It Ain’t Over Till it’s Over. Why Project Completion in California Isn’t as Straightforward as You Think
May 07, 2015 —
Garret Murai – California Construction Law BlogBaseball legend Yogi Berra was famous for his pithy quotes such as “the future ain’t what it used to be,” “half the lies they tell about me aren’t true,” and what is probably his most famous, “it ain’t over till it’s over.”
The last, of course, begs the question of when over is over? And, on California construction projects when over is over, or more accurately, when a project is complete, can be as paradoxical as a “yogiism.”
Why “Completion” is Important in California
In California, project “completion,” is important not only for getting paid, but for knowing the deadlines associated with California’s statutory construction payment remedies.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
VOSH Jumps Into the Employee Misclassification Pool
February 23, 2016 —
Christopher G. Hill – Construction Law MusingsThe proper classification of workers by construction companies has been on the radar of the Department of Labor for both the US and Virginia governments for quite a while. While most of the misclassification is innocent and not done to create issues, there have been enough instances of purposeful misclassification of certain workers as independent contractors (thus avoiding workers comp and other payroll expenses) that innocent contractors have born the brunt of these issues through increased payroll costs over those that misclassify (in the form of necessarily higher bids, higher overhead, etc.).
As an additional deterrent to improper classification of workers, the Virginia Department of Labor and Industry has issued guidelines for what will occur in Virginia Department of Safety and Health (VOSH) cases.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
When Business is Personal: Negligent and Intentional Interference Claims
October 24, 2023 —
Kathryne Baldwin & Jose L. Parra - Wilke FleuryThe nature of business is personal. Changes in personnel, project outlines, or business models cost businesses time and money to bring about, ward against, or stop. Any individual involved in business will likely have seen claims for interference with relationships, either prospective or contractual. But, what do those claims really mean and how viable are they in a capitalist society where free markets are held in such high esteem?
Defendants in lawsuits will typically see these claims pleaded as one of three major categories: intentional interference with prospective economic advantage, intentional interference with contractual relations or contract, or negligent interference with prospective economic advantage. As the name would suggest, the first two are more concrete and require a showing that the bad actor was aware of the existence of a contract or relationship and took affirmative steps to interfere with that relationship. The latter is more nebulous and looks at business relationships that were likely to occur and are based on a “should have known” standard.
Reprinted courtesy of
Kathryne E. Baldwin, Wilke Fleury and
José L. Parra, Wilke Fleury
Ms. Baldwin may be contacted at kbaldwin@wilkefleury.com
Mr. Parra may be contacted at jparra@wilkefleury.com
Read the court decisionRead the full story...Reprinted courtesy of
Top 10 Construction Contract Provisions – Changes and Claims
November 03, 2016 —
James R. Lynch – Ahlers & Cressman PLLCThis is the seventh post in our “Top 10 Construction Contract Provisions” series. Prior posts discussed
Price and Payment,
Liquidated Damages,
Consequential Damages – Part I and
Part II,
Indemnity,
Scope of Work, and
Flow-Down Provisions.
Today’s topic, Changes and Claims, is a contender for the top spot on our list, for both day-to-day impact on the job and importance in disputes. In fact, these provisions[i] are so variable and are involved in so many reported construction law decisions, that this post will not attempt to survey all their various forms, uses, or potential legal ramifications, but instead focuses on bottom line “best practices”—questions to consider as a general contractor, subcontractor, or owner when drafting, negotiating, or managing the Changes and Claims provisions of a contract. There is no “ideal” here, and the changes and claims procedures should be suited to the project, owner, contractor(s), likely issues, and other project-specific considerations. Key considerations include the following:
1. How prescriptive is the Change Order process? At one end of the spectrum, a Change Order provision may include requirements for written direction and request by the owner and formal response by the contractor, with pricing and specific supporting data or documentation, in addition to strict timelines for response, execution, and performance, precise methods to determine the resulting contract adjustment, limits on the type or extent of adjustment, or terms defining the effect of a signed Change Order, e.g. to what extent related claims or impacts might be extinguished. At the other end of the spectrum, the Change Order provision might simply recognize that the owner may direct changes, and the parties intend to document the directions and resulting compensation in a Change Order, with no further elaboration. There is no universal ideal on this spectrum. A highly defined and prescriptive process may be appropriate for a complex, high value, multi-stakeholder project on which significant changes are likely. The same process would be an inefficient waste of resources on a small and simple project where significant changes are unlikely and the parties would be unlikely to comply with more formal procedures.
Read the court decisionRead the full story...Reprinted courtesy of
James R. Lynch, Ahlers & Cressman PLLCMr. Lynch may be contacted at
jlynch@ac-lawyers.com
Cross-Motions for Partial Judgment on the Pleadings for COVID-19 Claim Denied
May 24, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied both parties' motions for partial judgment on the pleadings seeking clarification of the policy's contamination exclusion. Thor Equities, LLC v. Factory Mut. Ins. Co., 2021 U.S. Dist. LEXIS 62967 (S.D. N.Y. March 31, 2021).
Thor was a commercial landlord, renting properties across the country to hundreds of tenants, for use in a variety of businesses, including office space, retail stores, restaurants, and bars. When state governments began shutting down businesses and issuing stay-at-home orders in March 2020, many of Thor's tenants had to close shop and sought abatements or other accommodations. Thor alleged it suffered significant business interruption as a result of the pandemic.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Federal Subcontractor Who Failed to Follow FAR Regulations Finds That “Fair” and “Just” are Not Synonymous
April 22, 2019 —
Garret Murai - California Construction Law BlogInscribed over the doors of the U.S. Supreme Court are the words “Equal Justice Under Law.” It’s a reminder that judicial decisions should be just. That doesn’t necessarily mean fair.
In Aspic Engineering and Construction Company v. ECC Centcom Constructors, LLC, U.S. Court of Appeals for the 9th Circuit, Case No. 17-16510 (January 28, 2019), the 9th Circuit overturned an arbitration decision in favor of a local Afghani subcontractor seeking termination costs after it was terminated for convenience by a U.S.-based general contractor. This, despite the arbitrator’s finding that the subcontract was “clearly drafted to give every advantage to” the general contractor, that the local Afghani subcontractor’s “experience with government contracting [was] not nearly as extensive as that of” the general contractor, and “that the normal business practices and customs of subcontractors in Afghanistan were more ‘primitive’ than those of U.S. subcontractors experienced with U.S. Government work.”
Aspic Engineering and Construction
Local Afghani subcontractor Aspic Engineering and Construction Company was awarded two subcontracts by ECC Centcom Constructors the general contractor on two projects in Afghanistan overseen by the United States Army Corps of Engineers. The first subcontract involved construction of various buildings in the Badghis province of Afghanistan . The second subcontract involved the construction various buildings Sheberghan province of Afghanistan . Both subcontracts included clauses from the Federal Acquisition Regulation (FAR), which were incorporated by reference, and included flow-down provisions obligating Aspic to ECC in the same manner that ECC was obligated to the U.S. government.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at
gmurai@wendel.com
New Mexico Architect Is Tuned Into His State
February 08, 2021 —
David M. Brown - Engineering News-RecordFor 40-plus years, Van Gilbert has combined his love for the topography, history and culture of New Mexico with an equally passionate dedication to designing not just structures, but buildings that help create communities.
Reprinted courtesy of
David M. Brown, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Gone Fishing: Tenant’s Insurer Casts A Line Seeking To Subrogate Against The Landlord
October 17, 2022 —
William L. Doerler - The Subrogation StrategistIn J&J Fish on Ctr. Str., Inc. v. Crum & Forster Specialty Ins. Co., No. 20-cv-644-bhl, 2022 U.S. Dist. LEXIS 16361, the United States District Court for the Eastern District of Wisconsin (District Court) recognized that “[t]here will be no further fish fries on Center Street until someone pays to repair the collapsed floor at J&J Fish on Center Street, Inc. (J&J Fish).” The contenders were: 1) J&J Fish; 2) its’ insurer, Crum & Forster Specialty Insurance Company (Insurer); and 3) J&J Fish’s landlord, Vision Land, LLC (Vision). Recognizing Insurer’s right to subrogate against Vision based on the terms of the parties’ lease, the District Court held Insurer owed J&J Fish coverage for the losses it sustained, but that Insurer could subrogate against Vision for anything it had to pay J&J Fish.
In J&J Fish, Vision and J&J Fish signed a lease (Lease) for a building (the Building) located in Milwaukee, Wisconsin. The Lease required Vision to “purchase and keep in full force and effect on the building(s) . . . insurance against fire and such other risks as may be included in all-risks policies . . .” Vision, however, never obtained any insurance on the Building. Pursuant to the Lease, Vision also agreed to “maintain and repair the structure including the slab floor and exterior walls of the Premises.”
With respect to J&J Fish, the Lease required J&J Fish to maintain “Physical Damage insurance, including but not limited to fire . . . and all other risks of direct physical loss as insured . . . for the full replacement cost of all additions, improvements (including leasehold improvements) and alterations to the Premises.” J&J Fish purchased a commercial property and casualty insurance policy (the Policy) from Insurer. The Policy covered “additions, improvements . . . and alterations” as the Lease required. In addition, it insured the Building itself against “collapse,” subject to certain exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at