Employee or Independent Contractor? New Administrator’s Interpretation Issued by Department of Labor Provides Guidance
August 04, 2015 —
Tanya Salgado – White and Williams LLPThe question of whether a worker should be classified as an independent contractor or an employee is fraught with confusion and misunderstanding for many businesses. Compounding the problem is the fact that there are a number of different tests used to determine employee status, which vary by jurisdiction and by the particular law in question. For example, the Internal Revenue Service uses the common law rules which focus on the degree of control and independence exercised by the worker. In contrast, the United States Department of Labor uses the “economic realities” test which focuses on whether the worker is economically dependent on the employer.
In an effort to help combat the confusion over proper worker classification, the United States Department of Labor (DOL) has issued a new Administrator’s Interpretation that provides a detailed explanation of the test used by the DOL to determine if a worker has been misclassified as an independent contractor. The DOL enforces the Fair Labor Standards Act (FLSA), which mandates that employees (but not independent contractors) be paid minimum wage and overtime. When a business misclassifies non-exempt workers as independent contractors, and those workers are not paid the minimum hourly wage for their labor, or are not paid overtime when they work more than 40 hours in a workweek, this violates the FLSA.
Read the court decisionRead the full story...Reprinted courtesy of
Tanya Salgado, White and Williams LLPMs. Salgado may be contacted at
salgadot@whiteandwilliams.com
ASCE Statement on National Dam Safety Awareness Day - May 31
June 06, 2022 —
Dennis D. Truax, President, American Society of Civil Engineers (ASCE)Washington, DC. – Nationwide, more than 92,000 dams protect communities across the country, providing numerous services including irrigation, water conservation, and flood protection. Advocating for the safety, robustness, and sustainability of our nation's dams is a top priority for ASCE as we recognize May 31 as National Dam Safety Awareness Day.
National Dam Safety Awareness Day is observed in remembrance of the "Johnstown Flood" on May 31, 1889. Failures of the South Fork Dam near Johnstown, PA, resulted in the death of more than 2,200 people. This tragedy serves as an illustration of the critical importance of effectively maintaining and managing our nation's dams and ensuring that adequate dam safety measures remain in place to avoid these preventable tragedies.
ASCE's
2021 Report Card for America's Infrastructure gave the nation's dams a "D" grade. Of the nation's 92,000 dams, more than 15,000 are classified as having "high hazard potential", meaning that dam failure would result in the loss of life. While increased state investment in dam safety programs has allowed for better assessment of dams and the ability to identify rehabilitation needs as well as potential hazards, increased federal investment is still needed to ensure the safety of dams nationwide.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Plaintiffs Not Barred from Proving Causation in Slip and Fall Case, Even With No Witnesses and No Memory of Fall Itself
February 01, 2022 —
David Hoynacki, Arezoo Jamshidi & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPOn January 19, 2022, the California Court of Appeal, Second Appellate District (Los Angeles), held that a plaintiff is not barred as a matter of law from proving causation in a slip and fall case if there were no witnesses to the fall, and the plaintiff does not remember the fall itself. The Court of Appeal stated specifically that circumstantial evidence would permit a jury to make a “reasonable and probable inference” regarding contributing factors to a fall, even with no eye-witness evidence.
In
Kaney v. Mazza (BC619247, Jan. 19, 2022), plaintiff and appellant Lydia Kaney (Kaney), was visiting her sister in her rented home in September of 2014. At some point during the visit, the light in the bathroom at the top of the stairs stopped working—Kaney used the stairs, and fell. Kaney filed suit against her sister and the owner of the home alleging premises liability, negligence, and violation of the Americans with Disabilities Act (ADA). In her deposition, Kaney testified that she remembered going up to the bathroom, and then waking up on the floor in pain. She could not remember how she fell; she did not know if she had missed a step, or if she had slipped and fallen backwards. She speculated that a worn-out bath mat may have been the cause of the slip and fall because the rubber traction on the bath mat was worn away.
Reprinted courtesy of
David Hoynacki, Haight Brown & Bonesteel LLP,
Arezoo Jamshidi, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Mr. Hoynacki may be contacted at dhoynacki@hbblaw.com
Ms. Jamshidi may be contacted at ajamshidi@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Relevance and Reasonableness of Destructive Testing
August 17, 2017 —
David Adelstein - Florida Construction Legal UpdatesDestructive testing is a routine investigatory procedure in construction defect disputes. The destructive testing is necessary to determine liability (causation), the extent of damage, and the repair protocol. Destructive testing is designed to answer numerous questions: Why did the building component fail? Was the building component constructed incorrectly? What is the magnitude of the damage caused by the failure? What specifically caused the damage? What is the most effective way to fix the failure and damage? There are different iterations to the same questions, but in many instances, destructive testing is necessary to answer these questions.
Claimants sometimes prohibit destructive testing. Of course, destructive testing is intrusive. In many instances, it is very intrusive. But, this testing is a necessary evil. Without this testing, how can a defendant truly analyze their potential exposure and culpability? They need to be in a position to prepare a defense and figure out their liability. This does not mean destructive testing is warranted in every single construction defect dispute. That is not the case. However, to say it is never warranted is irrational.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Presenting a “Total Time” Delay Claim Is Not Sufficient
September 12, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen presenting a delay-type of claim on a construction project, a claimant MUST be in a position to properly PROVE the claim. Trying to present a delay claim loosey-goosey is not a recipe for success. In fact, it can be a recipe for an easy loss. This is not what you want. To combat this, make sure you engage a delay expert that understands delay methodologies and how to calculate delay and do NOT present a total time claim. Presenting a delay claim using a total time approach, discussed below, makes it too easy to attack the flaws and credibility of the approach. Per the discussion of the case below, a total time claim with a contractor that used its project manager, versus a delay expert, to support its claim turned the contractor’s claim into a loss.
In French Construction, LLC v. Department of Veteran Affairs, 2022 WL 3134507, CBCA 6490 (CBCA 2022), a contractor submitted a delay claim to the government for almost $400,000. The contractor was hired to construct a two-story corridor to connect hospital buildings. The contractor was required to be complete within 365 days. It was not. The contractor was seeking 419 days of delay from the government. The contractor’s “delay expert” was its project manager who compared the contractor’s as-planned schedule to an as-built schedule he prepared for the claim.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Cybercrime Is On the Rise
May 26, 2019 —
Tom Sawyer & Jeff Rubenstone - Engineering News-RecordAt the end of April, just as St. Ambrose Roman Catholic Church in Brunswick, Ohio, neared the close of a five-month-long, $5.5-million renovation, Father Bob Stec, the parish pastor, was surprised to hear that the contractor, Marous Brothers Construction, Willoughby, Ohio, had not received a $1.7- million payment.
Reprinted courtesy of
Tom Sawyer, Engineering News-Record and
Jeff Rubenstone, Engineering News-Record
Mr. Sawyer may be contacted at sawyert@enr.com
Mr. Rubenstone may be contacted at rubenstonej@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
Global Insurer Agrees to Pay COVID-19 Business Interruption Claims
July 06, 2020 —
Sergio F. Oehninger & Daniel Hentschel - Hunton Insurance Recovery BlogAXA, one of the biggest insurance companies in the world, has agreed to pay COVID-related business interruption claims by a group of restaurants in Paris after a court ruled that the restaurants’ revenue losses resulting from COVID-19 and related government orders were covered under AXA’s policies.
AXA initially took the position that its insurance policies did not cover business interruption caused by COVID-19. The restaurant then sued AXA in a French court, seeking coverage for operating losses resulting from a government order issued in March mandating the closure of restaurants and bars in response to the COVID-19 pandemic. The court concluded that the government orders, which prohibited restaurants from receiving the public and offering traditional sit-down dining services, triggered the policy’s coverage for business interruption coverage. The court rejected AXA’s argument that the pandemic was uninsurable, and made clear that if AXA intended to exclude such a risk it should have done so expressly in its policy. The court also rejected AXA’s argument that there must be a prerequisite of an insured event for the application of the “administrative closure” provision, noting that no prerequisite was required by the policy. AXA’s argument that the government orders did not require the restaurant to be closed because the restaurant was authorized to maintain take-away services was also rejected. As a result, the court ruled in favor of the policyholders, holding that the business interruption loss resulting from the government orders qualified for insurance coverage.
Reprinted courtesy of
Sergio F. Oehninger, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Texas Supreme Court Rules on Contractual Liability Exclusion in Construction Cases
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Texas Supreme Court ruled on Ewing v. Amerisure Ins. Co. on January 17th, a “much-anticipated” decision according to Carl A. Salisbury of Kilpatrick Townsend & Stockton LLP. “Construction projects are always the subject of contracts among owners and contractors” Salisbury stated in his article on Lexology.com. The recent decision demonstrates that “an exclusion in the standard Comprehensive Liability Insurance policy that precludes coverage for ‘liabilities assumed under contract’” does not usually “apply to construction contracts.”
In 2008, Ewing Construction Company built a set of tennis courts in Corpus Christi, according to Salisbury. “Shortly after construction was complete, according to the school district, ‘the courts started flaking, crumbling, and cracking, rendering them unusable for their intended purpose of hosting competitive tennis events.’” After the school district sued Ewing in state court, Ewing “turned the suit over to Amerisure, its CGL insurer, seeking a defense and indemnity. Amerisure denied all coverage, citing the contractual liability exclusion in its policy. This inspired Ewing to sue the carrier in federal district court for the Southern District of Texas.”
After several rulings and appeals, the case eventually reached the Texas Supreme Court: “According to the Ewing court, the contract claims that Ewing failed to perform in a good and workmanlike manner ‘are substantively the same as its claims that Ewing negligently performed under the contract because they contain the same factual allegations and alleged misconduct.’ Failure to perform in a ‘good and workmanlike manner’ is functionally and substantively the same as performing negligently. ‘Accordingly,’ the Ewing court said, ‘we conclude that a general contractor who agrees to perform its construction work in a good and workmanlike manner, without more, does not enlarge its duty to exercise ordinary care in fulfilling its contract, thus it does not ‘assume liability’ for damages arising out of its defective work so as to trigger the Contractual Liability Exclusion.’”
Read the court decisionRead the full story...Reprinted courtesy of