Waiving The Right to Arbitrate Under Federal Law
November 08, 2021 —
David Adelstein - Florida Construction Legal UpdatesIf there is an arbitration provision in your contract that you want to enforce, you do not want to take action inconsistent with those rights as this could give rise to a waiver argument, i.e., that you waived your rights to arbitrate, particularly if the other party has been prejudiced.
Under federal policy and law, establishing waiver requires the party arguing waiver to “bear a heavy burden of proof.” U.S. f/u/b/o John Wayne Construction, G.S.A. Division, LLC v. Federal Ins. Co., 2021 WL 4526727 (M.D.Fla. 2021) quoting Stone v. E.F. Hutton & Co., 898 F.2d 1542, 1543 (11th Cir. 1990).
“To determine whether the right to arbitrate has been waived, courts apply a two part test: i) whether, “‘under the totality of the circumstances,’ the party ‘has acted inconsistently with the arbitration right’”; and ii) “whether, by doing so, that party ‘has in some way prejudiced the other party.’” Id. quoting Ivax Corp. V. B. Braun of Am., Inc., 286 F.3d 1309, 1315-16 (11th Cir. 2002). Substantial participation in litigation prior to invoking the right to arbitrate supports a party acting inconsistent with the right to arbitrate. Id. And, “‘[p]rejudice has been found in situations where the party seeking arbitration allows the opposing party to undergo the types of litigation expenses that arbitration was designed to alleviate.’” Id. quoting Morewitz v. W. of Eng. Ship Owners Mut. Prot. & Indem. Ass’n (Luxembourg), 62 F.3d 1356, 1366 (11th Cir. 1995).
Hence the heavy burden for a party to support to prove waiver– establishing both substantial participation in litigation that is inconsistent with the right to arbitrate AND prejudice.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
In All Fairness: Illinois Appellate Court Finds That Arbitration Clause in a Residential Construction Contract Was Unconscionable and Unenforceable
August 22, 2022 —
Gus Sara - The Subrogation StrategistIn Bain v. Airoom, LLC, No. 1-21-001, 2022 Ill. App. LEXIS 241, the Appellate Court of Illinois (Appellate Court) considered whether the lower court erred in enforcing an arbitration clause in a construction contract between the parties and, as a result, dismissing the plaintiff’s lawsuit. The Appellate Court found that even if the arbitration clause was enforceable, the appropriate action would have been for the court to stay the lawsuit, as opposed to dismissing the case entirely. The Appellate Court then considered the language of the arbitration clause and found that several provisions were substantively unconscionable, which rendered the entire arbitration clause unenforceable. The Appellate Court reversed the lower court’s decision compelling arbitration and reinstated the plaintiff’s complaint.
In 2018, the plaintiff, Ms. Bain, a disabled senior citizen, hired the defendant, Airoom, LLC (Airoom), to renovate her home. Airoom provided its “Cash Sales Contract,” which included a binding arbitration clause. The clause required that any dispute arising or relating to the contract be resolved by binding arbitration through the American Arbitration Association (AAA), using the Construction Industry Arbitration Rules and Mediation Procedures (Construction Industry Rules).
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Homeowner Has No Grounds to Avoid Mechanics Lien
September 01, 2011 —
CDJ STAFFThe California Court of Appeals has rejected a motion by a homeowner in a dispute with the contractor who built an extension to his home. In McCracken v. Pirvulete, Mr. McCracken filed a mechanics lien after Mr. Pirvulete failed to complete payment. The matter went to trial with a series of exhibits that showed “the contractual relationship was strained and the parties disagreed over performance and payment.” As a result of the trial, the court awarded Mr. McCracken, the contractor, $1,922.22.
Mr. Pirvulete appealed, contending that the court had not allowed his daughter to act as a translator, that the court had failed to give him sufficient time to present his case, that the mechanics lien should have been dismissed, and several other claims, all before a formal judgment was issued. After the court formalized its judgment and rejected the appeal, Mr. Pirvulete appealed again.
The appeals court found that Mr. Pirvulete did not provide an adequate record for review. The court dismissed Mr. Pirvulete’s claims. The court notes that Mr. Pirvulete claimed that a request for a discovery period was denied, however, he has provided neither the request nor the denial. The trial court has no record of either.
Nor was there a record of a request that Mr. Pirvulete’s daughter provide translation. The court notes, “so far as we can glean from the record provided, the Register of Actions states, ‘Trial to proceed without Romanian Interpreter for Defendant; Daughter present to interpret if needed.’” Additionally, the court found that “there has been no showing that his facility with the English language is or was impaired in any way or that there was any portion of any proceeding, which he did not understand.”
Further, the appeals court found there were no grounds for a new trial, despite Mr. Pirvulete’s filings. The court concluded, “The owner has failed to provide a record adequate for review of most, if not all, of the claims of error. Some issues are not cognizable because they relate to entirely separate proceedings, and not the trial below. To the limited extent that the claims are examinable, the owner has made no showing of error.” The court affirmed the judgment of the lower court against Mr. Pirvulete.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Gillotti v. Stewart (2017) 2017 WL 1488711 Rejects Liberty Mutual, Holding Once Again that the Right to Repair Act is the Exclusive Remedy for Construction Defect Claims
November 21, 2017 —
Richard H. Glucksman, Esq. & Chelsea L. Zwart, Esq. - Chapman Glucksman Dean Roeb & Barger BulletinOriginally published by CDJ on June 5, 2017
Background
In Gillotti v. Stewart (April 26, 2017) 2017 WL 1488711, which was ordered to be published on May 18, 2017, the defendant grading subcontractor added soil over tree roots to level the driveway on the plaintiff homeowner’s sloped lot. The homeowner sued the grading subcontractor under the California Right to Repair Act (Civil Code §§ 895, et seq.) claiming that the subcontractor’s work damaged the trees.
After the jury found the subcontractor was not negligent, the trial court entered judgment in favor of the subcontractor. The homeowner appealed, arguing that the trial court improperly construed the Right to Repair Act as barring a common law negligence theory against the subcontractor and erred in failing to follow Liberty Mutual Insurance Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98. The Third District Court of Appeal disagreed and affirmed the trial court’s judgment in favor of the subcontractor.
Impact
This is the second time the Third District Court of Appeal has held that Liberty Mutual (discussed below) was wrongly decided and held that the Right to Repair Act is the exclusive remedy for construction defect claims. The decision follows its holding in Elliott Homes, Inc. v. Superior Court (Hicks) (2016) 6 Cal.App.5th 333, in which the Court of Appeal held that the Right to Repair Act’s pre-litigation procedures apply when homeowners plead construction defect claims based on common law causes of action, as opposed to violations of the building standards set forth in the Right to Repair Act. Elliott is currently on hold at the California Supreme Court, pending the decision in McMillin Albany, LLC v. Superior Court (2015) 239 Cal.App.4th 1132, wherein Liberty Mutual was rejected for the first time by the Fifth District. CGDRB continues to follow developments regarding the much anticipated McMillin decision closely, as well as all related matters.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean Roeb & Barger and
Chelsea L. Zwart, Chapman Glucksman Dean Roeb & Barger
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Ms. Zwart may be contacted at czwart@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado’s New Construction Defect Law Takes Effect in September: What You Need to Know
September 07, 2017 —
Jesse Witt - The Witt Law FirmColorado’s new construction defect law officially takes effect this month. Although HB 17-1279 was passed in May, the statutory text provides that it only applies “with respect to events and circumstances occurring on or after September 1, 2017.” With that date now upon us, practitioners should be mindful of the law’s new requirements.
The law applies to any lawsuit wherein a homeowner association files a construction defect action on behalf of two or more of its members. “Construction defect action” is defined broadly to include any claims against construction professionals relating to deficiencies in design or construction of real property. Before an association may commence such an action, its board must follow several steps.
First, the board must deliver notice of the potential construction defect action to all homeowners and the affected construction professionals at their last known addresses. This requirement does not apply to construction professionals identified after the notice has been mailed, or to construction professionals joined in a previously-approved lawsuit. The notice must include a description of the alleged construction defects with reasonable specificity, the relief sought, a good-faith estimate of the benefits and risks involved, and a list of mandatory disclosures concerning assessments, attorney fees, and the marketability of units affected by construction defects. The notice must also call a meeting of all homeowners. The notice should be sent to the construction professionals at least five days before the homeowners.
Reprinted courtesy of
Jesse Howard Witt, Acerbic Witt
Mr. Witt may be contacted at www.witt.law
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Record Keeping—the Devil’s in the Details
July 30, 2015 —
Craig Martin – Construction Contract AdvisorAnother court has found that poor record keeping will prevent recovery on a claim. The court in Weatherproofing Tech., Inc. v. Alacran Contracting, LLC found that a contractor’s documents were a mess and that no reasonable jury could base a verdict on the contractor’s records.
The underlying project involved the construction of an army training facility. The total project cost approximated $13 million. Alacran, the general contractor, subcontracted about $3 million of the work to Weatherproofing Tech. Alacran paid Weatherproofing $700,000 for its work, even though Weatherproofing submitted invoices of more than $2 million. Alacran justified its refusal to pay Weatherproofing on the grounds that the parties had agreed to split the profit and loss on the project and the project was out of money. Not surprisingly, Weatherproofing sued Alacran for the amount owed.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Payment Bond Claim Notice Requires More than Mailing
June 18, 2019 —
Christopher G. Hill - Construction Law MusingsIt’s been a while since I posted something new relating to Virginia’s “Little Miller Act” and its various notice requirements for a subcontractor to make a payment bond claim.
I have posted on the basics of a Virginia payment bond claim previously here at Musings. One of these basics is the 90 day notice requirement for suppliers or second tier subcontractors with no direct contractual relationship to the general contractor. A recent case from the Norfolk, Virginia Circuit Court examined when notice is “given” under the Little Miller Act.
In R T Atkinson Building Corp v Archer Western Construction, LLC the Court looked at the question of whether mailing of the notice of claim is enough to constitute notice being “given” in a manner that would satisfy the statutory requirements. In that case, the supplier mailed the notice within the 90 day window, but the defendant argued on summary judgment that it did not receive the notice until 2 days after the 90 day window had closed. In support of this contention, the defendant provided tracking information showing delivery by the USPS on the non-compliant date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Insurer Must Cover Portions of Arbitration Award
October 14, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined that there was coverage in a construction defect case for portions of an arbitration award. Liberty Surplus Ins. Corp. v. Century Sur. Co., 2019 U.S. DIst. LEXIS 116093 (S.D. Texas July 12, 2019).
Descon Construction contracted with the City of Edinburg, Texas, to build a library. Descon subcontracted with McAllen Steel Erectors to install the library metal roof. The roof began to leak within two months of occupancy. The leaks continued for seven years.
Edinburg sued Descon. The matter was arbitrated. The arbitration panel found that the library roof was defective, the exterior stucco system was defectively installed and certain work, including fire-caulking, had not been performed. The panel concluded that Descon was liable for breach of contract and breach of warranty. The panel determined that Edinburg was entitled to replacement of the existing roof. Further, McAllen was found to have breached its subcontract with Descon by defectively installing the roof, entitling Descon to recover $762,537 from McAllen.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com