Colorado Rejects Bill to Shorten Statute of Repose
May 07, 2015 —
Jesse Howard Witt – Acerbic WittThe House State, Veterans, and Military Affairs committee voted today to postpone Senate Bill 15-091 indefinitely, effectively killing the bill for the 2015 session.
As originally drafted, the bill would have given Colorado the shortest statute of repose in the United States. Senate amendments softened the impact of the bill somewhat, but it still would have reduced the amount of time that the owners of single-family homes would have to discover construction defects. Proponents argued that this was necessary because Colorado’s harsh weather conditions make it difficult for construction to last longer than five years. Opponents countered that construction defect laws only provide relief when a builder has violated a code or standard, which is unrelated to the expected lifespan of a product.
One of the Representatives noted that states like Alaska have much harsher weather patterns yet allow homeowners to bring claims up to ten years after construction is complete. Another questioned whether the bill would do anything to encourage affordable housing, a topic that has generated substantial media attention in recent months.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, Acerbic WittMr. Witt welcomes comments at www.wittlawfirm.net
LaGuardia Airport Is a Mess. An Engineer-Turned-Fund Manager Has a Fix
May 26, 2019 —
Sree Vidya Bhaktavatsalam - BloombergThierry Déau’s engineering training in France led him early in his career to building government-funded infrastructure. But it was his entrepreneur father back home in Martinique who inspired him to strike out on his own in 2005. He started Paris-based Meridiam to finance, build, and manage long-term projects. Now, with €7 billion ($7.83 billion) in seven funds and nine offices across Europe, the Middle East, Africa, and North America, Meridiam is playing a key role in high-profile projects such as the upgrade of New York’s LaGuardia Airport and a road tunnel under the Port of Miami. Déau describes Meridiam’s investment approach in an interview with Bloomberg Markets.
Read the court decisionRead the full story...Reprinted courtesy of
Sree Vidya Bhaktavatsalam, Bloomberg
New Addition To New Jersey Court Rules Impacts More Than Trial Practice
November 16, 2020 —
Thomas Regan & Karley Kamaris - Lewis Brisbois NewsroomOn September 1, 2020, New Jersey adopted a brand-new rule of procedure, Rule 4:25-8, which properly defines motions in limine. On its face, the new rule prohibits, broadly, filing motions in limine that may have a dispositive effect on the case. Most notably, the rule expressly eliminates the ability to move, on motion in limine, to bar expert testimony in matters in which such experts are required to sustain a party’s burden of proof. This effectively makes the summary judgment phase of litigation the last chance to bar experts from a jury trial or take any other dispositive action
The new rule comes at a time in which the evidentiary standard for experts is shifting in New Jersey. In October 2018, the New Jersey Supreme Court reconciled the framework for analyzing the reliability of expert testimony under N.J.R.E. 702 and 703 in In re: Accutane Litigation. Significantly, New Jersey, a traditional Frye jurisdiction, incorporated certain federal Daubert factors for expert “use by our courts” but, overall, fell short of adopting the Daubert standard as a whole. In applying the relevant Daubert factors, the trial court in Accutane held that the subject experts’ methodologies were unsound due to the failure to apply fundamentals of the scientific method of the medical-evidence hierarchy. The decision resulted in the dismissal of over 3,000 claims.
Reprinted courtesy of
Thomas Regan, Lewis Brisbois and
Karley Kamaris, Lewis Brisbois
Mr. Regan may be contacted at Thomas.Regan@lewisbrisbois.com
Ms. Kamaris may be contacted at Karley.Kamaris@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Bailout for an Improperly Drafted Indemnification Provision
February 11, 2019 —
David Adelstein - Florida Construction Legal UpdatesA recent opinion came out that held that even though an indemnification provision in a subcontract was unenforceable per Florida Statute s. 725.06, the unenforceable portion is merely severed out of the indemnification clause leaving the rest of the clause intact. In essence, an otherwise invalid indemnification clause is bailed out by this ruling (which does not even discuss whether this subcontract had a severability provision that states that if any portion of any provision in the subcontract is invalid, such invalid portion shall be severed and the remaining portion of the provision shall remain in full force and effect).
This opinion arose from a construction defect case, CB Contractxors, LLC v. Allens Steel Products, Inc.,43 Fla.L.Weekly D2773a (Fla. 5thDCA 2018), where the general contractor, sued by an association, flowed down damages to subcontractors based on the contractual indemnification provision in the subcontracts. Subcontractors moved to dismiss the contractual indemnification claim because it was not compliant with Florida Statute s. 725.06. The indemnification provision required the subcontractors to indemnify the general contractor even for the general contractors own partial negligence, but failed to specify a monetary limitation on the extent of the indemnification as required by Florida Statute s. 725.06. (The indemnification clause in the subcontract was the standard intermediate form of indemnification that required the subcontractor to indemnify the general contractor for claims regardless of whether the claims were caused in part by the general contractor.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Dispute Over Exhaustion of Primary Policy
May 20, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn a dispute between the excess and primary carriers, the Fifth Circuit determined the primary policy was exhausted, triggering coverage under the excess policy. Amerisure Mut. Ins. Co. v. Arch Spec. Ins. Co., 2015 U.S. App. LEXIS 6627 (5th Cir. April 21, 2015).
Amerisure issued a CGL policy to Admiral Glass & Mirror Co. The policy provided excess over any coverage under a controlled insurance program policy. Arch issued an Owner Controlled Insurance Program (OCIP) policy to Endeavor Highrise, LP and to its contrators and subcontractors for bodily injury and property damage arising out of the construction of the Endeavor Highrise. Admiral was a subcontractor insured under the OCIP.
The OCIP had combined bodily injury and property damage limits of $2,000,000 per occurrence, a general aggregate limit of $2,000,000 and a products-completed operations aggregate limit of $2,000,000. The OCIP contained a Supplementary Payments provision which provided that Arch would pay "[a]ll expenses we incur" in connection with any covered claim, and that "[t]hese payments will not reduce the limits of insurance." Endorsement 16, however, expressly deleted and replaced this statement with: "[supplementary payments] will reduce the limits of insurance." The OCIP also provided that Arch's duty to defend ended "when we have used up the applicable limit of insurance in the payment of judgments or settlements."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Under the Hood of U.S. Construction Spending Is Revised Data
January 06, 2016 —
Vince Golle – BloombergHere’s one key takeaway from the Commerce Department’s report Monday on U.S. construction spending. The
0.4 percent decrease in November, which itself was weaker than the most pessimistic Bloomberg survey forecast, was accompanied by downward revisions to prior months. The combination suggests some economists may revise down their fourth-quarter GDP tracking forecasts.
* October construction spending rose 0.3 percent, compared with a prior estimate of 1 percent, while September outlays advanced 0.2 percent versus a previous estimate of a 0.6 percent gain
Read the court decisionRead the full story...Reprinted courtesy of
Vince Golle, Bloomberg
Super Lawyers Selects Haight’s Melvin Marcia for Its 2023 Northern California Rising Stars List
July 16, 2023 —
Melvin F. Marcia - Haight Brown & Bonesteel LLPCongratulations to Melvin Marcia who was selected to the 2023 Northern California Rising Stars list. Each year, no more than 2.5 percent of the lawyers in the state are selected by the research team at Super Lawyers to receive this honor. Super Lawyers, part of Thomson Reuters, is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The annual selections are made using a patented multiphase process that includes a statewide survey of lawyers, an independent research evaluation of candidates and peer reviews by practice area. The result is a credible, comprehensive and diverse listing of exceptional attorneys. The Super Lawyers lists are published nationwide in Super Lawyers magazines and in leading city and regional magazines and newspapers across the country. Super Lawyers magazines also feature editorial profiles of attorneys who embody excellence in the practice of law.
Read the court decisionRead the full story...Reprinted courtesy of
Melvin F. Marcia, Haight Brown & Bonesteel LLPMr. Marcia may be contacted at
mmarcia@hbblaw.com
What If Your CCP 998 Offer is Silent on Costs?
March 18, 2019 —
Tony Carucci - Snell & Wilmer Real Estate Litigation BlogIn California, the “prevailing party” in litigation is generally entitled to recover its costs as a matter of law. See Cal. Code Civ. Proc. § 1032. But under California Code of Civil Procedure section 998, a party may make a so-called “offer to compromise,” which can reverse the parties’ entitlement to costs after the date of the offer, depending on the outcome of the litigation. Cal. Code Civ. Proc. § 998. The potential payoff of a 998 offer is that “If an offer made by a defendant is not accepted and the plaintiff fails to obtain a more favorable judgment or award, the plaintiff shall not recover his or her postoffer costs and shall pay the defendant’s costs from the time of the offer.” Cal. Code Civ. Proc. § 998(c)(1) (emphasis added).
But how do you determine whether a plaintiff obtained a more favorable judgment when the 998 offer is silent with respect to whether it includes costs?
In Martinez v. Eatlite One, Inc. (2018) 27 Cal.App.5th 1181, 1182–83, the defendant made a 998 offer of $12,001 that was silent regarding the treatment of attorneys’ fees and costs. Plaintiff did not respond to the offer, and the jury ultimately awarded plaintiff damages of $11,490. Id. In resolving the parties’ competing memoranda of costs and plaintiff’s motion for attorneys’ fees, the trial court awarded plaintiff her costs and attorneys’ fees. Id. at 1182. The trial court reasoned that plaintiff had obtained a more favorable judgment than the 998 offer because she was entitled to pre-offer costs and attorneys’ fees under the statute, which meant plaintiff’s ultimate recovery exceeded the 998 offer when added to the judgment. Id. at 1183. In other words, the court added plaintiff’s pre-offer costs and attorneys’ fees to the $11,490 verdict for the purposes of determining whether the “judgment” was greater than the 998 offer of $12,001. Id.
Read the court decisionRead the full story...Reprinted courtesy of
Tony Carucci, Snell & WilmerMr. Carucci may be contacted at