Blackouts Require a New Look at Backup Power
April 06, 2020 —
John McBride - Construction ExecutiveRecent blackouts on both East and West coasts are causing commercial property owners to reassess their need for backup power. The likelihood of more-frequent blackouts means backup power must evolve from ensuring the safe exit of office workers to enabling core business functions to continue uninterrupted. That’s a major shift in preparedness that construction executives should consider in future planning.
In New York City on July 13, 2019, a Con Edison blackout left 72,000 customers in Manhattan and Queens without power primarily because of a flawed connection at an electrical substation. Eight days later, a second Con Edison blackout left more than 50,000 customers, mostly in Brooklyn, without power due to high usage during a heat wave. These events occurred even though, as Con Edison stated, the New York City grid is one of the most complex and technologically advanced in the world and contains multiple layers of redundancy.
In northern and central California in late October, 2019, intentional blackouts were implemented by Pacific Gas and Electric (PG&E) on a massive scale in response to out-of-control wildfires. “Never before in California history have more than 2 million people gone five days without electrical power because of the intentional safety policy of a utility,” reported the Los Angeles Times. It was the second massive blackout in California in two weeks, after PG&E had earlier shut off power to almost 2 million people in rolling blackouts.
The blackouts on both coasts are remarkable not only for their breadth but for the range of causes—from limiting wildfires sparked in part by faulty, above-ground, power lines to a flawed connection at a substation to overuse during a heat wave. The conditions creating those causes are not likely to subside, and Con Edison warned this summer of more service outages to come. In California, The Washington Post writes, “blackouts are redefining the prosperous state.”
Reprinted courtesy of
John McBride, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Top 10 OSHA Violations For The Construction Industry In 2023
February 26, 2024 —
Dominic Donato & Jeff Miragliotta - Kahana FeldEvery year, the Occupational Safety and Health Administration (OSHA) publishes their top violations in the construction industry. And typically, the most common violations are consistent year after year. What separates 2023 is the number of citations involving Fall Protection, Scaffolding, Ladders, and the failure to use personal protective equipment (PPE) or other life safety equipment (LSE). The following is the list of the Top Ten OSHA violations for 2023:
(10) Toxic and Hazardous Substances. There were 382 citations issued for “hazardous communication” and improper warnings issued to construction employees.
(9) Excavations. There were 395 citations issued for failure to provide proper and specific excavation requirements and instructions.
(8) Scaffolding – Aerial Lifts. There were 481 citations issued for improper lifting equipment and supports for building scaffolding.
Reprinted courtesy of
Dominic Donato, Kahana Feld and
Jeff Miragliotta, Kahana Feld
Mr. Donato may be contacted at ddonato@kahanafeld.com
Mr. Miragliotta may be contacted at jmiragliotta@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Holds “Notice-Prejudice” Rule is “Fundamental Public Policy” of California, May Override Choice of Law Provisions in Policies
November 12, 2019 —
Anthony L. Miscioscia & Timothy A. Carroll - White and Williams LLPOn August 29, 2019, in Pitzer College v. Indian Harbor Insurance Company, 2019 Cal. LEXIS 6240, the California Supreme Court held that, in the insurance context, the common law “notice-prejudice” rule is a “fundamental public policy” of the State of California for purposes of choice of law analysis. Thus, even though the policy in Pitzer had a choice of law provision requiring application of New York law – which does not require an insurer to prove prejudice for late notice of claims under policies delivered outside of New York – that provision can be overridden by California’s public policy of requiring insurers to prove prejudice after late notice of a claim. The Supreme Court in Pitzer also held that the notice-prejudice rule “generally applies to consent provisions in the context of first party liability policy coverage,” but not to consent provisions in the third-party liability policy context.
The Pitzer case arose from a discovery of polluted soil at Pitzer College during a dormitory construction project. Facing pressure to finish the project by the start of the next school term, Pitzer officials took steps to remediate the polluted soil at a cost of $2 million. When Pitzer notified its insurer of the remediation, and made a claim for the attendant costs, the insurer “denied coverage based on Pitzer’s failure to give notice as soon as practicable and its failure to obtain [the insurer’s] consent before commencing the remediation process.” The Supreme Court observed that Pitzer did not inform its insurer of the remediation until “three months after it completed remediation and six months after it discovered the darkened soils.” In response to the denial of coverage, Pitzer sued the insurer in California state court, the insurer removed the action to federal court and the insurer moved for summary judgment “claiming that it had no obligation to indemnify Pitzer for remediation costs because Pitzer had violated the Policy’s notice and consent provisions.”
Reprinted courtesy of
Timothy Carroll, White and Williams and
Anthony Miscioscia, White and Williams
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Check The Boxes Regarding Contractual Conditions Precedent to Payment
August 21, 2023 —
David Adelstein - Florida Construction Legal UpdatesRemember this: complying with contractual conditions precedent to payment is important. There is a reason why construction contracts include contractual conditions precedent to payment. The contract does not include this language for sh*ts and giggles. This language is included to establish what is required of the payee before payment becomes due. There may be conditions precedent to the payment of progress payments. There may be conditions precedent to the payment of final payment. Payment is not due until the conditions precedent have been satisfied. Do yourself a favor and consider this language in the construction contract, particularly if a dispute arises. If the condition precedent has not or cannot be satisfied, game plan as to the factual reason. The best thing to do is be prepared – check the boxes regarding conditions precedent to ensure you have considered this contractual language.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Pinnacle Controls in Verano
February 21, 2013 —
CDJ STAFFThe California Court of Appeals has applied the California Supreme Court’s recent Pinnacle decision to a new case, Verano Condominium Association v. La Cima Development. As in Pinnacle, La Cima sought to compel arbitration of construction defect claims with a homeowners association. The trial court denied La Cima’s attempt to compel arbitration on the grounds that the arbitration agreement was made with the individual homeowners and not the homeowners association. Further, it was determined that the CC&Rs “were unenforceable due to unconscionability.”
La Cima appealed, and the appeals court affirmed in part and reversed in part. After Pinnacle, La Cima sought a review. The Supreme Court of California directed the appeals court to vacate their earlier decision and reconsider, based on Pinnacle.
The Fourth Circuit Court has concluded that this conflicted with the ruling in Pinnacle. There, as in Verano, homeowners signed agreements that disputes with the developer would be settled through binding arbitration. The appeals court had found for the community association, but on review, the California Supreme Court reversed this decision.
The California Court of Appeals had two issue to consider in this review: whether the arbitration provisions applied to the homeowners association, and whether these provisions were unconscionable. The court concluded that “in light of Pinnacle it is clear the arbitration provisions set forth in the Verano CC&Rs constitute a valid agreement to arbitrate.” On the second question, the Verano CC&Rs were described by the court as “materially indistinguishable” from those in the earlier case. As the state Supreme Court found that those were not unconscionable, clearly neither were these.
The case was remanded for further proceedings and La Cima is entitled to recover the costs of the appeal.
Read the court decisionRead the full story...Reprinted courtesy of
California Home Sellers Have Duty to Disclose Construction Defect Lawsuits
October 21, 2013 —
CDJ STAFFIf you’re selling a home in California that has been the subject of a construction defect lawsuit, you probably have to disclose this, according to Steven G. Lee, an attorney at Reid & Hellyer. Mr. Lee notes that California law mandates the disclosure of “any lawsuits by or against the Seller threatening to or affecting the Property, including any lawsuits alleging a defect or deficiency.” He further notes that “for those selling units in a condominium or townhouse development, this includes defects in the common areas.”
He notes that failure to disclose will not invalidate the sale, but the seller may be “liable for actual damages suffered by the buyer.” Merely disclosing the former defect may not be enough. Mr. Lee notes that the California Court of Appeals ruled in one case that although buyers had been informed of past water intrusion, knowledge of the construction defect lawsuit may have affected the buyer’s decision.
Read the court decisionRead the full story...Reprinted courtesy of
CalOSHA Updates its FAQ on its COVID-19 Emergency Temporary Regulations
March 22, 2021 —
Garret Murai - California Construction Law BlogAs we reported in early December, CalOSHA adopted emergency temporary regulations requiring, among other things, that employers implement a written COVID-19 prevention program, that notice be given by employers to employees in the event of potential COVID-19 exposure, and that employers continue to pay employees who have been exposed to COVID-19 even if the employee has no paid time off available. In conjunction with the emergency temporary regulations, CalOSHA posted a FAQ on the emergency regulations.
On February 26, 2021, CalOSHA updated its FAQ. Among other things, the updated FAQ updates the following sections of the FAQ:
- Scope of Coverage: Clarifies that the emergency regulations apply even to workplaces with only one employee but that it does not apply to employees working remotely.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
LEED Certified Courthouse Square Negotiating With Insurers, Mulling Over Demolition
June 06, 2011 —
Douglas Reiser, Builders Council BlogApparently, Courthouse Square is still unresolved. The County hasnow hired an attorney to handle its insurance claim against Affiliated FM. Is there a lawsuit coming?
Right now, no lawsuit is expected. According to officials, the insurer has been acting in good faith. But, its been quite a while since Salem officials learned that the Courthouse Square building had significant concrete issues that would result in probable demolition of the LEED certified building.
If you have yet to hear about Courthouse Square, let me fill you in briefly. The Salem building was substantially completed in 2000 and LEED certified by the US Green Building Council in 2002. The project cost more than $30 Million to complete and the building was revered for its innovation as a crowning achievement for city leaders.
But, structural problems in the building’s core were discovered as early as 2002, writes Chris Cheatham of Green Building Law Update. Final tests earlier in the year, determined that the building had to be vacated. The building has been clear since July 2010.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of