Noah Buhayar – BloombergWarren Buffett auctions a lunch date for charity every year, and the winning bid usually stretches to seven figures. He twice sold his used cars to fans for multiples of their Kelly Blue Book value. Someone once even paid more than $200,000 to purchase his old wallet. (It had a stock tip inside.) For those who venerate one of the world’s best investors, money is usually no object when buying a piece of the legend.
A year ago, Buffett put his vacation home in Emerald Bay, a gated enclave next to Laguna Beach, Calif., up for sale. He bought the property in 1971 at the urging of his first wife, Susan, for $150,000—the equivalent of a bit less than $1 million today. At the time, he didn’t think of it much as an investment, he told the Wall Street Journal last year. Laguna was less developed back then, more surfer-and-hippie paradise than multimillionaire’s haunt. The couple and their family often spent summers at the home, as well as time around Christmas, when Buffett would hole up in the master bedroom working on his closely followed
annual letter to
Berkshire Hathaway Inc. shareholders.
Read the court decisionRead the full story...Reprinted courtesy of
Noah Buhayar, Bloomberg
The Practical Distinction Between Anticipatory Breach and Repudiation and How to Deal with Both on Construction Projects
June 10, 2024 —
Devon Griger - ConsensusDocsWhen a multilevel construction project is underway and a contractor or subcontractor isn’t performing as expected, it can be difficult to know how to address the low performance without putting the parties’ contract and good working relationship at risk. However, there may come a time when poor performance lapses into a something much worse: an anticipatory breach or repudiation of the subject contract.
Imagine Scenario One: You are a general contractor managing a large-scale construction project and one of your subcontractors is falling behind on their work. The project manager for the subcontractor calls you and says, “Look, I don’t think we’re going to be able to hit our next milestone, and probably not the next one after that.” A conversation like this would generally trigger concern for most general contractors, but it would not necessarily invoke panic. These types of delay conversations are not uncommon on large scale projects.
Compare that example, however, with Scenario Two, where the subcontractor instead says, “We received an offer to work another job for much more money, so we’re leaving the project site today and will not be returning.” This is obviously different (and potentially worse) than Scenario One, and likely cause for much greater concern.
Read the court decisionRead the full story...Reprinted courtesy of
Devon Griger, Jones WalkerMs. Griger may be contacted at
dgriger@joneswalker.com
The Court-Side Seat: FERC Reviews, Panda Power Plaints and Sovereign Immunity
April 26, 2021 —
Anthony B. Cavender - Gravel2GavelThis is a brief report on new environmental law decisions, regulations and legislation.
THE U.S. SUPREME COURT
Massachusetts Lobsterman’s Association v. Raimondo, Secretary of Commerce
On March 22, 2021, the Supreme Court rejected a petition to review a Presidential decision to invoke the Antiquities Act of 1906 to designate as a monument “an area of submerged land about the size of Connecticut” in the Atlantic Ocean. This action forbids all sorts of economic activity, which compelled the filing of litigation in the First Circuit challenging this designation. Chief Justice Roberts supported the Court’s denial of certiorari, but remarked that a stronger legal case may persuade the Court to review such liberal uses of the Antiquities Act.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Construction Law Client Alert: California’s Right to Repair Act (SB 800) Takes Another Hit, Then Fights Back
February 25, 2014 —
Steven M. Cvitanovic and Whitney L. Stefko - Haight Brown & Bonesteel, LLPLast week, the California appellate courts decided two cases with ramifications under the Right to Repair Act. The first case, Burch, addresses whether the Right to Repair Act is the exclusive remedy for the homeowner. The second case, KB Home, addresses a situation where a homeowner or the homeowner's insurer fails to follow the procedures under the Right to Repair Act.
Last August, the Fourth Appellate District announced its decision in Liberty Mutual Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98 holding that SB 800 is not a homeowner’s exclusive remedy in situations where defects cause actual damage. Many lawyers believed that Liberty Mutual would be a one-off because of its facts – it was a subrogation case brought by an insurance company. So much for that.
Now the Second Appellate District is getting into the act.
In Burch v. The Superior Court of Los Angeles County, et al., the Second Appellate District overturned an order granting summary adjudication in favor of a developer, general contractor, and their respective owners, in a construction defect action brought by a residential homeowner. The trial court found that the Right to Repair Act precluded the homeowner’s negligence and implied warranty claims but the Court of Appeal reversed.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel, LLP and
Whitney L. Stefko, Haight Brown & Bonesteel, LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com, Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Court of Appeals Issues Decision Regarding Second-Tier Subcontractors and Pre-Lien Notice
February 06, 2023 —
Travis Colburn - Ahlers Cressman & SleightVelazquez Framing, LLC (“Velazquez”) v. Cascadia Homes, Inc. (“Cascadia”) is a Court of Appeals, Division 2 case where the primary issue on appeal was whether a second tier subcontractor was required to provide pre-lien notice under RCW 60.04 for its labor.
The defendant, Cascadia, was the general contractor that planned to build a home on property it owned in Lakewood, Washington.[1] High End Construction, LLC (“High End”), submitted a bid to Cascadia for framing work on the home. High End began work on Cascadia’s home, but later subcontracted with Velazquez to complete the framing work.[2] Velazquez did not submit a prelien notice for its work on Cascadia’s home, and Cascadia claimed it was unaware that High End subcontracted with Velazquez for framing at the project.
High End invoiced Cascadia and was paid for its work, but High End never paid Velazquez. Subsequently, Velazquez recorded a lien for both labor and materials, and later filed a complaint to foreclose its lien. Cascadia, due to the fact Velazquez did not provide it with prelien notice, moved for summary judgment, arguing prelien notice was required under RCW 60.04.031(1)[3] and the labor portion of a lien cannot be segregated where a subcontractor’s lien includes both labor and materials. Velazquez argued that no prelien notice was required under RCW 60.04.021[4] and RCW 60.04.031 and claimed that subcontractors can segregate the labor portion from the materials portion. The trial court granted Cascadia’s motion and ruled Velazquez did not fall within one of the exceptions for prelien notice in RCW 60.04.031(2), and therefore, could not enforce the lien. Velazquez appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
Texas Shortens Its Statute of Repose To 6 Years, With Limitations
October 02, 2023 —
Jason Daniel Feld & Roni Most - Kahana FeldEffective June 9, 2023, Texas has shortened its statute of repose from the existing 10-year statute for builders of new homes to 6-years under specific conditions. The significantly shorter statute of repose bars suits against construction contractors of detached one-and two-family homes and townhomes, filed six years after the substantial completion of such homes, where the contractor also furnished a written warranty in compliance with the statute. Notably, projects including apartments, mixed-use, and hotels are not covered by the new law. It is also noted that a grey area in the law exists as to whether condominiums will be covered by the statute. The statute of repose strictly bars the filing of any action, claim or arbitration demand regardless of when the injury was actually discovered (latent defects) and is separate and distinct from any applicable statute of limitations.
The New Texas Statute of Repose Law
Under the
Texas Civil Practice & Remedies Code § 16.009, persons who construct or repair improvements to real property cannot be sued for defective or unsafe conditions of the property or deficiencies in the construction or repair of the improvement later than 10 years after substantial completion of the improvement, except in certain narrow circumstances. This statute is known as the “statute of repose.” The statute applies not only to suits for construction defects, but also personal injury, wrongful death, contribution, and indemnity.
Reprinted courtesy of
Jason Daniel Feld, Kahana Feld and
Roni Most, Kahana Feld
Mr. Feld may be contacted at jfeld@kahanafeld.com
Mr. Most may be contacted at rmost@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
What ENR.com Construction News Gained the Most Views
January 09, 2023 —
C.J. Schexnayder - Engineering News-RecordAs the construction industry continued its ongoing recovery from the global pandemic in 2022, it also faced a number of formidable challenges—including staffing gaps, materials shortages, supply chain delays and the ongoing specter of inflation. Throughout the year, ENR editors reported on how these issues—and many more—were impacting the sector and how it responded.
Reprinted courtesy of
C.J. Schexnayder, Engineering News-Record
Mr. Schexnayder may be contacted at schexnayderc@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Scott Saylin Expands Employment Litigation and Insurance Litigation Team at Payne & Fears
September 23, 2024 —
Payne & Fears LLPScott Saylin has joined Payne & Fears LLP as a Law Clerk in the firm’s Employment Litigation Group and Insurance Litigation Group. Before his time at Payne & Fears, Scott served as a law clerk for Cascadia Healthcare in Boise, Idaho.
“We are pleased to welcome Scott Saylin back to the firm. He was with us as a summer associate before completing his final year of law school at George Washington University,” said Amy Patton, the group’s co-chair. “Scott has fantastic potential to develop into an excellent litigator and will be an asset to our team.”
Get to Know Scott
What activities do you enjoy outside of work?
Pickle ball, long walks, beach trips, cooking, watching the Lakers games, and playing the guitar & piano.
Read the court decisionRead the full story...Reprinted courtesy of
Payne & Fears LLP