Construction Delays for China’s Bahamas Resort Project
October 01, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Wall Street Journal reported that the $3.5 billion resort and casino China’s building in the Bahamas is being undermined by delays and labor crashes, which is “dulling the buzz surrounding the venture and threaten to undermine China's future business.”
Once finished, the project “will include 2,200 new hotel rooms, luxury condominiums priced as high as $12 million, a 100,000-square-foot casino and an 18-hole golf course. Singer Lenny Kravitz is designing the nightclub.”
Baha Mar, the developers, told the Wall Street Journal that they will not be meeting their December 2014 deadline, and instead are “focused on late spring 2015.”
Read the court decisionRead the full story...Reprinted courtesy of
What Every Project Participant Needs to Know About Delay Claims
August 05, 2024 —
Andrew G. Vicknair - The Dispute ResolverA “delay” on a construction project is defined as the stretching out of the time for completion of certain key milestone scopes of work which can impact the completion date of an entire project, due to some circumstances or events that were not reasonably anticipated when the project began. 2 Construction Law ¶ 6.01 (Matthew Bender, 2024). While delays can be caused by any number of events, the most common are defective plans and specifications; design changes; severe weather and other, similar unforeseeable events; unforeseen or differing site conditions; unavailability of materials or labor; labor inefficiencies or stoppages; contractor negligence; and owner influences, including construction changes or outright interference by the owner or its agents. If the project schedule is not recovered following a delay, then the project schedule will likely be extended, resulting in an increase in the contractor’s costs of performance. A contractor that has experienced a delay on a project can take certain actions to pursue recovery of any damages the contractor may have incurred. However, to do so it is important to understand the different types of delays and the methods for establishing the delays.
I. Types of Delays
Delays may be categorized as (1) critical versus non-critical delays, (2) excusable versus non-excusable delays, and (3) compensable versus non-compensable delays. A critical delay is a delay that affects the project completion date and delays the entire project. In essence, a critical delay is one that will extend the critical path of a project. A non-critical delay is a delay that has no effect on the project’s critical path. Courts have recognized that delays to work not on the critical path will generally not delay the completion of a project. G.M. Shupe, Inc. v U.S., 5 Cl. Ct. 662, 728 (1984). Such a non-critical delay may affect the completion of certain activities, but does not affect the completion date of the entire project. In order for a delay to provide the basis for a claim for additional time or money, the delay must impact critical path activities on the project schedule.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew G. Vicknair, D'Arcy Vicknair, LLCMr. Vicknair may be contacted at
agv@darcyvicknair.com
The Legal Landscape
June 17, 2024 —
David McMillin - Construction ExecutiveThe construction industry continues to change as new technologies reshape jobsites and new generations of leaders rethink the way companies should operate. But one piece of the puzzle remains very much the same: Everyone needs a good lawyer.
According to the most recent edition of the Arcadis Construction Disputes Report, the average value of a dispute in the industry has soared to $42.8 million—a 42% year-over-year increase between 2021 and 2022. And based on how busy the attorneys at
Construction Executive’s 2024 Top 50 Construction Law Firmshave been this year, there is no sign of legal issues becoming less important to builders and contractors.
Every construction leader wants to spend more time and energy doing what they do best—building projects safely, efficiently and profitably—and less time thinking about the things that might land them in court. How can you best avoid big disputes bound for mediation, arbitration or litigation? What emerging rules and regulations should be on your radar as you develop strategies for success?
While legal issues will never disappear, listening to what some of the best construction lawyers in the country—all members of 2024 Top 50 Construction Law Firms—are thinking about offers a helpful perspective on future-proofing your business against risk, liability and worse.
Reprinted courtesy of
David McMillin, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
The Future of Pandemic Coverage for Real Estate Owners and Developers
November 09, 2020 —
Ashley McWilliams - Saxe Doernberger & VitaShutdowns resulting from the COVID-19 pandemic have prompted an unprecedented number of business income and business interruption insurance claims. Many claims have resulted in litigation and require judicial intervention to determine whether private insurance carriers owe policyholders indemnification for pandemic related losses. Private insurance carriers that have denied the claims, in large part, argue that they did not underwrite coverage for the pandemic and assert that pandemic coverage is much too unpredictable to underwrite. Private carriers contend that a government-backed insurance program is necessary to mitigate the economic impact resulting from pandemic claims.
The COVID-19 pandemic has significantly impacted real estate owners and developers. Real estate owners and developers have sustained business income losses in the form of lost rents at commercial properties, service disruption, labor and/ or material shortages, to name a few. Questions about whether the virus caused “direct physical damage,” as well as whether specific “virus exclusions” on policies, have provided hurdles to coverage under existing schemes, click here.Those that have filed lawsuits against their insurers seeking coverage under current policy terms are having mixed results, at best. Click here to view SDV’s Litigation Tracker. A predictable source of indemnification for future pandemic-related losses would greatly relieve business disruption and, ultimately, the impact on the economy. However, the question remains, who will pay for such massive losses?
Read the court decisionRead the full story...Reprinted courtesy of
Ashley McWilliams, Saxe Doernberger & VitaMs. McWilliams may be contacted at
AMcWilliams@sdvlaw.com
Sanctions Issued for Frivolous Hurricane Sandy Complaint Filed Against Insurer
February 26, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court for the district of New Jersey cracked down on a Texas law firm that filed 250 Hurricane Sandy related cases against insurers without adequate investigation. Lighthouse Point Marina & Yacht Club, LLC v. Int'l Marine Underwriters, 2015 U.S. Dist. LEXIS 6430 (D. N.J. Jan. 20, 2015).
The Texas firm filed more that 250 actions in New Jersey courts against insurers to recover for alleged property damage caused by Hurricane Sandy. The original complaints were nearly identical with the same typos. The complaint in this case alleged that the insurer did not pay benefits under the policy for "extreme external and internal damages, as well as other wind-related loss," but did not specify the value or nature of the damage. The insurer answered that it sent an adjuster to the property soon after the storm and found wind damages to two fences, but no damage to any building on the property. The adjuster valued the claim at $1,612.00 and recommended a payment of $612.00, after applying the $1000 deductible.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
In All Fairness: Illinois Appellate Court Finds That Arbitration Clause in a Residential Construction Contract Was Unconscionable and Unenforceable
August 22, 2022 —
Gus Sara - The Subrogation StrategistIn Bain v. Airoom, LLC, No. 1-21-001, 2022 Ill. App. LEXIS 241, the Appellate Court of Illinois (Appellate Court) considered whether the lower court erred in enforcing an arbitration clause in a construction contract between the parties and, as a result, dismissing the plaintiff’s lawsuit. The Appellate Court found that even if the arbitration clause was enforceable, the appropriate action would have been for the court to stay the lawsuit, as opposed to dismissing the case entirely. The Appellate Court then considered the language of the arbitration clause and found that several provisions were substantively unconscionable, which rendered the entire arbitration clause unenforceable. The Appellate Court reversed the lower court’s decision compelling arbitration and reinstated the plaintiff’s complaint.
In 2018, the plaintiff, Ms. Bain, a disabled senior citizen, hired the defendant, Airoom, LLC (Airoom), to renovate her home. Airoom provided its “Cash Sales Contract,” which included a binding arbitration clause. The clause required that any dispute arising or relating to the contract be resolved by binding arbitration through the American Arbitration Association (AAA), using the Construction Industry Arbitration Rules and Mediation Procedures (Construction Industry Rules).
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Expansion of Statutes of Limitations and Repose in K-12 and Municipal Construction Contracts
March 27, 2019 —
Henry Bangert - Colorado Construction LitigationThe purpose of this whitepaper is to bring attention to a trend in K-12 and municipal construction contracts, which expands the time periods for law suits against construction professionals.
Introduction and Background
Under Colorado statute, the period of time within which a legal action for construction defects may be brought against a construction professional in Colorado is two years from when the claimant (or its predecessor in interest) discovers or in the exercise of reasonable diligence should have discovered the physical manifestations of a defect (the “Statute of Limitations”), but in no case may an action be brought more than six years after substantial completion of the improvement, unless the claim arises in the fifth or sixth year after substantial completion, in which event the action may be brought within two years of such date, i.e., up to eight years after substantial completion (the “Statute of Repose”). See C.R.S. § 13-80-104. While the triggering events differ for the Statute of Limitations and Statue of Repose, the periods are intended to run concurrently to limit the period of time an action may be brought against construction professionals for construction defects to, at most, eight years after substantial completion. Importantly, these limitations periods may be expanded by agreement.
Prior to 1986, Colorado law provided for a 10-year Statute of Repose. However, in 1986, Colorado’s legislature shortened the Statute of Repose time limit to the current six (or up to eight) year period. In 1986, Colorado also redefined the date the claim arises from the date the defect was discovered or should have been discovered to the date the physical manifestation of a defect was discovered or should have been discovered. Therefore, after 1986, the two-year limitations period could begin to run when a claimant should have discovered the manifestation of a defect, even if the claimant did not recognize that a defect existed.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Best Practices: Commercial Lockouts in Arizona
April 15, 2024 —
Patrick Tighe - Snell & Wilmer Real Estate Litigation BlogIf a tenant defaults under a commercial lease, Arizona law permits the landlord to re-take possession of the premises by locking out the defaulting tenant. However, if the landlord’s lockout is wrongful, the landlord may be liable for the damages the tenant sustains because of the wrongful lockout. To minimize such liability, here are some general best practices to follow when locking out a defaulting tenant:
- Do Not Breach the Peace. It is vital when performing a lockout to not breach the peace. What constitutes a “breach of the peace” depends on the particular circumstances at hand. For example, if a tenant arrives during the lockout and becomes angry or threatens violence, the landlord should stop performing the lockout and return at a later time. As a general rule of thumb, it is best to perform lockouts in the early morning hours or in the late evening hours when the landlord is less likely to encounter the tenant.
- Provide A Notice of Default. Many commercial leases require the landlord to provide a notice of default before the landlord can lock out a defaulting tenant. Check, double check, and triple check that the landlord followed the lease’s notice of default provisions correctly, including that the landlord sent the notices to all required parties in accordance with the time requirements set forth in the lease.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Tighe, Snell & WilmerMr. Tighe may be contacted at
ptighe@swlaw.com