Duty to Defend Construction Defect Case Triggered by Complaint's Allegations
August 20, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe subcontractor's insurer could not escape contributing to defense costs of its insured when coverage was possible based upon the underlying complaint's allegations. Seneca Ins. Co. v. James River Ins. Co., 2014 U.S. Dist. LEXIS 97156 (D. Ore. July 17, 2014).
The underlying action alleged construction defects in a 60-unit complex located in Seaside, Oregon. S.D. Deacon Corp. was the general contractor and contracted with the owners association to reconstruct portions of the building, including the curtain wall. Deacon subcontracted with Superwall Design, LLP for work on the curtain wall renovation.
At some point not specified in the underlying complaint, the Association notified Deacon of construction defects in the curtain wall renovation. Deacon investigated and concluded that the alleged property damage was the result of inadequate usage of materials, violations of state and local building codes, and violations of relevant industry standards relating to the work performed by Superwall. Deacon contended that the problems were caused by Superwall's faulty workmanship.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Illinois Supreme Court Limits Reach of Implied Warranty Claims Against Contractors
April 10, 2019 —
Thomas Cronin - Gordon & Rees Construction Law BlogIn a recent decision, the Illinois Supreme Court held that a purchaser of a newly constructed home could not assert a claim for breach of the implied warranty of habitability against a subcontractor where the subcontractor had no contractual relationship with the purchaser. Sienna Court Condo. Ass’n v. Champion Aluminum Corp., 2018 IL 122022, ¶ 1. The decision overruled Minton v. The Richards Group of Chicago, which held that a purchaser who “has no recourse to the builder-vendor and has sustained loss due to the faulty and latent defect in their new home caused by the subcontractor” could assert a claim of a breach of the warranty of habitability against the subcontractor. 116 Ill. App. 3d 852, 855 (1983).
In Sienna Court Condo. Ass’n, the plaintiff alleged that the condo building had several latent defects which made individual units and common areas unfit for habitation. 2008 IL 122022 at ¶ 3. The Court rejected the plaintiff’s argument that privity should not be a factor in determining whether a claim for a breach of the warranty of habitability can be asserted. Id. at ¶ 19. The Court also rejected the plaintiff’s argument that claims for a breach warranty of habitability should not be governed by contract law but should instead be governed by tort law analogous to application of strict liability. Id.
The Court reasoned that the economic loss rule, as articulated in Moorman Manufacturing Co. v. National Tank Co., 91 Ill. 2d 69, 91 (1982), refuted the plaintiff’s argument that the implied warranty of habitability should be covered by tort law. 2008 IL 122022 at ¶ 20. Under the economic loss rule, a plaintiff “cannot recover for solely economic loss under the tort theories of strict liability, negligence, and innocent misrepresentation.” National Tank Co., 91 Ill. 2d at 91. The Court explained that the rule prevented plaintiffs from turning a contractual claim into a tort claim. 2008 IL 122022 at ¶ 21. The Court further noted that contractual privity is required for a claim of economic loss, and an economic loss claim is not limited to strict liability claims. Id. Because the plaintiff’s claim was solely for an economic loss, it was a contractual claim in nature; therefore, the Court concluded that “the implied warranty of habitability cannot be characterized as a tort.” Id. at ¶ 22.
Read the court decisionRead the full story...Reprinted courtesy of
Thomas Cronin, Gordon & Rees Scully MansukhaniMr. Cronin may be contacted at
tcronin@grsm.com
New Pedestrian, Utility Bridge Takes Shape on Everett Waterfront
December 16, 2019 —
Tim Newcomb - Engineering News-RecordAmidst the constraints of weight limits, a seawall, a waterfront restaurant and high-voltage power poles, crews from ICI Interwest Construction Inc. and heavy mover Oxbo Mega Transport Solutions positioned a $20 million, 282-ft-long pedestrian and utility bridge in place this fall along the Everett, Washington, waterfront.
Reprinted courtesy of
Tim Newcomb, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
ICE Said to Seek Mortgage Role Through Talks With Data Service
August 06, 2014 —
Matthew Leising, Jesse Hamilton and Jody Shenn – BloombergIntercontinental Exchange Inc. (ICE), best known for energy trading and its control of the New York Stock Exchange, is engaged in negotiations that would give it a foothold in the $9.4 trillion U.S. mortgage market.
ICE is in early stage talks to form a partnership with Mortgage Electronic Registration Systems Inc., which documents the ownership and resale of about half of U.S. home loans, according to a person familiar with the matter, who asked to not be identified because the discussions are private.
The Atlanta-based exchange owner has been gauging demand for derivatives that enable investors to bet on defaults by U.S. homeowners, Bloomberg News reported in May. ICE, which earns most of its revenue by owning one of the world’s largest derivatives markets, has recently expanded into new businesses such as equity trading with its 2013 purchase of NYSE Euronext and the administration of interest-rate benchmarks.
Mr. Leising may be contacted at mleising@bloomberg.net; Mr. Hamilton may be contacted at jhamilton33@bloomberg.net; Ms. Shenn may be contacted at jshenn@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Matthew Leising, Jesse Hamilton and Jody Shenn, Bloomberg
Miller Act Bond Claims Subject to “Pay If Paid”. . . Sometimes
November 04, 2019 —
Christopher G. Hill - Construction Law MusingsThe Federal Miller Act is a great tool that subcontractors and suppliers on Federal projects can use for collection of wrongfully withheld amounts due. However, as a recent federal case from the Eastern District of Virginia points out, the construction contract’s terms affect when a subcontractor or supplier can use this great collection tool and how much it can recover.
In Aarow v Travelers the Court looked at the interaction between a typical termination clause, a “pay when paid” clause, and the Miller Act. The key facts are these. The general contractor on the project at issue, Syska, did not get paid some disputed amounts by the owner and subsequently did not pay Aarow, the plaintiff and a subcontractor on the project. Aarow then refused to continue work and was terminated by Syska who then took over the completion of the work. Aarow sued, seeking damages for the value of its work prior to the termination. Travellers, the surety defended stating that, if Aarow was properly terminated for cause by Syska, then Aarow was not entitled to payment under the contract until such time as the work was completed and accepted by the owner. The termination clauses are set out in the linked opinion.
The Court agreed with Travelers, stating that the pay when paid clause created a situation whereby Aarow could not stop work merely because of a non-payment by Syska attributed to non-payment by the owner. The Court was clear in stating that the Miller Act trumps “pay when paid” in instances where the only cause for non-payment is non-payment by an owner. The Court then reasoned that it is the interaction between the termination and “pay when paid” provisions, and not the “pay when paid” clause itself, that exonerated Travelers because it created the default by Aarow due to its refusal to continue work. In short, Aarow was properly terminated for cause because it left the job without justification and therefore Travelers was not liable.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
No One to Go After for Construction Defects at Animal Shelter
January 28, 2013 —
CDJ STAFFThe Riverside County Animal Shelter in Thousand Palms has had problems since it opened in 2006, including floors that weren't able to withstand scratching by dogs and a malfunctioning HVAC system. The county's expenses only started with the $6.9 million cost of building the shelter, as the building has required almost constant repairs. Riverside County Supervisor John Benoit said that "there were shortcomings in the construction that became apparent later."
The County can't sue, because the builder closed operations after a bankruptcy. "There's no one to go after," said Benoit.
Read the court decisionRead the full story...Reprinted courtesy of
Newmeyer Dillion Attorneys Named to 2020 Southern California Rising Stars List
June 22, 2020 —
Newmeyer DillionProminent business and real estate law firm Newmeyer Dillion is pleased to announce that partner Eric Rollins and associates Jason Moberly Caruso and Richard Protzmann have been selected to the 2020 Southern California Rising Stars list by Super Lawyers. Each year, no more than 2.5 percent of the lawyers in the state are selected to receive this honor. The attorneys will be recognized in the June 2020 issues of Super Lawyers Magazine, Los Angeles Magazine and Orange Coast Magazine.
Eric Rollins, a partner in the Newport Beach office, provides legal counsel in a diverse array of practice areas with a focus on business, real estate, construction, insurance, and entertainment law. In his more than ten years at the firm, Eric has litigated and resolved hundreds of matters in both state and federal court through negotiation, mediation, arbitration, and trial. This is his third year as a Rising Star honoree.
Jason Moberly Caruso is an associate in the Newport Beach office. Jason's practice focuses on various aspects of "contaminated sites" environmental legal work, complex litigation, and appellate matters. This is the fifth consecutive year Jason has been honored.
Richard Protzmann is an associate in the Newport Beach office. Richard's practice focuses on focuses his practice on areas of business litigation, eminent domain, environmental law, zoning and land use, and general real estate litigation. This is the first year Richard has been selected.
Super Lawyers is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The patented selection process evaluates candidates on 12 indicators of peer recognition and professional achievement, resulting in a comprehensive, credible and diverse listing of exceptional attorneys. The Rising Stars list is developed using the same selection process except candidates must be either 40 years old or younger, or have been in practice for 10 years or less.
About Newmeyer Dillion
For 35 years, Newmeyer Dillion has delivered creative and outstanding legal solutions and trial results that achieve client objectives in diverse industries. With over 70 attorneys working as a cohesive team to represent clients in all aspects of business, employment, real estate, environmental/land use, privacy & data security and insurance law, Newmeyer Dillion delivers holistic and integrated legal services tailored to propel each client's operations, growth, and profits. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California and Nevada, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.newmeyerdillion.com.
Read the court decisionRead the full story...Reprinted courtesy of
Little Known Florida Venue Statue Benefitting Resident Contractors
June 30, 2016 —
David Adelstein – Florida Construction Legal UpdatesWhen it comes to
venue, there is a rather unknown venue statute that benefits resident contractors, subcontractors, and suppliers working on Florida projects. This statute,
Fla. Stat. s. 47.025, states:
Any venue provision in a contract for improvement to real property which requires legal action involving a resident contractor, subcontractor, sub-subcontractor, or materialman, as defined in part I of chapter 713, to be brought outside this state is void as a matter of public policy. To the extent that the venue provision in the contract is void under this section, any legal action arising out of that contract shall be brought only in this state in the county where the defendant resides, where the cause of action accrued, or where the property in litigation is located, unless, after the dispute arises, the parties stipulate to another venue.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at