Tred R. Eyerly - Insurance Law HawaiiThe court found that even if the insured's negligent misrepresentations constituted an accident, the disclosures did not cause physical damage to the property. Wood v. USAA Cas. Ins. Co., 2024 U.S. Dist. LEXIS 180624 (D. S.C. Sept. 12, 2024).
The insured, Clinton Wood, purchased a townhome in January 2014. After the purchase, Wood experienced leaks and significant water intrusion, as did other townhome owners in the same development. Wood and the other owners retained an engineer to evaluate the cause of the water damage. The engineer determined that the water intrusion was caused by defects in the design and construction of the residence. The engineer told Wood that the proposed repairs would not adequately address and resolve the water intrusion and leaks, and that the problems would continue even if repairs were made.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New-Home Sales in U.S. Unexpectedly Fall to Four-Month Low
January 07, 2015 —
Victoria Stilwell – BloombergPurchases of new U.S. homes unexpectedly declined in November to a four-month low, underscoring a lack of momentum this year in residential real estate.
Sales dropped 1.6 percent to a 438,000 annualized pace last month following a 445,000 rate in October that was weaker than previously estimated, Commerce Department figures showed today in Washington. The median estimate of 73 economists surveyed by Bloomberg called for a 460,000 pace in November.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, BloombergMs. Stilwell may be contacted at
vstilwell1@bloomberg.net
California Contractors: Amended Section 7141.5 Provides Important License Renewal Safety Net
July 25, 2021 —
Amy L. Pierce, Mark A. Oertel, John Lubitz & Adam B. Wiens - Lewis BrisboisUnder California’s Contractors State License Law, Cal. Bus. & Prof. Code §§ 7000 et seq., contractors’ licenses expire two years from the last day of the month in which the license was issued or two years from the date on which the renewed license last expired. The Contractors State License Board (CSLB) sends licensees a renewal application 60 to 90 days in advance of the date the license is set to expire. Even with various controls in place, mistakes happen and a renewal application filing deadline can be missed.
During the August 5-6, 2019 Executive, Licensing, and Legislative Committee Meetings, the CSLB discussed proposed amendments to Section 7141.5 to reduce both the burden on it to review applications for retroactive renewal of a license that had not been timely submitted and to provide contractors with some relief from the high burden to establish “the failure to renew was due to circumstances beyond the control of the licensee.” Not long after, the CSLB’s Board of Directors gave staff approval to seek an author for the bill and, on September 29, 2020, Governor Newsom signed Senate Bill 1474 into law, which includes the CSLB’s proposed amendments to Section 7141.5, effective January 1, 2021.
Reprinted courtesy of
Amy L. Pierce, Lewis Brisbois,
Mark A. Oertel, Lewis Brisbois,
John Lubitz, Lewis Brisbois and
Adam B. Wiens, Lewis Brisbois
Ms. Pierce may be contacted at Amy.Pierce@lewisbrisbois.com
Mr. Oertel may be contacted at Mark.Oertel@lewisbrisbois.com
Mr. Lubitz may be contacted at John.Lubitz@lewisbrisbois.com
Mr. Wiens may be contacted at Adam.Wiens@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Indiana Federal Court Holds No Coverage for $50M Default Judgment for Lack of Timely Notice of Class Action
August 26, 2019 —
Anthony L. Miscioscia and Timothy A. Carroll - White and Williams LLPIn Greene v. Kenneth R. Will, a CGL insurer recently prevailed in a declaratory judgment action arising from an underlying class action alleging pollution and nuisance claims against the insured, VIM Recycling LLC, an Indiana-based waste-recycling facility.[1] “[T]his case has some whiskers on it,” the Indiana federal district court recounted in its exhaustive decision granting the insurer relief. The court relieved the insurer of indemnifying a $50 million default judgment against the insured, which, the court observed, “proved to be a bad neighbor” and “nuisance in both the legal and colloquial sense.” The court held that the insured failed to provide timely notice of the class action.
“The judgment against the [insured] came about when a group of nearby homeowners decided that they had had enough of VIM’s polluting behavior and brought this class action to recover damages for environmental violations, nuisance and negligence based on the impact of the waste facility on their homes and property,” the court explained. Eventually, the court entered a default judgment against the insured for $50,568,750, plus an award of $273,339.85 in attorney’s fees. Because the insured was “judgment-proof,” the class action plaintiffs “aligned” with the insured “hoping to collect on their monumental judgment” from the insured’s CGL insurer. Within a few weeks’ time, the class action plaintiffs sued the insurer seeking a declaration of coverage for the default judgment against the insured.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Timothy A. Carroll, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Microwave Transmission of Space-Based Solar Power: The Focus of New Attention
July 24, 2023 —
Robert A. James & William E. Fork - Gravel2Gavel Construction & Real Estate Law BlogScientists have long proposed that solar electricity generation in space could be an integral component of the world’s carbon-free future. In the 1970s, a U.S. Navy experiment showed that it might be possible to capture solar power and wirelessly transmit it from outer space using microwave beams. Progress stalled after that early test—the models used were at such a massive scale that creating a real-world system felt like science fiction. Recently, amid growing concerns about power grid security and intensifying legislation around carbon emissions, renewed attention focused on a smaller, more lithe microwave transmission system. This time around, the military is not the only interested party. Scientists around the world are conducting similar research. As investors and governments stand at the edge of a fresh green power opportunity, we look at microwave power transmission and some of the projects in this emerging field.
The basic premise of space-based solar power technology is simple enough: photovoltaic panels on a satellite in space convert the sun’s energy to electromagnetic waves at microwave frequencies. The satellite then beams the microwave energy to a receiver on Earth that transforms it into direct current. Until recently, this technique had been performed on the ground over short distances, but nobody had attempted to launch a solar panel into space. The status quo has shifted over the past few years as researchers have begun to send prototypes into orbit. In early 2023, CalTech was the first to report a breakthrough. Its model successfully beamed power from space back to their receiver atop a building in California.
Reprinted courtesy of
Robert A. James, Pillsbury and
William E. Fork, Pillsbury
Mr. James may be contacted at rob.james@pillsburylaw.com
Mr. Fork may be contacted at william.fork@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Louisiana Couple Sues over Defects in Foreclosed Home
September 24, 2013 —
CDJ STAFFA Louisiana couple is suing over the home they bought, claiming that the sellers knew there were defects in the home, including termite damage, mold, and roof leaks. When the Eastmans bought the home, they were assured that inspectors had cleared the property.
The home had been foreclosed upon and purchased by Beverly Knoll, LLC. The Eastmans subsequently purchased the home from Beverly Knoll. After the sale, the plaintiffs hired their own inspector who found the damage and no evidence of attempts at repair.
The Eastmans informed one of the defendants, Troy Duhon, who informed them that the defendants would be assuming the costs of repair. However, after the Eastmans requested $94,000 in reimbursements, the defendants declined to pay.
Read the court decisionRead the full story...Reprinted courtesy of
Instant Hotel Tower, But Is It Safe?
March 28, 2012 —
CDJ STAFFBroad Sustainable Building has leapfrogged in China’s construction boom by building a thirty-story hotel in just fifteen days in the city of Changsha. According to an article in the Los Angeles Times, most of the building was prefabricated, but most prefabricated buildings require a longer time for assembly. Broad claimed that it cut no corners on safety. However, Zhang Li, a Beijing architect, told the Times that “incredible speed also means incredible risk.”
At the completion date, the interior was still partially finished. Some rooms were furnished, while others weren’t quite so ready. The hotel will be used to house clients who are visiting Broad and some of its employees.
Broad called their process “the most profound innovation in human history” and predicted that soon a third of new buildings worldwide would be constructed this way. The company anticipates using the same process to build taller buildings, with hopes of eventually constructing a 150-story building.
China is currently undergoing a building boom which Zhang attributed to a desire to catch up to the developed world. As a result of this boom, he noted that building inspections are often skipped in China to speed up building.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Five Frequently Overlooked Points of Construction Contracts
October 18, 2021 —
Craig H. O'Neill - White and Williams LLPThere is no shortage of articles addressing the key points of construction contracts. Just enter that phrase into any internet search engine and you will find plenty. It should go without saying that a construction contract should be in writing, it should clearly identify the scope of work to be performed and the sums to be paid for that work, and it should address the parties’ rights and responsibilities with regard to termination or suspension of the contract, correcting defective work, and handling claims and disputes—just to name a few. Of course, these items should receive their due consideration. Too often, however, other important aspects of the construction contract get shortchanged. This article aims the spotlight on five often overlooked aspects of construction contracts.
Project Schedules
Surprisingly, many construction contracts pay little attention to a central component of any construction project: the project schedule. Many contracts provide the dates of commencement and substantial completion but not much else. With the frequent use of project management techniques such as the Critical Path Method (CPM) and the associated software, it is easier than ever to identify which tasks should be prioritized and identify potential areas of delay. The owner’s contract with the general contractor should clearly define the scheduling methods used and provide measures to keep the parties informed of the progress of the work. By including basic scheduling requirements in the contract documents—such as the submission of “Baseline Project Schedules” (consistent with the contract time provisions), “Schedule Progress Updates” (comparing the progress of the work against the Baseline Project Schedule), and “Schedule Recovery Plans” (when Schedule Project Updates indicate projected delays)—the parties can avoid or reduce disputes over project delays that often lead to litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Craig H. O'Neill, White and Williams LLPMr. O'Neill may be contacted at