Beyond the Flow-Down Clause: Subcontract Provisions That Can Expose General Contractors to Increased Liability and Inconsistent Outcomes
December 10, 2024 —
Phillip L. Parham III - ConsensusDocsFlow-down clauses in construction subcontracts—blanket clauses providing that some or all of the terms and conditions in the prime contract between the general contractor and the property owner apply equally between the subcontractor and general contractor—are an important component to managing risk for a general contractor and reducing the likelihood of disputes with either/both the owner and subcontractor. Put simply, flow-down provisions can provide continuity between the general contractor’s obligations to the owner and the subcontractor’s obligations to the general contractor. Properly drafted, flow-down clauses reduce the general contractor’s risk by ensuring that the subcontractor is legally bound to meet the owner’s objectives for the project in the same way as the general contractor. But relying on blanket flow-down clauses, alone, to protect the general contractor is like a soldier going into battle with nothing but a helmet, leaving significant other areas exposed and unprotected. In other words, a general contractor should look beyond just a singular, blanket flow down of terms to ensure its bases are properly covered.
Accordingly, this article goes beyond the blanket flow-down clause and highlights several key subcontract provisions where inconsistent obligations among the subcontractor, general contractor, and owner expose the general contractor to increased liability and inconsistent outcomes. Specifically, this article will examine disputes resolution clauses, liquidating provisions, notice provisions, and termination provisions. However, this article will not provide a deep examination of these clauses, nor does it highlight every potentially relevant clause. Rather, it focuses on these select clauses to highlight important issues associated with flow-down provisions.
Read the court decisionRead the full story...Reprinted courtesy of
Phillip L. Parham III, Jones Walker LLPMr. Parham may be contacted at
pparham@joneswalker.com
Precedent-Setting ‘Green’ Apartments in Kansas City
September 17, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to the Kansas City Star, the Missouri riverfront apartment development, Second and Delaware, is being constructed with “greener-than-green technology” and features the following: “Sixteen-inch-thick concrete walls. Rooftop gardens. A 90 percent reduction in energy use compared to current building codes.”
The two buildings “will comprise the largest U.S. multifamily apartment project using Passive House Institute-certified construction, a system that’s more energy-efficient than the highest LEED (Leadership in Energy and Environmental Design) building standard.”
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court of Kentucky Holds Plaintiff Can Recover for Stigma Damages in Addition to Repair Costs Resulting From Property Damage
August 15, 2018 —
Gus Sara - The Subrogation StrategistIn Muncie v. Wiesemann, 2018 K.Y. LEXIS 257, the Supreme Court of Kentucky considered whether stigma damages[1] in a property casualty case are recoverable in addition to the costs incurred to remediate the actual damage. The court held that stigma damages are recoverable in addition to repair costs, but the total of the stigma damages and repair costs cannot exceed the diminution in the fair market value of the property. The court’s decision establishes that if the repair costs are insufficient to make the plaintiff whole, a recovery for stigma damages up to the amount of the diminution in the market value of the home is appropriate.
Appellants Cindy and Jim Muncie incurred significant property damage to their home as a result of an oil leak originating from a neighboring property owned by the Estate of Martha Magel. In 2011, Auto Owners Insurance Company (Auto Owners), the liability carrier for the Estate’s testatrix, Patricia Weisman, filed an impleader complaint in federal court to discharge its obligation to settle the third-party liability claims on behalf of Ms. Weisman. Auto Owners reached a settlement with the Muncies for $60,000 which represented the remediation costs for the actual damage to the property. The settlement release reserved the Muncies’ right to pursue a claim for stigma damages associated with the oil leak.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com
Partner Bradley T. Guldalian Secures Summary Judgment Win for National Hotel Chain
August 26, 2019 —
Bradley T. Guldalian - Traub LiebermanOn June 26, 2019, Traub Lieberman Straus & Shrewsberry LLP Partner Bradley T. Guldalian secured summary judgment on behalf of a national hotel chain in a slip and fall accident filed in Osceola County Circuit Court in Kissimmee, Florida. The underlying loss occurred when the Plaintiff slipped and fell in a puddle of water allegedly existing in the hotel’s laundry room and suffered a partial thickness rotator cuff tear involving the distal infraspinatus tendon for which he underwent surgery and incurred over $70,000 in medical bills. The Plaintiff filed a premises liability action against the hotel claiming the hotel had failed to maintain its premises in a reasonably safe condition proximately causing the Plaintiff’s fall and resulting injuries.
After discovery closed, Mr. Guldalian filed a motion for summary judgment on behalf of the hotel arguing that to prevail in a negligence claim involving a “transitory foreign substance”, such as water on a floor, an injured party must plead and prove pursuant to Florida Statute 768.0755 that the business establishment had actual or constructive knowledge of the dangerous condition and should have taken action to remedy it prior to the time of the alleged fall. Constructive knowledge may be proven by circumstantial evidence showing that (1) the dangerous condition existed for such a length of time that, in the exercise of ordinary care, the business establishment should have known of the condition or (2) that the condition occurred with such regularity that it was foreseeable that the condition would be present on the day the injury occurred.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley T. Guldalian, Traub LiebermanMr. Guldalian may be contacted at
bguldalian@tlsslaw.com
WSHB Secures Victory in Construction Defect Case: Contractor Wins Bench Trial
October 01, 2024 —
Wood Smith Henning & BermanWood Smith Henning & Berman is pleased to announce a significant victory in a bench trial led by trial attorney
Thomas Fama. The case, which had been pending for nearly five years due to pandemic-related delays and unreasonable demands by the plaintiff, concluded with a resounding judgment in favor of the defendant.
"The result of this trial is a testament to our team's unwavering tenacity and strategic focus throughout the entire process," stated WSHB partner Tom Fama, lead counsel in the case. "We kept our eye on the proverbial ball and diligently worked to expose the lack of evidence supporting the plaintiff's claims."
The matter involved allegations of defective installation of a solar energy system, which the plaintiff claimed leaked during inclement weather. Fama and his team successfully demonstrated that the plaintiff's claims lacked substance, highlighting numerous pre-existing conditions on the roof that could have been responsible for the problem.
Read the court decisionRead the full story...Reprinted courtesy of
Wood Smith Henning & Berman
Virginia General Assembly Helps Construction Contractors
June 10, 2015 —
Christopher G. Hill – Construction Law MusingsAs reported last week at the Virginia Real Estate, Land Use and Construction Law Blog (authored by my good friend Tim Hughes (@timrhughes)), the Virginia General Assembly has passed an amendment to the jurisdictional limitations of Virginia General District Courts. The new statute, going into effect July 1, 2011, increases the jurisdiction of these courts to $25,000 from the present level of $15,000.
Why is this a big deal? As a solo practitioner who represents contractors and subcontractors in cases big and small, this increase is a boon to my practice and the collect-ability of some debts. I think back to the numerous conversations I have had with clients who had bona fide claims for around $20,000. These conversations inevitably turned toward the cost of Circuit Court versus General District Court and whether it would be better to leave money out of the claim to avoid the ramped up attorney fee and filing costs (not to mention the time from filing to judgment). This conversation was especially relevant in the instance where the contracts did not contain an attorney fees provision.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Homebuilders See Record Bearish Bets on Shaky Recovery
June 18, 2014 —
Callie Bost – BloombergSomeone thinks the housing rebound is built on shaky foundations.
A record 180,000 puts traded on the SPDR S&P Homebuilders (XHB) exchange-traded fund on June 11, according to data compiled by Bloomberg. The contract with the highest ownership pays off in the event of a 20 percent slump by December in the ETF tracking stocks from DR Horton Inc. to Williams-Sonoma Inc.
Prospects for rising interest rates and an uneven recovery in the housing market have hurt returns this year, sending the SPDR Homebuilders ETF down 3.3 percent. While economic data yesterday showed that builders broke ground on 1 million U.S. homes in May, permits, a proxy for future construction, decreased because of fewer applications for condominiums and apartment buildings.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Bost may be contacted at
cbost2@bloomberg.net
Insurer Entitled to Reimbursement of Defense Costs Under Unjust Enrichment Theory
May 04, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court for the district of Hawaii determined that the insurer could recover defense costs from an additional insured consistent with its Reservation of Rights letter under an unjust enrichment theory. Giga, Inc. v. Kiewit Infrastructure W. Co., 2020 U.S. Dist. LEXIS 10151 (D. Haw. Jan. 22, 2020).
This case was related fall-out from the Arthur case. Arthur v. Dept. of Hawaiian Homelands, 185 Haw. 149 (Haw. Ct. App. 2015). A prior post on the case is here.
In Arthur, a resident, Mona Arthur, of the Kalawahine Streamside Housing Development, was killed when she apparently slipped and fell from a hillside adjacent to the project. She was on the hillside tending to her garden there. At the bottom of the hill was a two foot fence in front of a drainage ditch, where Mona allegedly hit her head.
Mona's husband, William Arthur, sued a variety of defendants including the land owner, designer, developer, civil engineer and others. William alleged the defendants were negligent in the design, construction and supervision of the construction of the hillside area.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com