understanding of the phrase “approved as to form and content.” Rather, the Court concluded that an attorney’s signature under that often-used phrase does not preclude as a matter of law that the attorney intended to be bound by the agreement. The entire agreement, including the substantive provisions, need to be examined to determine the attorney’s intent in affixing his/her signature to the agreement.
Turning to the Crossland/Fournier Monster settlement agreement, the Court was unpersuaded by Mr. Schechter’s argument that he was not bound to the agreement because counsel was not included in the definition of “party”. The Court stated that it’s the substance of the agreement that determines whether counsel is a party to the contract, as opposed to a party to the lawsuit.
The Court was persuaded, in part, by the important role that confidentiality plays in brokering settlements. It noted that public disclosure of private settlements would serve to “chill” parties’ ability to resolve matters short of trial, and there was little doubt that confidentiality was an important term of the Crossland/Fournier Monster settlement. In concluding that Monster had met its burden to defeat an anti-SLAPP motion, the Court pointed to the numerous references to counsel in the substantive provisions of the agreement which a trier of fact could conclude bound Mr. Schechter to the confidentiality terms.
Danielle Ward has concentrated her law practice on defending developer, general contractor, and subcontractor clients in a variety of construction matters. She has been an attorney with Balestreri Potocki & Holmes since 2010 and can be reached at dward@bph-law.com.
Read the court decisionRead the full story...Reprinted courtesy of
World Cup May Pull Out of Brazil because of Construction Delays
January 28, 2014 —
Beverley BevenFlorez-CDJ STAFFBack in October of last year, CNN reported that a judge suspended construction at one of the stadiums being built for this summer’s World Cup in Brazil. The judge stated that the dangers for construction workers included "being buried, run over, falling from heights and being hit by material, among other serious risks,” according to CNN.
Recently, the Los Angeles Times reported that FIFA is threatening to pull out of Brazil because of construction delays: “We cannot organize a match without a stadium,” Jerome Valcke, FIFA’s secretary general, as quoted in the Los Angeles Times. “This has reached a critical point.”
The deadline for completion of the 12 World Cup stadiums was January 1st, but various delays—including “fatal construction accidents at stadiums in Sao Paulo, Brasilia, and Manaus” as well as worker walk offs over pay—forced FIFA to “relax” the deadline.
Read the full story at CNN...
Read the full story at the Los Angeles Times... Read the court decisionRead the full story...Reprinted courtesy of
Chambers USA 2021 Recognizes Five Partners and Two Practices at Lewis Brisbois
June 07, 2021 —
Lewis BrisboisFive Lewis Brisbois partners and two Lewis Brisbois practices were recently ranked by Chambers in its 2021 USA rankings list.
Kansas City and Wichita Managing Partner Alan L. Rupe and Phoenix Managing Partner Carl F. Mariano were both ranked Band 1 for “Labor & Employment – Kansas” and “Insurance – Arizona,” respectively, while Minneapolis Partner Tina A. Syring was ranked Band 4 for “Labor & Employment – Minnesota,” and Washington D.C. Managing Partner Jane C. Luxton and Partner Karen C. Bennett were ranked Band 5 for “Environment – District of Columbia.”
Significantly, Chambers also ranked Lewis Brisbois’ Kansas Labor & Employment Practice Band 2 and the firm’s Washington D.C. Environmental Practice Band 4.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
“License and Registration, Please.” The Big Risk of Getting Busted for Working without a Proper Contractor’s License
July 25, 2021 —
Christopher A. Henry & Mia Hughes - ConsensusDocsThe need for contractors to maintain the proper contracting license may seem like a mundane, clerical detail, and generally is just that. If, however, the contractor ignores or mishandles paperwork and the proper license is not in hand, licensing may go from a mundane, clerical detail to a financial catastrophe. An unlicensed contractor may be barred from asserting claims or collecting payments for work already performed; the contractor may even be required to return payments for unlicensed work performed.
A recent case in Georgia, a state that had no state-wide general contractor’s license requirement in effect until 2008 illustrates the risk of unlicensed work.[1] In Saks Management and Associates, LLC v. Sung General Contracting, Inc.,[2] the court ruled that without a license the general contractor did not have the right to enforce a contract. The contractor’s claims for payment failed, and the mundane, clerical error led a major financial loss. This disastrous result for the Georgia contractor is far from an outlier, and is a real risk in many states.
Reprinted courtesy of
Christopher A. Henry, Jones Walker LLP and
Mia Hughes, Jones Walker LLP
Mr. Henry may be contacted at chenry@joneswalker.com