Goldberg Segalla Welcomes William L. Nimick
February 07, 2022 —
Goldberg Segalla LLP(RALEIGH, N.C.)—Goldberg Segalla added William L. Nimick to the firm's Construction Litigation and Counsel group in Raleigh. Nimick was previously with The Law Offices of Stephen R. Paul in Raleigh.
Nimick is an experienced litigator who focuses his practice on counseling and defending corporate entities, insurers, contractors, and subcontractors in a range of liability claims, including those alleging construction defect, personal injury, property damage, premises liability, and more. Nimick draws on a background in civil litigation, personal injury and wrongful death, workers' compensation, and subrogation. He has handled subrogation claims across North Carolina, including construction defects, motor vehicle accidents, product liability lawsuits, and large fire losses.
Nimick earned his bachelor's degree at the University of North Carolina at Wilmington and his juris doctor at the Campbell University Norman Adrian Wiggins School of Law.
About Goldberg Segalla
Goldberg Segalla is a national civil litigation firm with more than 20 offices in 10 states spanning major metro markets across the U.S., providing strategic coverage wherever our clients do business. As a firm of experienced litigators and trial attorneys, Goldberg Segalla's capabilities span business and commercial disputes, employment and labor, insurance coverage, product liability, and more. Today, our more than 400 attorneys are trusted counselors to public and private clients in key sectors and industries including construction and energy, transportation, manufacturing, retail and hospitality, and insurance. To learn more, visit goldbergsegalla.com or follow us on
LinkedIn,
Facebook, and
Twitter.
Read the court decisionRead the full story...Reprinted courtesy of
A Year Later, Homeowners Still Repairing Damage from Sandy
October 01, 2013 —
CDJ STAFFThe New York and New Jersey coastal communities are still in the thick of rebuilding and repairing after hurricane Sandy struck almost a year ago. Newsday reports that in the eight months following the October 2012 storm, more than 23,000 building permits were issued in Long Island communities, an 11 percent rise over the previous year. The town of Long Beach, New York has waived fees and hired more staff in order to encourage people to rebuild, in order to rebuild the town’s tax base.
Homeowners aren’t going it alone, New York expects to fund more than $1 billion of rebuilding for homeowners who are unable to afford repairing their homes. At this point, the state is still processing more than five thousand requests for grants. The money is still in the state’s coffers. Other homeowners are still filing insurance claims.
While towns are busy issuing building permits, contractors are busy too. Bill Sims of Sims Steel said that his business has changed from commercial construction to raising homes higher to put them above future floods. “There’s probably been more homes raised this last year than in the previous 20 years,” he told Newsday. Another contractor, Pat Gordon said that he is “only taking what we can handle.” He described Long Beach as “a traffic jam of construction trucks that has never been seen before.”
Read the court decisionRead the full story...Reprinted courtesy of
Building Stagnant in Las Cruces Region
November 20, 2013 —
CDJ STAFFThere was an increase in the number of building permits issued in Las Cruces, New Mexico through the first ten months of 2013, but the 2,162 permits represent only a minimal increase over last year’s 2,158 permits. To make matters worse for building suppliers and workers, builders can “pull all the permits for a subdivision at one time but might not start some of those for six months,” said Lee Rawson, the owner of Rawson Builders Supply.
For a comparison, during the building boom of 2006, Las Cruces issued 3,529 building permits. The values are down too. Although fewer permits were issued in 2012, their valuation was $147 million, while the marginally larger number in 2013 is worth only $128 million.
As a result, the area is losing skilled labor. After 25 consecutive months of declining construction, workers are leaving the construction industry. Mr. Rawson noted that “you can’t just go find that skilled labor, it doesn’t exist.”
Read the court decisionRead the full story...Reprinted courtesy of
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Construction in the Time of Coronavirus
March 30, 2020 —
Christopher G. Hill - Construction Law MusingsOne cannot look look at one’s phone, computer or even the road outside the window without seeing signs of the impact that coronavirus (COVD-19) is having on the world at large. Schools are shut down, traffic is lighter and there is the daily count of new confirmed cases, in Virginia and elsewhere. “Social distancing” is the buzzword of the day. I am writing this post from a home office because of CDC and other guidance regarding the best way to “flatten the curve.” We have all been told to avoid large groups and stay close to home.
All of this is well and good, but construction must go on. In travelling around Richmond, I see construction vehicles on the road quite a bit. This is a good thing. It seems that most of the Richmond, Virginia area contractors are trying to stay as close to “business as usual” as possible while still remaining vigilant and careful to follow CDC and OSHA guidelines on workplace activity and COVD-19. However, the situation is ever changing and government and other outside forces could lead to project slowdowns, project shutdowns or other virus related impacts to everything from permitting to staffing of a project.
As I have discussed, likely ad nauseam, any commercial or residential construction project is controlled by a series of contracts (hopefully well drafted) that control the relationships on the job. Subcontractors in particular have the provisions of their subcontract and those of the prime contract to worry about. One of the major provisions that could trip up any construction professionals on these jobs is the notice provision of the subcontract (thanks for the reminder go to a friend and fellow construction lawyer Mark Cobb at his blog).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Insurer Prohibited from Bringing Separate Contribution Action in Subrogation to Rights of Suspended Insured
January 15, 2019 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel LLPIn Travelers Property Casualty Co. of Amer. v. Engel Insulation, Inc. (No. C085753, filed 11/30/18), a California appeals court held that an insurer may not file its own action to assert claims solely as a subrogee of a suspended corporation, where the corporation could not otherwise assert the claims on its own behalf.
In Engel, a homeowners association filed a construction defect action against the developer, Westlake. Travelers defended Westlake as an additional insured on the policy of a subcontractor. After the case settled, Travelers brought a subrogation action against another subcontractor for contribution to the defense costs. However, Westlake had its corporate status suspended for failure to pay taxes, and the subcontractor moved for judgment on the pleadings, which was granted.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Why Employees Are Taking Ownership of Their Architecture Firms
January 22, 2024 —
Kriston Capps - BloombergThe architecture firm BNIM has always been a leader on sustainable design. In the late 1980s, principal emeritus Bob Berkebile was one of the first architects to push the industry to take the idea of green buildings seriously. Then-President Bill Clinton even recruited him to lead a climate-minded restoration of the White House. Berkebile and his Kansas City, Missouri–based firm — he’s the “B” in BNIM, alongside Tom Nelson, David Immenschuh and Steve McDowell — received top honors from the American Institute of Architects in 2011, among many other accolades.
Now the firm behind such projects as the US Embassy expansion in Kampala, Uganda, and a proposed South Loop park to deck over a highway in downtown Kansas City hopes to stand out in another way. In October, BNIM announced its transition to an employee stock ownership plan, or ESOP. The firm is one of a handful in the industry to recently embrace the employee-ownership model, following similar moves in 2021 by SHoP Architects and Zaha Hadid Architects.
Read the court decisionRead the full story...Reprinted courtesy of
Kriston Capps, Bloomberg
Insured's Testimony On Expectation of Coverage Deemed Harmless
August 30, 2017 —
Tred R. Eyerly - Insurance Law HawaiiAffirming the district court, the Third Circuit found that the insured's testimony that she expected her loss to be covered was harmless. Gordon v .Allstate Prop. & Cas. Ins. Co., 2017 U.S. App. LEXIS 13507 (3rd Cir. July 26, 2017).
After a storm, portions of the stone facade of the insured's home collapsed. Allstate denied coverage because her policy was limited to "sudden and accident physical loss to the property" caused by a named peril, including windstorm. Allstate contended that the damage to the home was caused by neglect, not the storm.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com