Avoid L&I Violations by Following Appropriate Safety Procedures
November 07, 2022 —
Reeya Patel - Ahlers Cressman & Sleight PLLCDepartment of Labor and Industries of the State of Washington v. Roof Doctor, Inc. d/b/a Roof Doctors, Inc. of Tacoma (Unpublished opinion)
Roof Doctor, a company engaging maintenance of roofs, was hired to complete work for a commercial building in Tacoma in February 2018. During the job, Roof Doctor was cited for two violations by a Washington State Department of Labor and Industries’ (L&I) compliance inspector and seven additional asbestos violations. Each citation was rated with a probability of 1 – 3 to determine the likelihood of injury, illness, or disease. The ratings allowed issuance of an appropriate monetary penalty.
The disputes among the parties on appeal were as follows:
First, L&I and Roof Doctor disputed the asbestos probability ratings and calculated penalties. L&I produced as evidence, the fact that nine employees were physically hanging roofing material with asbestos, but none had training or knew that the material contained asbestos. L&I did agree that that most of the employees were experienced in handling roofing material and knew of the dangers that asbestos presented. Roof Doctor explained that because the employees were working outdoors, the danger of asbestos exposure was mitigated due to a low probability that a high concentration of asbestos could be inhaled by the employees when outdoors.
Read the court decisionRead the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
The Almost-Collapse of a Sarasota, Florida Condo Building
July 11, 2021 —
Beverley BevenFlorez – CDJ StaffFive years ago, residents of the Dolphin Tower in Sarasota, Florida were forced to evacuate after cracks appeared in their fourth-floor condominium units.
“My assistant calls me and says, ‘[Kris] thinks the building is falling down,’” David Karins of Karins Engineering told Sarasota Magazine. “I said, ‘I doubt that.’ Then I got there and saw what was going on and I said, ‘You know, the building may be falling down.’”
In July of 2010, city officials ordered all residents to evacuate. Five years and $11 million dollars in rehabilitation and residents were finally able to move back in last month.
The Herald-Tribune had previously interviewed John Bonacci, an engineer at Sarasota’s Karins Engineering: “I’d say yes, there was grave danger. It was luck that it didn’t come all the way down. Getting shoring in there quickly was instrumental in preventing it from collapsing.”
Read the full story, Sarasota Magazine...
Read the full story, Herald-Tribune...
Read the court decisionRead the full story...Reprinted courtesy of
Construction Contract Clauses Only a Grinch Would Love – Part 4
November 30, 2016 —
Garret Murai – California Construction Law BlogScope, time and cost provisions may be the most important clauses in your construction contract but they’re not the only ones which can impact your bottom line. The fourth and final part in a multi-part series, here are some other important construction contract clauses that can put a damper on your holidays.
Provision: Warranty Provisions
- Typical Provision: “Subcontractor warrants to Contractor that all materials and equipment furnished shall be new unless otherwise specified and that all Work performed shall be performed in a good and workmanlike manner, of good quality and free from defects, and in conformance with industry standards, manufacturer’s recommendations and the Contract Documents. All work not conforming to these requirements, including substitutions not properly approved, shall be considered defective. Subcontractor agrees to promptly make good any and all defects due to faulty workmanship, materials and/or equipment which may appear within the Contract Documents, and if no such period is stipulated in the Contract, then for a period of one year from the date of acceptance by the Owner. Nothing herein shall shorten or limit any applicable periods of limitations including, but not limited to, those set forth in Civil Code, Part 2, Title 2, Chapter 3.”
- What it Means: Warranty periods are subject to the agreement of the parties. However, warranties are different than limitations periods, such as California’s 4 year statute of repose for patent defects and 10 year statute of repose for latent defects (note: a statute of repose is different than a statute of limitation. A statute of repose sets a deadline based on an event. So, for example, under the 10 year statute of repose for latent defects a claimant must bring a latent defect claim within 10 years following substantial completion even if the latent defect wasn’t discovered until 10 years and 1 month following substantial completion. A statute of limitation, in contrast, sets a deadline based on the occurrence of an injury or damage. So, for example, California has a 2 year statute of limitation for personal injuries, which sets a deadline of 2 years from the date of injury to bring a personal injury claim). Warranty periods are also different from limitations periods because most warranties require work to be corrected at no cost, and because many contracts include attorney’s fee provisions, breach of a warranty can give rise to claim for attorney’s fees as well.
- What You Can Do: Lower-tiered parties should examine warranty provisions to see if they are reasonable, and if not reasonable, should seek to either eliminate or limit those provisions, such as by reducing the warranty period or providing different warranty periods for different components of work, etc.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Colorado Supreme Court Rules that Developers Retain Perpetual Control over Construction Defect Covenants
June 21, 2017 —
Jesse Witt - The Witt Law FirmThe Colorado Supreme Court ruled today that developers can retain control over community covenants in perpetuity by recording a covenant that requires declarant consent to any amendments. Although the Colorado Common Interest Ownership Act (CCIOA) states that such controls should be void, the court nevertheless ruled that a declarant may veto amendments that alter the dispute resolution procedures for construction defect actions at any time.
The case of Vallagio at Inverness Residential Condominium Ass’n v. Metropolitan Homes, Inc., __ P.3d __, 15CO508, arose when the community’s members discovered widespread construction defects. When the declarant developed the project, it had recorded a declaration of covenants that purported to waive the homeowners’ right to a jury trial and instead require that any construction defect disputes be resolved by a private arbitration panel. The declaration also prohibited the homeowners from recovering attorney fees and costs, and it limited the declarant’s liability for damages. Consistent with CCIOA, the declaration allowed the homeowners to amend their covenants by a 67% vote, but it recited that the declarant could veto any such amendment prior to the sale of the last unit to a homeowner. The covenants further stated that the declarant must consent to any amendment that altered the construction defect restrictions.
Reprinted courtesy of
Jesse Howard Witt, Acerbic Witt
Mr. Witt may be contacted at www.witt.law
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Don’t Sign a Contract that Doesn’t Address Covid-19 (Or Pandemics and Epidemics)
December 14, 2020 —
David Adelstein - Florida Construction Legal UpdatesDo yourself a favor: Don’t sign a construction contract that doesn’t address COVID-19 or any pandemic or epidemic from this point forward!
As the number of COVID-19 numbers rise, it would be reasonable to think this could have an impact on ongoing or future construction projects. For this reason, I want to revisit the subject of addressing COVID-19 (and any pandemic or epidemic) in your construction contract.
The potential impact caused by COVID-19 could result from governmental regulations that impact construction of the project, shutdowns due to affected workers, owners’ decisions to suspend performance or adjust the way the project is being constructed, increased deep cleaning requirements, and increased measures associated with social distancing and re-sequencing of shifts. This all plays into the timeliness of performance and the productivity of manpower and equipment usage. When submitting a price, a lot of these considerations may not be factored in because doing so could lead to a price that will never get accepted.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Eleventh Circuit Finds No Coverage for Faulty Workmanship Claims
November 15, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe Eleventh Circuit affirmed the district court's grant of summary judgment to the insurer on the general contractor's claims for damages due to faulty workmanship. Tricon Dev. of Brevard v. Nautilus Ins. Co., 2021 U.S. App. LEXIS 27317 (11th Cir. Sept .10, 2021).
Tricon was the general contractor for a condominium project in Florida. Tricon hired a subcontractor to fabricate and install metal railings for the project. The subcontractor was insured by Nautilus under two CGL policies. The policies had endorsements to add Tricon as an additional insured.
The subcontractor fabricated some of the railings, but they had defects and damage. Further they were not installed properly and did not meet the project's specifications. Tricon found another manufacturer to fabricate new railings to satisfy the projects' requirements. Tricon agreed to pay the cost of removing the subcontractor's railings and fabricating and installing new ones. If submitted a claim to Nautilus to cover these costs.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Blurred Lines: New York Supreme Court Clarifies Scope of Privileged Documents in Connection with Pre-Denial Communications Prepared by Insurer's Coverage Counsel
September 17, 2015 —
Greg Steinberg – White and Williams LLPIn a recent decision, the New York Supreme Court clarified the scope of privileged documents with respect to communications prepared by an insurer’s counsel prior to issuing a denial of coverage letter. The coverage litigation at issue arose out of MF Global Inc.’s claims under fidelity bonds for losses incurred as a result of large trades made by former MF Global employee, Evan Dooley. The trades cost MF Global, Dooley’s former clearing firm, $141 million after it had to reimburse the CME Group, Inc. futures clearinghouse that handled the trade. The insurers that issued the fidelity bonds contested coverage and sued MF Global in 2009.
The opinion underscores the fact that there is no “bright line” rule in New York with respect to disclosure of communications in the insurance context prior to the issuance of a coverage determination – the disclosure requirement will instead turn on what’s actually privileged. In addition, while retention of counsel may not serve as an automatic shield for all documents prepared prior to the coverage decision, insurers will not be required to disclose, among other things, communications which include an “indicia of the provision of legal services.”
Read the court decisionRead the full story...Reprinted courtesy of
Greg Steinberg, White and Williams LLPMr. Steinberg may be contacted at
steinbergg@whiteandwilliams.com
A Brief Discussion – Liquidating Agreements
June 27, 2022 —
Gerard J. Onorata - Peckar & Abramson, P.C.During a construction project, it is not uncommon for disputes to arise between a general contractor and a subcontractor. Frequently, these disputes involve claims for extra work and delay damages that can be attributed to the owner of the project due to deficient design or unforeseen conditions. When these occasions arise, the parties can often resolve these claims without the need for litigation or arbitration by entering into a “liquidating agreement.”
What is a Liquidating Agreement?
Because there is no direct contractual relationship between a subcontractor and an owner, there does not exist a legal basis for a subcontractor to assert a breach of contract claim against a project owner. In legal parlance, this is known as “lack of contractual privity.” A liquidating agreement bridges this contractual gap and allows a subcontractor to pass its claim against the owner through the general contractor. Essentially, with a liquidating agreement, the general contractor acts as a conduit for passing through the subcontractor’s claim.
Read the court decisionRead the full story...Reprinted courtesy of
Gerard J. Onorata, Peckar & Abramson, P.C.Mr. Onorata may be contacted at