U.S. Home Prices Climbed 0.1% in July as Gains Slowed
September 24, 2014 —
Prashant Gopal – BloombergU.S. home prices rose less than economists estimated in July as investors pull back from the property market.
Prices climbed 0.1 percent on a seasonally adjusted basis from June, the Federal Housing Finance Agency said today in a report from Washington. The average economist estimate was for a 0.5 percent increase, according to data compiled by Bloomberg.
Investors who helped drive up prices are retreating as fewer foreclosures and other discounted homes become available. All-cash purchases in August fell to about 23 percent of the market from the usual 33 percent, the National Association of Realtors reported yesterday. Investors accounted for 12 percent, the least since late 2009.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
CGL Coverage for Liquidated Damages and the Contractual Liability Exclusion
October 09, 2023 —
Stu Richeson - The Dispute ResolverLiquidated delay damages are common in construction contracts and are generally imposed when a contractor fails to achieve substantial completion within the time required by the contract. While contracts like the AIA A201-2017 have provisions for extending the time to achieve substantial completion when delays are caused by circumstances beyond the contractor’s control, delays can result from factors other than improper management or planning and the like, for which the owner is not required to give the contractor additional time. Courts are split on whether there is ever coverage under a CGL policy for contractually agreed upon liquidated delay damages.
Liquidated delay damages are often excluded under the contractual liability exclusion of most CGL policies. The contractual liability exclusion excludes coverage for “liability for which the Insured is obligated to pay damages by reason of the assumption of liability in a contract or agreement.” Courts often find the contractual liability exclusion in a CGL policy precludes coverage for liquidated delay damages, because such damages are contractual in nature and are triggered by the failure to bring the contract to substantial completion by a fixed deadline, regardless of the cause of the delay. However, some courts will look to the cause of the delay and find that there is coverage under a CGL policy for liquidated delay damages that are the result of property damage caused by an accident or occurrence.
In Clark Const. Grp., Inc. v. Eagle Amalgamated Serv., Inc., 01-2478-DV, 2005 WL 2092998, at *1 (W.D. Tenn. Aug. 24, 2005) a general contractor entered a contract for the renovation of the convention center in Memphis. Part of the project included the demolition of a structure attached to the convention center. The demolition work was improperly performed by a subcontractor and resulted in damage to the convention center.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
Texas School System Goes to Court over Construction Defect
December 30, 2013 —
CDJ STAFFThe Zapata County Independent School District filed a lawsuit against Satterfield and Pontikes, claiming construction defect in two schools and two gyms that the company built for the district, according to the Laredo Morning Times. The company built two elementary schools, Zapata South and Fidel & Andrea Villarreal, and the gyms were built at Zapata North and Arturo L. Benavides. The case is scheduled to reach the courtroom in January, 2014.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “A Fastball Right to the Bean!”
May 06, 2024 —
Daniel Lund III - LexologyThe Metropolitan Municipality of Lima, Peru, filed suit in federal court in Washington DC to vacate two separate arbitration awards rendered against the city in international arbitration proceedings subject to the Federal Arbitration Act.
The city had contracted to build, improve, and maintain various highways in and around the city. To pay for this infrastructure, Lima agreed that the contractor would “receive revenues from existing and new toll booths.”
Apparently, the City of Lima forgot how much citizens of the area loathed tolls, and, according to the court, the local public officials “quickly truckled” (how apropos for a road project!) to the pressure. As a result, revenues promised to the contractor were not forthcoming, and the city did nothing about it.
The contractor initiated arbitration, and the city countered by arguing that the contractor had bribed its way into the contract. The city lost and was held in breach.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Florida Appellate Court Holds Four-Year Statute of Limitations Applicable Irrespective of Contractor Licensure
June 22, 2016 —
Clay Whittaker – Florida Construction Law UpdateIn Brock v. Garner Window & Door Sales, Inc.,[1] Florida’s Fifth District Court of Appeal rejected a novel attempt to circumvent Florida’s well-established four-year statute of limitations for all actions founded on the construction of an improvement to real property. Plaintiff filed a lawsuit alleging breach of contract as a result of water intrusion damage following the installation of windows.[2] It was undisputed that Plaintiff commenced the litigation more than four years following the discovery of the allegedly latent defect in the window installation.[3] Plaintiff’s counsel argued that the window contractor could not rely on the four-year statute of limitations because the window subcontractor was not a licensed contractor and, therefore, the five-year statute of limitations for actions founded on written contracts should apply.
Read the court decisionRead the full story...Reprinted courtesy of
Clay Whittaker, Cole, Scott, & Kissane, P.A.Mr. Whittaker may be contacted at
clay.whittaker@csklegal.com
$48 Million Award and Successful Defense of $135 Million Claim
June 04, 2024 —
Peckar & AbramsonPeckar & Abramson is proud to have represented one of the nation’s largest general contractors in the achievement of a $48 million award in its favor and the denial of a $135 million claim against it in Federal Court in the Middle District of Florida on May 3, 2024 arising out of the FDOT’s $2.3 billion reconstruction of I-4, a P3 project and the Department’s largest project ever in the State of Florida.
After a 2-week bench trial, P&A secured the favorable decision which found that the general contractor client was entitled to recover $48 million on its affirmative claim against the party who initiated the lawsuit and that it did not breach its fiduciary duties and was not grossly negligent as was claimed which resulted in a denial of the initiating party’s $135 million claim in its entirety.
Read the court decisionRead the full story...Reprinted courtesy of
Peckar & Abramson
Don’t Conspire to Build a Home…Wait…What?
June 08, 2020 —
Ben Volpe - Colorado Construction Litigation BlogIn 1986, the Colorado General Assembly enacted the Pro Rata Liability Act, codified at C.R.S. § 13-21-111.5, which eliminated joint and several liability for defendants in favor of pro rata liability.[1] The statute was “designed to avoid holding defendants liable for an amount of compensatory damages reflecting more than their respective degrees of fault.”[2] However, the following year, the Colorado legislature carved out an exception to preserve joint liability for persons “who consciously conspire and deliberately pursue a common plan or design to commit a tortious act.”[3] Because of this conspiracy exception, plaintiffs try to circumvent the general rule against joint and several liability by arguing that construction professionals defending construction defect cases were acting in concert, as co-conspirators. Plaintiffs argue that if they can prove that two or more construction professionals consciously conspired and deliberately pursued a common plan or design, i.e., to build a home or residential community, and such a plan results in the commission of a tort, i.e., negligence, the defendants may be held jointly and severally liable for all of the damages awarded.
Since 1986, Colorado courts have construed the “conspiracy” provision in § 13-21-111.5(4), but some have disagreed as to what constitutes a conspiracy for purposes of imposing joint liability.
Civil Conspiracy
In Colorado, the elements of civil conspiracy are that: “(1) two or more persons; (2) come to a meeting of the minds; (3) on an object to be accomplished or a course of action to be followed; (4) and one or more overt unlawful acts are performed; (5) with damages as the proximate result thereof.”[4]
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin Volpe, Higgins, Hopkins, McLain & Roswell, LLCMr. Volpe may be contacted at
volpe@hhmrlaw.com
OSHA Issues New Rules on Injury Record Keeping
August 19, 2015 —
Craig Martin – Construction Contractor AdvisorOn July 28, 2015, OSHA issued proposed rules seeking to clarify an employer’s ongoing obligation to make and maintain accurate records of work-related injuries and illness. The new rules were drafted in response to the U.S. Court of Appeals decision in AKM LLC, d/b/a Volks Constructors v. Secretary of Labor, in which a contractor successfully argued that OSHA’s citation was issued well beyond the six month limitation period.
OSHA’s Injury Record Keeping Obligations
The Occupational Safety and Health Act requires each employer to make, keep and preserve records of workplace injuries and illnesses. 29 U.S.C. § 658(c). OSHA has promulgated a set of regulations which require employers to record information about work-related injuries and illnesses in three ways. Employers must prepare an incident report and a separate injury log “within seven (7) calendar days of receiving information that a recordable injury or illness has occurred,” 29 C.F.R. § 1904.29(b)(3), and must also prepare a year-end summary report of all recordable injuries during the calendar year, id. § 1904.32(a)(2). An employer “must save” all of these documents for five years from the end of the calendar year those records cover. 29 C.F.R. § 1904.33(a).
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com