Public Works Bid Protests – Who Is Responsible? Who Is Responsive?
December 14, 2020 —
Eric Divine - Porter Law GroupMost Public Works Solicitations Are Low Bid
The process for awarding public works projects in California is controlled by the Public Contract Code. Generally, regardless of whether the public agency is the State, a county, a city or a local district, the project is awarded to the contractor who is “responsible” and submits the least expensive “responsive” bid. This is generally known as a “low bid” contract. In the context of public works, the terms responsible and responsive have very important meanings. As a result, State and local governments have gotten into very expensive trouble for not following the law. So, to understand how to best present a bid protest on a low bid solicitation, you, as a contractor should have a good understanding of the meaning of these terms.
Note: There are other methods of contracting for public works that are not low bid, which are typically called “best value” contracts because the procurement process considers factors other than just price. These methods are typically used for large projects because the added complexity and expense of the procurement process only makes sense when the project is itself complex and expensive.
Read the court decisionRead the full story...Reprinted courtesy of
Eric Divine, Porter Law GroupMr. Divine may be contacted at
edivine@porterlaw.com
Failure to Consider Safety Element in Design Does Not Preclude Public Entity’s Discretionary Authority Under Design Immunity Defense
May 16, 2018 —
Garret Murai - California Construction Law BlogIn Rodriguez v. Department of Transportation, Case No. F074027 (March 27, 2018), the Court of Appeals for the Fifth District considered the following mind-twister: Can you knowingly approve something (which does not include something else) if you never considered the absence of that “something else?” Think about that for a moment . . . or, better yet, just read on.
Rodriguez v. Department of Transportation
In 2013, a pickup truck traveling westbound on State Route 152 toward Los Banos, California, ran off the road injuring Erik Rodriguez and the driver and killing another passenger. Rodriguez sued the California Department of Transportation (Caltrans) on the ground that the accident was caused by a dangerous condition on public property.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Why You Make A Better Wall Than A Window: Why Policyholders Can Rest Assured That Insurers Should Pay Legal Bills for Claims with Potential Coverage
March 14, 2018 —
Alan Packer and Graham Mills - Newmeyer & Dillion, LLPUnfortunately, policyholders, such as manufacturers and contractors, routinely face the unnecessary challenge of how to access all of the insurance coverage which they have purchased. Frequently, the most pressing need is to get the insurance company to pay the legal bills when the policyholders have been sued. The recent Iowa federal district court opinion in
Pella Corporation v. Liberty Mutual Insurance Company should help a policyholder in a dispute to require its insurance company to pay those legal bills sooner rather than later by highlighting that the duty to defend arises from the potential for coverage, and the insurer may not force the policyholder to prove the damage to obtain a defense.
In
Pella, a window manufacturer purchased several years of insurance coverage from Liberty Mutual. Similar to many companies, Pella had many “layers” of insurance coverage in any given year. These layers collectively function like a tower. The general idea is that each layer provides a certain amount of coverage after the insurance policy below it had paid its money. The Liberty Mutual insurance policies provided excess coverage.
After the
Pella window manufacturer made and sold its windows, it was sued in numerous lawsuits alleging that its windows were defective and that those defective windows caused a wide variety of damage to the structures in which they were installed. The window manufacturer tendered those lawsuits to its insurance companies in its tower of coverage, asking that the insurance companies pay its legal bills incurred in its defense. As to Liberty Mutual, the window manufacturer argued that the Liberty Mutual insurance policies were triggered, and so obligated to reimburse it, if a window was installed during the years that those policies provided coverage or if there was a mere allegation that a window was installed during the years that those policies provided coverage. Liberty Mutual opposed, arguing that the date of installation of the windows was insufficient to trigger the policies, and that the manufacturer was required to demonstrate the date that damage actually occurred to trigger a defense.
The key issue before the
Pella Court in this decision was a simple one: which insurance policies, if any, issued by Liberty Mutual had an obligation to pay the window manufacturer’s legal bills? The answer to that question is critical and financially significant. Getting an insurance company to honor its obligations and start paying the legal bills as soon as possible is very important for a policyholder because of the cost of defending oneself in a lawsuit; often the key reason why an insurance policy is even purchased is to provide the policyholder with the right to call upon the insurance company’s financial resources to defend it should it be sued.
In a ruling that will be welcomed by policyholders, the
Pella Court held that Liberty Mutual’s multiple insurance policies were triggered, and so obligated to pay for the window manufacturer’s defense, if one of two events occurred during the years in which those insurance policies provided coverage: (1) a window was actually installed during a year when the insurance policy provided coverage or (2) the window was alleged to be installed in the year that the insurance policy provided coverage. The Court agreed with the policyholder that once the windows were installed, property damage was alleged and “may
potentially have occurred” from that point on, thus the policies on the risk from that point forward. The practical effect of this ruling meant that Liberty Mutual had to reimburse the window manufacturer for the defense fees and costs that it had paid.
While
Pella was decided under Iowa law, the principles upon which it relied are similar to those applied under California law. Importantly, both California and Iowa law hold that an insurance company must provide a defense in response to a claim that is, or could be, covered by the insurance policy. The mere potential that the claim might be covered is enough for the insurance company to be obligated to pay for policyholder’s legal fees and costs.
Establishing that an insurance company must pay legal fees and costs as soon as possible allows a policyholder to save its own money. Why should a policyholder pay legal bills when it purchased an insurance policy as protection to ensure that it did not have to pay those bills? The answer is that a policyholder should not and, under
Pella, the policyholder does not have to. Rather, the insurance company must start paying for that defense from a very early date. Pella confirms for policyholders the position that their insurance companies should pay legal bills earlier rather than later.
Alan Packer is a partner in the Walnut Creek office for Newmeyer & Dillion, LLP, representing homebuilders, property owners, and business clients on a broad range of legal matters, including risk management, insurance matters, wrap consultation and documentation, efforts to counter solicitation of homeowners, subcontract documentation, as well as complex litigation matters. Alan can be reached at alan.packer@ndlf.com.
Graham Mills is a partner in the Walnut Creek offce of Newmeyer & Dillion, LLP, representing clients in the area of complex insurance law with an emphasis on insurance recovery, construction litigation, real estate litigation, and business litigation. He regularly examines and analyzes a wide variety of insurance policies. Graham can be reached at graham.mills@ndlf.com.
ABOUT NEWMEYER & DILLION LLP
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review’s AV Preeminent® highest rating.
For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Incorporation, Indemnity and Statutes of Limitations, Oh My!
January 19, 2017 —
Christopher G. Hill – Construction Law MusingsWe all know that the contract is king in Virginia. We also know that Virginia will allow for a so called “incorporation” clause that will allow for “flow down” of certain prime contract provisions in a way that will make those provisions applicable to subcontractors. We also know that a claim for breach of contract or other contractual claim does not last forever due to certain statutes of limitation found in the Code of Virginia. What happens when all of these elements crash together in one place leading to litigation? Well, a relatively recent case from the Virginia Supreme Court gives at least a partial answer.
In Hensel Phelps Construction Company v Thompson Masonry Contractor, Inc, the Virginia Supreme Court considered a claim that arose from construction at Virginia Tech by Hensel Phelps. The construction concluded in 1998 (remember that date). The Prime Contract included language concerning a one year “Guarantee of Work” as well as fairly typical Warranty of Workmanship” language. However the Prime Contract also stated that the one year guaranty term did nothing to affect any other limitations period for any other action pursuant to the Prime Contract (this is important as well because Virginia Tech was not subject to any statute of limitations due to its status as an agency of the Commonwealth of Virginia). Final payment was made to Hensel Phelps and subsequently to the subcontractors in 1999.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Las Vegas’ McCarran Tower Construction Issues Delays Opening
August 13, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Las Vegas Review-Journal reported that an improperly applied chemical coating might delay the opening of McCarran International Airport’s Federal Aviation Administration tower by a year and cost millions of dollars to repair.
The chemical coating was intended “to prevent the spread of toxic fungus,” but was “improperly applied and is ineffective,” workers on the site told the Las Vegas Review-Journal.
“Officials said the” $99 million, 352-foot “tower was expected to be operational by 2015, but the FAA now says it won’t be able to use the facility until late 2016 or early 2017.”
Read the court decisionRead the full story...Reprinted courtesy of
Construction Executives Should Be Dusting Off Employee Handbooks
January 03, 2022 —
Adam E. Richards & Andrew Zelman - Construction ExecutiveFor most businesses—large and small—the importance of maintaining and updating an employee handbook that sets forth a uniform set of company policies cannot be understated. The construction industry, which is seemingly plagued by a never-ending labor shortage, necessitating construction executives having to grapple with pandemic-related workplace issues and challenges, is not exempt from the benefits of a thorough, well-formed handbook.
The employee handbook should be a window into the soul of a business. Even though annual updates are appropriate, they seldom occur. To say a lot has happened over the last few years barely begins to scratch the surface. Particularly, during the COVID-19 pandemic, construction executives and human resources professionals within construction-related businesses throughout the country have been forced to evaluate business models, values and cultures in furtherance of deciding where and how to evolve.
Once those decisions are made, the employee handbook is deserving of time and attention. Reflecting the evolution of your construction business is only part of the overall plan; however, demonstrating compliance with new laws is equally important.
Reprinted courtesy of
Adam E. Richards & Andrew Zelman, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Creative Avenue for Judgment Creditor to Collect a Judgment
October 27, 2016 —
David Adelstein – Florida Construction Legal UpdatesI have a judgment against another entity. Now what? I want to briefly talk about this “now what?” in the context of the recent decision in MYD Marine Distributor, Inc. v. International Paint, Ltd., 41 Fla. L. Weekly D2364a (Fla. 4th DCA 2016). Although this case is not a construction case, it poses an interesting issue for any entity that has a judgment entered against it (known as the judgment debtor) while it is contemporaneously the plaintiff and pursuing monetary damages in an unrelated case or cases. This case also presents an avenue for any judgment creditor to pursue in the event other post-judgment collection efforts are unsuccessful.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
Commercial Construction Lenders Rejoice: The Pennsylvania Legislature Provides a Statutory fix for the “Kessler” Decision
July 16, 2014 —
Thomas C. Rogers – White and Williams LLPIn May 2012, the Pennsylvania Superior Court rendered its now infamous “Kessler” decision. The Kessler decision resulted in fundamental changes in the operation of the Pennsylvania Mechanics Lien Act as it applied to construction loans where the visible commencement of work on the project commenced before the recordation of the construction loan’s open-end mortgage.
Essentially, the Kessler decision held that if the visible commence of work on the project began prior to the recording of the open-end mortgage and any loan advances were made other than for what are commonly considered “hard construction” costs, then any unpaid contractors and subcontractors who later filed mechanics’ liens would have their liens take priority over the lien of all of the construction loan advances.
Subsequent to the Kessler decision, both the lending and title insurance communities in Pennsylvania have struggled mightily to structure deals around the problems created by Kessler and to provide lenders with title insurance coverage for construction loans when work commenced before the recordation of the open-end mortgage.
Read the court decisionRead the full story...Reprinted courtesy of
Thomas C. Rogers, White and Williams LLPMr. Rogers may be contacted at