Pay-if-Paid Clauses, Nasty, but Enforceable
March 12, 2015 —
Craig Martin – Construction Contractor AdvisorI am preparing for a presentation this week on Troublesome Contract Clauses to the Construction Specifications Institute (“CSI”), Nebraska Chapter. One of the clauses we will be discussing is the dreaded Pay-if-Paid clause, a particularly nasty provision that places the risk of owner’s solvency squarely on the subcontractor’s shoulders. While pay-if-paid clauses can create tremendous problems for subcontractors, they are enforceable.
Pay-if-Paid clauses eliminate the obligation to pay the subcontractor until the general contractor is paid by the owner. Pay-if-paid clauses usually contain something akin to the following phrases:
- payment to subcontractors are “expressly and unequivocally contingent upon receipt of payment from the Owner for the Subcontract Work.”
- the subcontractor “expressly acknowledges that it relies on payment under the Subcontract on the creditworthiness of Owner, not that of the General Contractor.”
- the owner’s acceptance of the work and payment to the General Contractor are “conditions precedent to any obligation of the General Contractor to pay the subcontractor.”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Insurer Must Pay for Matching Siding of Insured's Buildings
December 02, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Seventh Circuit found that the insurer was obligated to pay for siding of a building that was not damaged by hail so that it matched the replaced damaged portions of the siding. Windridge of Naperville Condominium Association v. Philadelphia Indem. Ins. Co., 2019 U.S. App. 23607 (7th Cir. Aug. 7, 2019).
A hail and wind storm damaged buildings owned by Windridge. The storm physically damaged the aluminum siding on the buildings' sought and west sides. Philadelphia Indemnity, Windridge's insurer, contended that it was only required to replace the siding on those sides. Windridge argued that replacement siding that matched the undamaged north and east elevations was no longer available, so Philadelphia had to replace the siding on all four sides of the buildings to that all of the siding matched.
Windridge sued and moved for summary judgment. The district court ruled that matching was required. The only sensible result was to treat the damage as having occurred to the building's siding as a whole.
The policy was a replacement-cost policy. Philadelphia promised to "pay for direct physical 'loss' to 'Covered Property' caused by or resulting from" the storm, with the amount of loss being "the cost to replace the lost or damaged property with other property . . . of comparable material and quality . . . and . . . used for the same purpose." The loss payment provision offered four different measures for loss, leaving Philadelphia free to choose the least expensive: (1) pay the value of the lost or damaged property; (2) pay the cost of repairing or replacing the lost or damaged property; (3) take all or any part of the property at an agreed or appraised value; or (4) repair, rebuild or replace the property with other property of like kind and quality.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Prompt Payment Act Obligation is Not Triggered When the Owner Holds Less Retention from the General Contractor
October 27, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCMost states have laws known as “prompt payment” statutes which govern the timing of payments on public works projects[i] from project owners to general contractors, and from general contractors to subcontractors.[ii] The purpose of these statutes is to ensure that contractors and subcontractors who may have less leverage than the project owners and prime contractors, respectively, are paid for their work on a timely basis.
Prompt Payment Act cases are rare, and, since many of the prompt payment statutes are founded on the same principles, when we come across a Prompt Payment Act case, it is “blog worthy.” This dispute arose from the construction of the Exposition Light Rail Line Project connecting downtown Los Angeles with Culver City on which FCI/Fluor/Parsons (“FFP”) was the prime contractor, and Bloise Construction, Inc. (“Bloise”) was the excavation subcontractor to FFP. Under the prime contract, Expo,[iii] the owner, was permitted to withhold ten percent of the payments owed to FFP, and FFP, pursuant to its subcontract with Bloise, was entitled to also withhold ten percent of the payments to Bloise as retention.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman, PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Construction Contract Basics: No Damages for Delay
May 06, 2024 —
Christopher G. Hill - Construction Law MusingsAfter WAY too long a hiatus, I am back with another in my series of “Construction Contract Basics” posts. In past posts, I’ve covered venue provisions, attorney fee provisions, and indemnity clauses. In this post, I’ll share a few thoughts (or “musings”) on the topic of so-called “no damages for delay” clauses. These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the owner or general contractor, is an extension of time to complete the work.
These types of clauses generally make it impossible for a subcontractor (if found in a Subcontract) or Contractor (if found in a Prime Contract) that is delayed through no fault of its own to recover any damages relating to the expenses that are inevitably caused by such delays. Such expenses/damages could include additional supervisory time (including more high-dollar superintendent payments), acceleration costs, demobilization/mobilization costs, and other related expenses. These can add up to real money. Couple that with the inevitable liquidated damages or delay damages that will occur should a contractor or subcontractor cause any delay, and this becomes a very one-sided proposition.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Arizona Court Cites California Courts to Determine Construction Defect Coverage is Time Barred
December 30, 2013 —
CDJ STAFFConstruction defect claims in an Arizona community are time barred and so the judge had determined that National Fire & Marine Insurance is not liable for coverage. National Fire claimed that while there was no Arizona case law concerning statutes of limitations for equitable contributions by insurance carriers, the court agreed that “its position is directly supported by cases from other jurisdictions.”
In the underlying construction defect case, Steadfast Insurance had settled with homeowners over allegations of construction defects. National Fire was a co-insurer and declined coverage. National Fire’s citing of two California cases was not unique for the Arizona courts. Other Arizona cases cited the same two California cases.
Read the court decisionRead the full story...Reprinted courtesy of
Maine Case Demonstrates High Risk for Buying Home “As Is”
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Meredith Eilers of Bernstein Shur, writing in JDSupra Business Advisor, a Boston Appeals court “enforced an 'as is' provision in a purchase and sale agreement and concluded that the sale of a multimillion dollar oceanfront property in Bar Harbor was not accompanied by Maine’s implied warranty of habitability.”
Eilers explained that “the first circuit concluded that the bargained-for ‘as is’ provision that was incorporated into the purchase and sale agreement—in exchange for a reduction in the purchase price—essentially waived any claims from the buyer regarding misrepresentations by the sellers.” This left “the buyer to incur the repair costs without the ability to recover those costs from the seller” and it demonstrated “that agreeing to such a clause when closing a real estate deal has real risks.”
Read the court decisionRead the full story...Reprinted courtesy of
New York Court Holds Insurer Can Recover Before Insured Is Made Whole
October 24, 2023 —
Gus Sara - The Subrogation StrategistIn State Farm Fire & Cas. Co. v. Tamagawa, Index No. 510977/2021, 2023 N.Y. Misc. Lexis 5434, the Supreme Court of New York considered whether an insurance carrier can settle its property subrogation lawsuit with the defendant, and discontinue the lawsuit, while the carrier’s insured still had pending claims with the carrier and claims for uninsured losses against the defendant. The court held that the carrier’s claims for the amount paid are divisible and independent of the insured’s claims and that the carrier’s settlement did not affect the insured’s right to sue for any unreimbursed losses. The court’s decision reminds us that, in New York, a carrier can resolve its subrogation claim before the insured is made whole.
In June 2018, a water loss occurred in an apartment owned by Malik Graves-Pryor (Graves-Pryor). Graves-Pryor reported a claim to his property insurance carrier, State Farm Fire & Casualty Company (Carrier). Investigation into the water loss revealed that the water originated from failed plumbing pipes in another apartment unit owned by Taku Tamagawa (Tamagawa). Carrier paid its insured over $600,000 for repairs. In May 2021, Carrier filed a subrogation lawsuit against Tamagawa, alleging improper maintenance of the plumbing pipes.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
New Safety Requirements added for Keystone Pipeline
June 11, 2014 —
Beverley BevenFlorez-CDJ STAFFAfter learning about construction defects on the “southern leg of the Canada-to-Texas project,” safety regulators have added two additional conditions “on construction of TransCanada Corp.’s Keystone XL oil pipeline,” according to Claims Journal. The defects, which have been fixed, included “high rates of bad welds, dented pipe and damaged pipeline coating.”
The first condition requires “TransCanada to hire a third-party contractor chosen by the pipeline safety agency to monitor the construction” and report to the U.S. government, while the second condition requires “TransCanada to adopt a quality management program.”
Both conditions were “buried near the end of the 26 appendices in a voluminous environmental impact statement on Keystone XL released by the State Department on Jan. 31.”
Read the court decisionRead the full story...Reprinted courtesy of