The Practical Distinction Between Anticipatory Breach and Repudiation and How to Deal with Both on Construction Projects
June 10, 2024 —
Devon Griger - ConsensusDocsWhen a multilevel construction project is underway and a contractor or subcontractor isn’t performing as expected, it can be difficult to know how to address the low performance without putting the parties’ contract and good working relationship at risk. However, there may come a time when poor performance lapses into a something much worse: an anticipatory breach or repudiation of the subject contract.
Imagine Scenario One: You are a general contractor managing a large-scale construction project and one of your subcontractors is falling behind on their work. The project manager for the subcontractor calls you and says, “Look, I don’t think we’re going to be able to hit our next milestone, and probably not the next one after that.” A conversation like this would generally trigger concern for most general contractors, but it would not necessarily invoke panic. These types of delay conversations are not uncommon on large scale projects.
Compare that example, however, with Scenario Two, where the subcontractor instead says, “We received an offer to work another job for much more money, so we’re leaving the project site today and will not be returning.” This is obviously different (and potentially worse) than Scenario One, and likely cause for much greater concern.
Read the court decisionRead the full story...Reprinted courtesy of
Devon Griger, Jones WalkerMs. Griger may be contacted at
dgriger@joneswalker.com
Environmental Suit Against Lockheed Martin Dismissed
August 13, 2014 —
Beverley BevenFlorez-CDJ STAFFA federal judge dismissed an environmental suit against Lockheed Martin, finding that contamination levels on the plaintiffs’ Moorestown, New Jersey properties were not high enough to pose a health threat, according to the New Jersey Law Journal.
Two owners who live across the street from the plant had “sued under the Resource Conservation & Recovery Act, the Comprehensive Environmental Response, Compensation & Liability Act and various state statutes.” However, “while the suit was pending, the New Jersey Department of Environmental Protection raised the threshold for concentration levels of substances such as TCE and PCE to warrant additional testing.”
Read the court decisionRead the full story...Reprinted courtesy of
Boston Team Secures Summary Judgment Dismissal on Client’s Behalf in Serious Personal Injury Case
October 21, 2024 —
Lewis Brisbois NewsroomBoston, Mass. (October 14, 2024) - Boston Managing Partner Kenneth B. Walton and Partner Matthew M. O' Leary recently secured summary judgment on behalf of a civil engineering firm in a serious personal injury matter arising from a trip-and-fall incident in a mall parking lot.
The client was retained to provide site civil engineering design for the parking lot of a local mall. The design included multiple bioretention areas known as rain gardens. In November of 2019, a woman tripped and fell while attempting to cross a rain garden to reach her car. She suffered significant bodily injuries, including a fracture of the cervical spine that resulted in partial paralysis.
The woman and her husband sued the mall's owner for negligence and loss of consortium in June 2021. The owner, in turn, impleaded Lewis Brisbois' client and the lot's builder, asserting third-party claims for contribution, contractual and common law indemnity, and breach of contract. In addition, the builder cross-claimed against Lewis Brisbois' client for contribution and common law indemnity.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Using the Prevention Doctrine
April 22, 2019 —
David Erhart - Gordon & Rees Construction Law BlogThe following scenario happens regularly in the construction industry. A contractor on a project reaches out to a subcontractor to perform work. Excited about the prospect of performing the work, the subcontractor signs a contract and puts it nose to the grindstone. After dutifully completing the work the subcontractor turns to the contractor and asks to be paid. But, the contractor refuses saying that there is a provision in the subcontract that says the contractor is only obligated to pay the subcontractor if the contractor receives payment from the owner. So the contractor has completed the work, but has no money to show for it.
One potential remedy for a subcontractor in this situation is the use of the prevention doctrine. “Under the prevention doctrine, ‘if a promisor prevents or hinders fulfillment of a condition to his performance, the condition may be waived or excused.’” Cox v. SNAP, Inc., 859 F.3d 304, 308 (4th Cir. 2017) (quoting Moore Bros. Co. v. Brown & Root, Inc., 207 F.3d 7171, 725 (4th Cir. 2000)). “Put simply, ‘where a party to a contract is the cause of the failure of the performance of the obligation due him or her, that party cannot in any way take advantage of that failure.’” Haddon Hous Assocs v. United States, 711 F.3d 1330, 1338 (Fed. Cir. 2013) (quoting Restatement (Second) of Contracts § 245; Williston, § 39:4).
Read the court decisionRead the full story...Reprinted courtesy of
David Erhart, Gordon & Rees Scully MansukhaniMr. Erhart may be contacted at
derhart@grsm.com
President Trump Nullifies “Volks Rule” Regarding Occupational Safety and Health Administration (OSHA) Recordkeeping Requirements
April 13, 2017 —
Louis “Dutch” Schotemeyer – Newmeyer & Dillion LLPOSHA requires employers to maintain safety records for a period of five years. The Occupational Safety and Health Act contains a six month statute of limitations for OSHA to issue citations to employers for violations. In an effort to close the gap between the five years employers are required to keep records and the six month citation window, the Obama Administration implemented the “Volks Rule,” making recordkeeping requirements a “continuing obligation” for employers and effectively extending the statute of limitations for violations of recordkeeping requirements from six months to five years.
On March 22, 2017, the Senate approved a House Joint Resolution (H.J. Res. 83) nullifying the “Volks Rule” and limiting the statute of limitations to six months for recordkeeping violations. President Trump signed the resolution nullifying the “Volks Rule” on April 3, 2017. The nullification appears to be in line with President Trump’s stated goal of generally eliminating governmental regulations.
What Does This Mean for California Employers?
California manages its own OSHA program, which generally follows the federal program, but is not always in lock-step with Federal OSHA. Cal/OSHA, under its current rules, may only cite employers for recordkeeping violations that occurred during the six months preceding an inspection or review of those records. To date, there has been no indication that California’s Division of Occupational Safety and Health (DOSH) has plans to adopt the “Volks Rule.” Barring a change, California employers will continue to operate under the status quo and be required to maintain safety records for five years, but will only be exposed to citations for recordkeeping violations occurring within the last six months.
Current Cal/OSHA Recordkeeping Requirements
Cal/OSHA form 300 (also known as the “OSHA Log 300”) is used to record information about every work-related death and most work-related injuries that cannot be treated with onsite first aid (specific requirements can be found in the California Code of Regulations, Title 8, Sections 14300 through 14300.48). Currently, California Code of Regulations, Title 8, Section 14300.33 requires employers to retain OSHA Log 300 for a period of five years following the end of the calendar year during which the record was created, despite the fact that Cal/OSHA can only cite employers for failing to maintain such records for up to six months preceding an inspection.
Looking to the Future
Cal/OSHA is working on regulations that would require electronic submission of OSHA Log 300 records in California. This would bring Cal/OSHA more in line with Federal OSHA, which already requires electronic submission.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Louis "Dutch" Schotemeyer, Newmeyer & Dillion LLPMr. Schotemeyer may be contacted at
dutch.schotemeyer@ndlf.com
Will Protecting Copyrights Get Easier for Architects?
November 28, 2022 —
Scott L. Baker - Los Angeles Litigation BlogLike any creative business, architects rely on their intellectual property. Their designs are at the center of their work. For example, as we discussed in a previous post, many architects nowadays focus on creating new ways for their building designs to be environmentally friendly and sustainable.
However, nearly every form of intellectual property faces the risk of theft or infringement in the business world.
Architects face unique challenges with their copyrights – as well as risks.
Copyright Issues in the Architecture World
One of the biggest issues, of course, is that there are many aspects of building designs that architects
cannot protect by copyright. This is simply because various details are fundamental in the construction of every building. One person cannot own the rights to such a common design.
Read the court decisionRead the full story...Reprinted courtesy of
Scott L. Baker, Baker & AssociatesMr. Baker may be contacted at
slb@bakerslaw.com
Chinese Demand Rush for Australia Homes to Stay, Ausin Says
August 06, 2014 —
Nichola Saminather – BloombergAusin Group (Finance) Pty, which offers property and mortgage broking in Australia to Chinese buyers, expects to sell two-thirds more homes and to double the amount of loans it arranges as demand from the mainland surges.
The company forecasts A$1.5 billion ($1.4 billion) in sales of new residential properties in the year ending June 30, compared with A$900 million over the previous 12 months, Sydney-based Managing Director Joseph Zaja said in an interview yesterday. The value of mortgages the closely held company arranges through Australian banks is expected to climb to A$500 million in the 2015 calendar year, he said.
Ausin is benefiting from surging demand from China, where the housing market is faltering. Chinese purchasers overtook Americans to become the biggest buyers of real estate in Australia in the 12 months through June 2013, plowing A$5.9 billion into commercial and residential property, a 42 percent increase from the previous 12 months.
Read the court decisionRead the full story...Reprinted courtesy of
Nichola Saminather, BloombergMs. Saminather may be contacted at
nsaminather1@bloomberg.net
Toolbox Talk Series Recap - Undocumented Change Work
October 15, 2024 —
Douglas J. Mackin - The Dispute ResolverIn the August 29, 2024 edition of Division 1's Toolbox Talk Series,
Don Rea presented on the causes of undocumented change order work and what actions parties to a construction project can take to protect themselves, which compliments and reinforces some of the key points from the
May 30, 2024 Toolbox Talk on maximizing profits while experiencing changes during project performance.
Article 7 of AIA A201 General Conditions covers (i) change orders, (ii) constructive change directives, and (iii) “minor changes.” Work that falls outside the scope of the construction contract will often fit into one of these three categories. Rea’s presentation focused on the fact that, regardless of which category applies, proper documentation of the change work is vital.
Read the court decisionRead the full story...Reprinted courtesy of
Douglas J. Mackin, Cozen O’ConnorMr. Mackin may be contacted at
dmackin@cozen.com