Improperly Installed Flanges Are Impaired Property
February 16, 2016 —
Tred R. Eyerly – Insurance Law HawaiiAnswering certified questions from the Fifth Circuit, the Texas Supreme Court found there was no coverage for flanges that leaked after installation. U. S. Metals, Inc. v. Liberty Mutual Group, Inc., 2015 Texas LEXIS 1081 (Dec. 4, 2015).
U. S. Metals sold Exxon 350 custom-made, stainless steel, weld-neck flanges for use in refineries. Testing after installation showed the flanges leaked and did not meet industry standards. Exxon decided to replace the flanges to avoid risk of fire and explosion. For each flange, this involved stripping the temperature coating and insulation, cutting the flange out of the pipe, removing the gaskets, grinding the pipe surfaces smooth for re-welding, replacing the flange and gaskets, welding the new flange to the pipes, and replacing the temperature coating and insulation. The replacement process delayed operation of the diesel units for several weeks.
Exxon sued U.S. Metal for over $6 million as the cost of replacing the flanges and $16 million as damages for lost use of the diesel units during the process. U.S. Metals settled with Exxon for $2.2 million and then sought indemnification from its liability insurer, Liberty Mutual.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Hurricane Laura: Implications for Insurers in Louisiana
October 19, 2020 —
Jennifer Michel & Tabitha Durbin - Lewis BrisboisJust two days before the 15th Anniversary of Hurricane Katrina, Category 4 Hurricane Laura made landfall near Cameron, Louisiana. Although the “unsurvivable” 20-foot storm surge, which had been predicted ahead of the storm, thankfully was significantly less, the impact of Laura on the Southwest Coast of Louisiana and Southeast Coast of Texas and its neighboring parishes and counties, most notably Cameron Parish, was quite severe. Lake Charles, Louisiana suffered widespread flooding and sustained catastrophic wind damage. Although the storm moved quickly, it retained its strength longer than expected such that even areas well inland sustained considerable damage. Preliminary estimates for insured losses from storm surge, flooding, and winds range from $8 to $12 billion for residential and commercial properties. Insurers providing residential or commercial property insurance in Louisiana should keep the following statutory claims handling requirements in mind.
Louisiana Statutory Provisions
Under Louisiana law, an insurer is expected to comply with certain statutory requirements in investigating and handling claims submitted by its insureds and third-party claimants. The majority of these requirements, and the consequences of their violation, are codified by La. R.S. 22:1892, which governs the payment and adjustment of claims, and La. R.S. 22:1973, which delineates an insurer’s duty of good faith. Together, the statutes impose three requirements on insurers: timely initiation of loss adjustment, timely payment of claims, and a duty of good faith and fairness in the adjustment and payment of said claims.
Reprinted courtesy of
Jennifer Michel, Lewis Brisbois and
Tabitha Durbin, Lewis Brisbois
Ms. Michel may be contacted at Jenny.Michel@lewisbrisbois.com
Ms. Durbin may be contacted at Tabitha.Durbin@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Entire Fairness or Business Judgment? It’s Anyone’s Guess
January 09, 2015 —
Maurice Pesso, Greg M. Steinberg and Christopher J. Orrico – White and Williams LLPIn lawsuits challenging the validity of business transactions and combinations, the most significant issue is often which standard of review the court applies: the defense-friendly “Business Judgment Rule” or the more stringent “Entire Fairness Standard.” The standard utilized by the court – or more often times the standard which the parties think the court will apply – can drive decisions on motion practice, settlement discussions, and resolution strategy. Under the Business Judgment Rule, directors are presumed to have acted in good faith and their decisions will only be questioned when they are shown to have engaged in self-dealing or fraud. However, if a “Controlling Shareholder” stands on both sides of the transaction, the court will often scrutinize the transaction under the more plaintiff-friendly “Entire Fairness Standard.”
So, what constitutes a “Controlling Shareholder?” If the party in question owns more than 50% of a company’s equity, the answer is clear-cut. However, for cases involving stockholders who own less than 50% of a company’s equity and stand on both sides of the disputed transaction, the answer is not so simple. This uncertainty was highlighted in back-to-back decisions by the Delaware Chancery Court in November 2014. On November 25, 2014, the court granted the defendants’ motion to dismiss a derivative lawsuit alleging breach of fiduciary duty in In Re Sanchez Energy Derivative Litigation (“Sanchez”). Vice Chancellor Glasscock held that the complaint failed to plead facts sufficient to raise an inference that two directors with a collective 21.5% equity interest in the company were Controlling Shareholders. The very next day, in In Re Zhongpin Inc. Stockholders Litigation (“Zhongpin”), the Delaware Chancery Court denied the defendants’ motion to dismiss breach of fiduciary duty claims against an alleged “Controlling Shareholder” and members of the company’s board. In Zhongpin, Vice Chancellor Noble held that sufficient facts were plead to raise an inference that a CEO with a 17.5% equity was a “Controlling Shareholder.”
Reprinted courtesy of White and Williams LLP attorneys
Maurice Pesso,
Greg M. Steinberg and
Christopher J. Orrico
Mr. Pesso may be contacted at pessom@whiteandwilliams.com
Mr. Steinberg may be contacted at steinbergg@whiteandwilliams.com
Mr. Orrico may be contacted at orricoc@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Court Voids Settlement Agreement in Construction Defect Case
September 01, 2011 —
CDJ STAFFA U.S. District Court Judge in Florida has ruled in favor of a company that sought to void a settlement agreement. The case, Water v. HDR Engineering, involved claims of construction defects at Florida’s C.W. Bill Young Regional Reservoir. The Tampa Bay Water Authority attributed these to both HDR Engineering’s design and Bernard Construction Company which had built the embankment. Bernard Construction filed a complaint against their subcontractor, McDonald.
Tampa Bay Water settled with Bernard Construction and McDonald, in an agreement that set a minimum and maximum settlement, but also would “prohibit Barnard and McDonald from presenting any evidence on several claims and positions of TBW, to require Barnard to call certain witnesses at trial, to preclude Barnard and McDonald from calling other witnesses, and to restrict the filing of trial and post-trial motions.” HDR Engineering moved to void the agreement as collusive.
The judge that the agreement¬? contained “133 paragraphs of ‘Agreed Facts’ that the parties stipulated would survive any order declaring the Settlement Agreement void or unenforceable.” He characterized these as stipulating “that Barnard neither caused nor contributed to TBW’s damages.” HDR motioned that a summary judgment be given to Barnard Engineering.
The court found that “the evidence identified by TBW is patently insufficient to survive summary judgment.” Further, TBW’s expert initially held Barnard responsible for “lenses, pockets, streaks and layers within the embankment,” but then later withdrew this assigning the responsibility to HDR. Further, the court notes that, “TBW’s arguments that lenses, pockets, streaks, and layers in the soil wedge caused or contributed to its damages and that Barnard is liable for those damages have been foreclosed by the Agreed Facts.”
As TBW failed to provide sufficient evidence to withstand summary judgment, the court granted summary judgment, mooted the claim against McDonald, and terminated the agreement between TBW and the other parties.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Federal District Court Continues to Find Construction Defects do Not Arise From An Occurrence
May 10, 2012 —
CDJ STAFFCoverage for construction defects continues to be hotly contested in Hawaii state and federal courts. In a recent decision, Judge Mollway felt bound to follow the Ninth Circuit’s decision in Burlington Ins. Co. v. Oceanic Design & Constr., Inc., 383 F.3d 940, 944 (9th Cir. 2004), where the court found construction defect claims arise from breach of contract, not from an occurrence. Judge Mollway’s most recent decision on the issue is Illinois Nat. Ins. Co. v. Nordic PCL Constr., Inc., 2012 U.S. Dist. LEXIS 58464 (D. Haw. April 26, 2012).
Nordic constructed a grocery store for Safeway. In addition to the grocery store, Nordic built a 165-space rooftop parking deck, retail shops and related improvements. After opening for business in 2007, Safeway experienced significant leaks. Safeway demanded that Nordic repair the parking deck. Nordic sent the demand letter to the insurer, who agreed to appoint counsel subject to a reservation of rights.
Safeway filed suit against Nordic in state court alleging, among other things, breach of contract and negligence. The insurer provided Nordic with a defense, but Nordic hired independent counsel.
The insurer filed for declaratory relief in federal district court.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
What Should Be in Every Construction Agreement
November 04, 2019 —
Patrick Barthet - Construction ExecutiveA detailed and coherent construction agreement in place on every job minimizes confusion, makes clear everyone’s respective responsibilities and reduces disputes. There are six things that should be addressed in every construction agreement.
DEFINE THE SCOPE
Define what the scope of work is that will be provided. Will it be only materials; will it be materials and labor; or will it be just labor? Be very clear and specific in how the scope of work is spelled out. Many contracts state that the contractor is responsible for all work that’s shown on the plans and specifications, as well as that which is reasonably inferable. While subjective—even if not actually on the plans or specifications, someone may believe that something should be part of the contractor’s work. This could expand what has to be done beyond what was understood or priced.
LIST ALL THE EXCLUSIONS
Do the parties each have the same understanding as to what is covered in the contract? How often are contractors faced with customers thinking something was included as part of the work? The contractor may have believed that task, or that material, or that specially fabricated item was excluded. But was it? Did the contractor articulate what was and was not in the scope and price? Specifically listing what is excluded can obviate this problem. Articulate what is not in the price or scope and reduce the chance of one party believing that something is to be done when it isn't.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
Ohio subcontractor work exception to the “your work” exclusion
August 11, 2011 —
CDCoverage.comIn Mosser Construction, Inc. v. Travelers Indem. Co., No. 09-4449 (6th Cir. July 14, 2011)(unpublished), claimant project owner Port Clinton contracted with insured general contractor Mosser for the construction of a building. Following completion, Port Clinton sued Mosser for breach of contract seeking damages because of physical injury to the project occurring after completion resulting from defective backfill material that settled improperly.
Mosser’s CGL insurer Travelers denied a defense and Mosser filed suit against Travelers seeking a declaratory judgment. Mosser and Travelers filed cross-motions for summary judgment on the issue of whether the supplier of the backfill material?Gerken?qualified as a subcontractor for purposes of the subcontractor work exception to the “your work” exclusion—exclusion l.—for property damage to or arising out of Mosser’s completed work.  Mosser had purchased the backfill material from Gerken pursuant to a purchase order specifying that Gerken was to supply Mosser with an industry standard grade of backfill for use in the Port Clinton project.
Read the full story…
Reprinted courtesy of CDCoverage.com
Read the court decisionRead the full story...Reprinted courtesy of
Benford’s Law: A Seldom Used Weapon in Forensic Accounting
March 05, 2015 —
Roger Hughes – California Construction Law BlogWhat is Digit Analysis and Why it Should be of Interest to Construction Attorneys?
Benford’s Law was named after Frank Benford, a General Electric physicist. Mr. Benford was the first to discover that “leading digits” do not follow a uniform distribution pattern as suggested by intuition. If you are like me, the response to such a statement is “huh”? But stick with me because this is important stuff to anyone who suspects a claim presentation may have been rigged, a bit here or a bit there, or maybe all over. It turns out that calculations purportedly based upon naturally, randomly occurring numbers may have been contrived. By “randomly occurring” we mean numbers that occur naturally without human interference as opposed to a contrived selection. Said another way, it is now accepted as a mathematical truth that the pattern of numbers randomly generated can be distinguished from numbers influenced by human intervention. Yikes, glad you told me that before I prepared my taxes.
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com