Professional Services Exclusion in CGL Policies
December 05, 2022 —
David Adelstein - Florida Construction Legal UpdatesA professional services exclusion in a commercial general liability policy means something. It’s an exclusion an insurer will rely on to avoid insurance coverage based on “professional services” performed or rendered by the insured. Don’t take it from me. Take it from the recent opinion in Colony Insurance Company v. Coastal Construction Management, LLC, 2022 WL 16636697 (M.D.Fla. 2022) where the trial court granted a commercial general liability insurer’s motion for judgment on the pleadings based on the professional services exclusion.
Here, an owner sued, among other parties, an entity performing only construction management services based on construction defects at its project. The construction manager did not perform any design or physical construction. It was hired to make site inspections of the construction, review construction quality and finish standards, ensure workmanship quality, coordinate the punchlist process, and supervise management and administration of the project.
The construction manager’s commercial general liability insurer sued for declaratory relief claiming it owed no duty to defend or indemnify based on the professional services exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
District Court Awards Summary Judgment to Insurance Firm in Framing Case
August 04, 2011 —
CDJ STAFFIn the case of Continental Western Insurance Company v. Shay Construction Inc., Judge Walker Miller has granted a summary judgment against Shay Construction and their co-defendant, Milender White Construction Company.
Shay was the framing subcontractor for Milender White on what the court described as “a major construction project in Grand County, Colorado.” Two of Shay’s subcontractors, Wood Source Inc. and Chase Lumber Company furnished materials, labor, and equipment to Shay. They subsequently sued for nonpayment and sought to enforce mechanic’s liens, naming both Shay and Milender as defendants. Milender White alleged that Shay had “breached its obligation under its subcontracts with Milender White.”
Shay’s insurance provider, Continental Western, stated that its coverage did not include “the dispute between Shay, its subcontractors, particularly the cross claims asserted by Milender White.” Shay then sued Continental Western, alleging breach of contract and statutory bad faith.
The court, however, has found with Continental Western and has granted them a summary judgment. They found “no genuine issue as to any material fact.” The judge did not side with Continental Western on their interpretation of the phrase “those sums that the insured becomes legally obligated to pay as damages.” The court found that the Colorado courts have not limited this to tort actions only. However, as Milender’s cross claim included claims of faulty workmanship on the part of Shay, Judge Miller found for Continental.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Everyone’s Working From Home Due to the Coronavirus – Is There Insurance Coverage for a Data Breach?
May 18, 2020 —
Heather Whitehead & Jeff Dennis - Newmeyer DillionMost organizations are now requiring that their employees work from home (“WFH”) with the ongoing COVID-19 (commonly referred to as the Coronavirus) pandemic. These remote working arrangements provide new opportunities for hackers to infiltrate computer systems, and not surprisingly, attempted cyber attacks are on the rise. Given the rapid deployment of employees being forced to work from home, many employees are using their personal laptops, tablets and other devices to complete their work. The use of such personal devices increases the risk to network systems, including a potential breach or data loss.
However, in the event of a breach or other incident, there may be limitations in your cyber liability insurance policy based upon the type of hardware being used. Businesses need to be proactive to protect themselves from attacks by practicing vigilant cyber safety, and also reviewing their insurance policies in detail for coverage considerations prior to the occurrence of any cyber incident.
Reprinted courtesy of
Heather H. Whitehead, Newmeyer Dillion and
Jeffrey M. Dennis, Newmeyer Dillion
Ms. Whitehead may be contacted at heather.whitehead@ndlf.com
Mr. Dennis may be contacted at jeff.dennis@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurers Refuse Indemnification of Subcontractors in Construction Defect Suit
November 13, 2013 —
CDJ STAFFSMG Stone Co. Inc. and J. Colavin & Son Inc. were hired by Webcor Construction LP to install stone floor tiles at the Ritz-Carlton residences at the L.A. Live complex in Los Angeles. But the tiles began to crack even before installation was finished. The building management had all the tiles ripped out and replaced, although only 10% of the tiles were defective. The building management then claimed Webcor owed them $40 million, but settled for $8 million.
$7 million of that claim was paid by Steadfast Insurance Co., with the remaining $1 million paid by Webcor. The two other insurers involved, American Home and The Insurance Company of the State of Pennsylvania, are attempting to deflect Webcor or Steadfast from making claims against them.
Both insurers claim no obligation to indemnify the contractor or subcontractors as the claims do not involved “property damage,” as defined in the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Appeals Court Finds Manuscript Additional Insured Endorsements Ambiguous Regarding Completed Operations Coverage for Additional Insured
September 07, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Pulte Home Corp. v. American Safety Indemnity Co. (No. D070478; filed 8/30/17), a California appeals court found that manuscript additional insured endorsements on construction subcontractors’ policies were ambiguous regarding additional insured coverage for the developer, and that substantial evidence supported a finding that the insurer’s refusal to defend the developer was in bad faith. The court also approved awarding punitive damages on a one-to-one basis with the general damages. But the appeals court remanded the case for a further determination on the amount of Brandt fees, based on the developer’s change from a contingency to an hourly agreement.
The Pulte case arose from the development of two residential housing projects beginning in 2003 and sold in 2005-2006. Subcontractors were required to name Pulte as additional insured on their policies, some of them issued by American Safety. In 2013, homeowners sued Pulte based in part on the work of subcontractors insured by American Safety, which then denied coverage to Pulte because the construction had taken place years earlier.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Home Buyer Disclosures, What’s Required and What Isn’t
February 05, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to Sandy Gadow of the Washington Post, while all states require a property disclosure statement, “the extent of what must be revealed can vary from state to state, county to county and even city to city.” Gadow stated that while, “Federal law requires certain disclosures, such as the existence of asbestos or lead-based paint in the home or other known health or safety risks. But the enforcement of other disclosures (such as reporting certain environmental conditions pertinent to the area, or the existence of Megan’s Law offenders) will be determined by local ordinance or law.”
Gadow recommends home buyers go to their state’s Department of Real Estate to discover the Seller Disclosure requirements.
Read the court decisionRead the full story...Reprinted courtesy of
San Francisco Airport’s Terminal 1 Aims Sky High
January 06, 2020 —
Aileen Cho - Engineering News-RecordEach night, a prancing robotic dog roves the site of Terminal 1 at San Francisco International Airport (SFO), taking photographs of construction on the new terminal, which replaces a 1960s-era building with nearly 900,000 sq ft of state-of-the-art space. The $2.6-billion Harvey Milk terminal is the highlight of a $7.2-billion capital plan. “We are about halfway through,” says Geoff Neumayr, chief development officer for SFO. The program includes a 3,600-space parking garage, a consolidated office campus, a new hotel, a waste treatment plant, improvements to Terminal 2 and the international terminal, and a new on-airport train station. This summer the first nine gates opened at Terminal 1, with nine more slated to open next year and a completion date of 2023 with 25 total gates, including two that will accommodate Airbus A380s double-decker planes.
Aileen Cho, Engineering News-Record
Ms. Cho may be contacted at choa@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Contract Should Have Clear and Definite Terms to Avoid a Patent Ambiguity
December 11, 2023 —
David Adelstein - Florida Construction Legal UpdatesIf you need more of a reason to have contracts with clear and definite terms, this case is it. This case exemplifies what can happen if the contract, not only does not have clear and definite terms, but contains a patent ambiguity. The contract will be deemed unenforceable which will make one of the contracting parties very unhappy!
In Bowein v. Sherman, 48 Fla.L.Weekly D2208a (Fla. 6th DCA 2023), the buyer and seller entered into a real estate transaction. The transaction was for $2 Million. The purchase-and-sale agreement included the address and legal description of a parcel to be sold. However, there was a section in the agreement called “Other Terms and Conditions” which identified that the offer was actually for four properties that were being sold by the seller. When it came to closing time, the seller refused to close because the seller disputed that the $2 Million purchase price was for all four of his properties. The buyer sued the seller for specific performance to force the sale which the trial court agreed in favor of the buyer. However, the appellate court did not.
First, the appellate court held that “[t]he equitable remedy of specific performance may be granted only where the parties have actually entered into a definite and certain agreement.” Bowein, supra (quotation and citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at