Massachusetts District Court Holds Contractors Are Not Additional Insureds on Developer’s Builder’s Risk Policy
August 31, 2020 —
Gus Sara - The Subrogation StrategistIn Factory Mut. Ins. Co. v. Skanska United States Bldg., No. 18-cv-11700-DLC, 2020 U.S. Dist. LEXIS 95403 (Skanska), the United States District Court for the District of Massachusetts considered whether contractors on a construction job were additional insureds on the developer’s builder’s risk insurance policy. After a water loss occurred during construction, the builder’s risk insurance carrier paid its named insured for the resultant damage, and subsequently filed a subrogation action against two contractors. The defendants filed a motion for summary judgment, claiming that the anti-subrogation rule barred the carrier from subrogating against them because they were additional insureds on the policy. The court found that based on the particular language of the additional insured provision in the policy, the defendants were not additional insureds for purposes of the subrogation action.
Skanska arose from property damage that occurred during a construction project where Novartis Corporation (Novartis) endeavored to construct a biomedical research building in Cambridge, Massachusetts and retained Skanska USA Building, Inc. (Skanska) as the general contractor. In turn, Skanksa hired J.C. Cannistraro, LLC (JCC) as a subcontractor. Novartis secured a builder’s risk insurance policy from Factory Mutual Insurance Company (Factory Mutual). The policy defined “Insured” as Novartis and its subsidiaries, partnerships and joint ventures that it controlled or owned. The policy included another provision, titled “Property Damage,” which stated that the policy “insures the interest of contractors and subcontractors in insured property… to the extent of the Insured’s legal liability for insured physical loss or damage to such property.”
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Sureties and Bond Producers May Be Liable For a Contractor’s False Claims Act Violations
October 19, 2017 —
Michael C. Zisa & Susan Elliott – Peckar & Abramson, P.C.Two recent decisions from the United States District Court for the District of Columbia and the United States Court of Federal Claims highlight that sureties and bond producers are not immune to the potentially severe consequences of the False Claims Act (“FCA”) and related federal fraud statutes. In each case, the Court determined that sureties and bond producers can face potential liability under these fraud statutes for direct and indirect submission of false claims to the federal government.
Reprinted courtesy of
Michael C. Zisa, Peckar & Abramson, P.C. and
Susan Elliott, Peckar & Abramson, P.C.
Mr. Zisa may be contacted at mzicherman@pecklaw.com
Ms. Elliott may be contacted at selliott@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Not So Universal Design Fails (guest post)
April 28, 2016 —
Melissa Dewey Brumback – Construction Law in North CarolinaToday we have a guest post from Carla Williams, who works in customer service for the
Williams Brothers Corporation of America. Carla humorously brings light to a serious problem– the intent behind ADA and Universal Design is very often not met with poorly-thought out applications in the real world. Enjoy, and feel free to leave a comment for Carla below.
Universal design is the idea that architecture should be inherently accessible to everyone. The growing number of architects adopting universal design is great news for people with accessibility needs. Instead of having separate entrances and walkways to make a building accessible, universal design allows people of all abilities to move together.
Unfortunately, many buildings are stuck back in 1990 right after the Americans with Disabilities Act was made law. These buildings may be technically “accessible,” but they aren’t spaces people with accessibility needs can maneuver very easily. Until all building designers come to understand and implement the beauty and functionality of universal design, the world is left with less than ideal accessibility. “Less than ideal” is a bit of an understatement. Many times full-on “accessibility fails” take place.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Disputes Will Not Be Subject to Arbitration Provision If There Is No “Significant Relationship”
November 29, 2021 —
David Adelstein - Florida Construction Legal UpdatesAs you know from prior articles, arbitration is a creature of contract. This means if you want your disputes to be resolved by binding arbitration, as opposed to litigation, you want to make sure there is an arbitration provision in your contract. If there are certain types of disputes you do not want subject to arbitration, you want to specify those types of disputes/claims in your arbitration provision. If you are not sure, make sure to discuss the pros and cons of arbitration with your counsel when drafting and negotiating the contract. However, even with a broad arbitration provision, there are times where a dispute may still fall out of the scope of the arbitration provision, i.e., the dispute is not arbitrable. If this occurs, such dispute will be resolved by litigation. Parties that have buyer’s remove and do not want to arbitrate their dispute may try to make this argument that the dispute is not subject to the scope of the arbitration provision. There are times this argument carries weight because the dispute has no significant relationship to the agreement with the arbitration provision, as shown below.
In Deweees v. Johnson, 46 Fla. L. Weekly D2356b (Fla. 4th DCA 2021), a plaintiff purchased a home in a private residential community. The purchase contract with the developer contained a broad arbitration provision that materially provided that, “all post-closing claims, disputes, and controversies…between purchaser and seller will be resolved by binding arbitration except those arising under section G.5 and G.6 above.” Dewees, supra. Sections G.5 and G.6 provided that the purchaser will not interfere in the sales process with other purchasers and will not interfere with workmen during the construction process. There was also a workmanship and structural defect warranty for the dwelling that also contained an arbitration provision.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Caterpillar Said to Be Focus of Senate Overseas Tax Probe
March 26, 2014 —
Richard Rubin and Jesse Drucker - BloombergA U.S. Senate investigative panel is examining Caterpillar Inc. (CAT) and whether the company improperly avoided U.S. taxes by moving profits outside the country, said three people familiar with the inquiry.
The Senate’s Permanent Subcommittee on Investigations will hold a hearing in early April, said two of the people. They spoke on condition of anonymity before an official announcement.
Rachel Potts, a spokeswoman for Caterpillar, declined to comment. Two staff members for the subcommittee declined to comment.
In 2009, Daniel Schlicksup, an employee who had worked on tax strategy, alleged in a lawsuit in federal court that Caterpillar used a “Swiss structure” to shift profits to offshore companies and avoid more than $2 billion in U.S. taxes. He also alleged that Caterpillar used a “Bermuda structure” involving shell companies to return profits to the U.S. without paying required taxes.
Mr. Rubin may be contacted at rrubin12@bloomberg.net; Mr. Drucker may be contacted at jdrucker4@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Richard Rubin and Jesse Drucker, Bloomberg
Colorado Requires Builders to Accommodate High-Efficiency Devices in New Homes
December 14, 2020 —
David M. McLain – Colorado Construction LitigationStarting in 2009, the Colorado Legislature began adding requirements that builders offer certain options to accommodate high-efficiency devices. These requirements started with solar prewire options in 2009, then water-smart home options in 2010. In 2020, the Legislature added requirements for electric vehicle charging and heating systems. These sections apply to unoccupied homes serving as sales inventory or a model home or manufactured homes, as defined by Colorado law. While the Legislature has only required builders to include options to accommodate these devices, it may be just a matter of time until builders must install the prescribed devices themselves.
In 2009, the Legislature passed C.R.S. 38-35.7-106, which was amended this year by HB 20-1155. As it now reads, Colorado law requires every builder of single-family detached residences to offer to have the home’s electrical or plumbing system, or both, include:
- A residential photovoltaic solar generation system or a residential thermal system, or both;
- Upgrades of wiring or plumbing, or both, planned by the builder to accommodate future installation of such systems; and
- A chase or conduit, or both, constructed to allow ease of future installation of the necessary wiring or plumbing for such systems.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Expert Medical Science Causation Testimony Improperly Excluded under Daubert; ID of Sole Cause of Medical Condition Not Required
April 15, 2014 —
R. Bryan Martin & Whitney L. Stefko - Haight Brown & Bonesteel LLPOn April 4, 2014, in Messick v. Novartis Pharmaceuticals Corp., the United States Court of Appeals for the Ninth Circuit reversed the district court's summary judgment in favor of Defendant Pharmaceutical Corporation because the district court improperly excluded expert testimony. The three-judge panel held that the district court erred by excluding causation testimony offered by Plaintiff's expert it found to be irrelevant and unreliable.
Plaintiff was diagnosed with breast cancer in 2000. In response to her development of osteoporosis after chemotherapy, Plaintiff treated with the drug Zometa for several months in 2002. Zometa is a bisphosphonate, a class of drug commonly used to treat multiple myeloma. Such drugs are generally used to reduce or eliminate the possibility of skeletal-related degeneration and injuries to which cancer patients are particularly susceptible. Novartis Pharmaceuticals Corporation produces Zometa, which was approved by the FDA in 2001 and 2002. In 2005 after encountering issues with her jaw, it was discovered that Plaintiff had osteonecrosis near three of her teeth. The oral specialists treating Plaintiff did so under the assumption that she was suffering from bisphosphonate-related osteonecrosis of the jaw ("BRONJ"), a condition recognized by the American Association of Oral and Maxillofacial Surgeons ("AAOMS"). Plaintiff's BRONJ healed in 2008 - three years after beginning treatment.
Thereafter, Plaintiff brought suit against Novartis for strict products liability, negligent manufacture, negligent failure to warn, breach of express and implied warranty, and loss of consortium. In support of her claims, Plaintiff offered her expert's testimony on ONJ and BRONJ, and on the causal link between plaintiff's bisphosphonate treatment and later development of BRONJ. Novartis filed a Daubert motion to exclude the specific causation testimony of Plaintiff's experts and a motion seeking summary judgment. The district court granted both motions on the basis that Plaintiff's expert testimony was irrelevant and unreliable.
Reprinted courtesy of
R. Bryan Martin, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Martin may be contacted at bmartin@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of