When Are General Conditions and General Requirements Covered by Builder's Risk
December 18, 2022 —
Michael V. Pepe & Grace V. Hebbel - Saxe Doernberger & VitaGeneral conditions and general requirements are terms of art in the construction industry that describe the indirect costs necessary to complete a construction project. After physical loss or damage to a project, the following question often arises: Are “general conditions” and “general requirements” covered under a builder’s risk policy?
General Conditions vs. General Requirements
General conditions are usually described as the cost of managing a construction project. Examples include salaries for personnel like project managers, supervisors, engineers, field office staff, as well as the cost of field trailers, office equipment and supplies, and anything necessary to support the staff.
General requirements are the non-management indirect costs of executing the project, including items such as pre-development costs, permits, security, dumpsters, fences, temporary lighting, worker amenities, and clean-up costs.
Reprinted courtesy of
Michael V. Pepe, Saxe Doernberger & Vita and
Grace V. Hebbel, Saxe Doernberger & Vita
Mr. Pepe may be contacted at MPepe@sdvlaw.com
Ms. Hebbel may be contacted at GHebbel@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Whitney Stefko Named to ENR’s Top Young Professionals, formerly ENR’s Top 20 Under 40, in California
February 16, 2017 —
Haight Brown & Bonesteel LLPEvery year, Engineering News-Record (ENR) honors young professionals who are making a big splash in the construction industry. This year, ENR named Whitney Stefko to its list of individuals who represent the best of the best in the construction industry. In its feature article, “Top Young Professionals Make a Big Impact in Construction Industry,” Stefko is recognized for her expertise in professional liability and construction defense law, and her success in representing hundreds of cases on behalf of developers, general contractors, subcontractors and design professionals.
Read the court decisionRead the full story...Reprinted courtesy of
Whitney L. Stefko, Haight Brown & Bonesteel LLPMs. Stefko may be contacted at
wstefko@hbblaw.com
Contractor Prevailing Against Subcontractor On Common Law Indemnity Claim
June 29, 2020 —
David Adelstein - Florida Construction Legal UpdatesCommon law indemnity is not an easy claim to prove as the one seeking common law indemnity MUST be without fault:
Indemnity is a right which inures to one who discharges a duty owed by him, but which, as between himself and another, should have been discharged by the other and is allowable only where the whole fault is in the one against whom indemnity is sought. It shifts the entire loss from one who, although without active negligence or fault, has been obligated to pay, because of some vicarious, constructive, derivative, or technical liability, to another who should bear the costs because it was the latter’s wrongdoing for which the former is held liable.
Brother’s Painting & Pressure Cleaning Corp. v. Curry-Dixon Construction, LLC, 45 Fla. L. Weekly D259b (Fla. 3d DCA 2020) quoting Houdaille Industries, Inc. v. Edwards, 374 So.2d 490, 492-93 (Fla. 1979).
Not only must the one seeking common law indemnity be without fault, but there also needs to be a special relationship between the parties (indemnitee and common law indemnitor) for common law indemnification to exist. Brother’s Painting & Pressure Cleaning Corp., supra (citation omitted). A special relationship has been found to exist between a general contractor and its subcontractors. Id. at n.2.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
What is a Civil Dispute?
August 07, 2018 —
Bremer Whyte Brown & O’MearaBroadly speaking, all lawsuits can be put into one of two categories: criminal or civil. Criminal cases are brought by the government against a private person and/or organization for committing an act that is considered harmful to society as a whole; whereas civil cases involve private disputes between individuals and/or organizations.
Civil litigation begins when one person or organization claims that another person or organization has failed to carry out a legal duty owed to the claimant. Legal duties are those prescribed either by contract between the parties, or by the law.
In order for a claimant to commence legal action against another party, the claimant must file a summons and complaint with the court and serve a copy of the summons and complaint on the party against whom the lawsuit is being brought. The person who brings the lawsuit is called the “Plaintiff” and the person against whom the lawsuit is brought is called the “Defendant.”
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O’Meara
Does the Miller Act Trump Subcontract Dispute Provisions?
May 16, 2018 —
Christopher M. Horton - Smith CurrieAll general contractors performing public building or public works contracts with the federal government must be familiar with the Miller Act. It is a requirement for doing business with the federal government. Pursuant to the Miller Act, a general contractor entering into a public building or public works contract with the federal government must furnish a payment bond in an amount equal to the contract price, unless the contracting officer determines that it is impractical to obtain a bond in that amount and specifies an alternative bond amount.
Miller Act payment bonds guarantee payment to certain subcontractors and suppliers supplying labor and materials to contractors or subcontractors engaged in the construction. As a result, subcontractors have an avenue of relief should they not get paid for work done on the project. Specifically, subcontractors have a right to bring an action against the surety within 90-days after the date on which the person did or performed the last labor or furnished or supplied the last of material for which the claim is made. Any such action must be brought no later than one year after the date on which the person did or performed the last labor or furnished or supplied the last of material. 40 United States Code § 3133.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher M. Horton, Smith CurrieMr. Horton may be contacted at
cmhorton@smithcurrie.com
Planned Everglades Reservoir at Center of Spat Between Fla.'s Gov.-Elect, Water Management District
January 02, 2019 —
Miami Herald - Engineering News-RecordDec. 11 -- Florida's incoming governor stopped short of demanding South Florida water managers step down over a contentious land deal with sugar farmers, saying he would instead await a recommendation from his transition team. That doesn't mean their days may not be numbered.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
Appetite for Deconstruction
July 02, 2024 —
Patrick Sisson - BloombergThe death of 206 College Avenue was slow and painstaking. Over several days in January 2022, dozens of bundled-up volunteers swarmed over the three-story property, a tired wooden boarding house built in the early 1900s in Ithaca, New York. Long used as rental apartments for Cornell University students, the 13-bedroom house was set to be demolished, along with several neighboring structures of the same vintage, to make room for a new multi-use complex. But while those buildings were quickly reduced to rubble by trackhoes, the house at 206 was deconstructed, piece by piece, so that its elements could be used again.
The Catherine Commons Deconstruction Project, an effort by Cornell’s Circular Construction Lab, was a large-scale pilot designed to show how building waste can be kept out of landfills. As volunteers pulled nails out of fir, oak, and walnut boards and hauled lumber off to be sorted and redistributed, a team of eight workers with heavy machinery began meticulously sawing, slicing and removing 8-by-18-foot panels of the old building. These were trucked off to a warehouse, where they’d be taken apart and recycled.
The labor that went into this process was substantially more than a typical demolition. But it avoided the societal penalties left behind at nearly every building and demo site across the US. The sheer volume of waste generated by knocking down, adding to or renovating buildings in the US is stunning: 600 million tons of construction demolition waste annually, according to the most recent EPA estimate from 2018. Roughly 75% gets ground up into aggregate and fill, and only a small share is recycled and reused, necessitating production of new material for the next project. For scale, municipal solid waste only accounts for 300 million tons every year.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Sisson, Bloomberg
Two-Part Series on Condominium Construction Defect Issues
May 19, 2014 —
Beverley BevenFlorez-CDJ STAFFGregory L. Shelton, construction law attorney at Horack, Talley, Pharr & Lowndes, P.A., wrote a two-part series in the Charlotte Observer about condominium construction defect issues. The first part described “common defects and their consequences,” while the second part explained “how legal time limits can prevent the association or its owners from suing the parties responsible for defective construction.”
If interested in purchasing a condo unit, Shelton recommended hiring a building inspector, though he cautioned that “the inspector should be truly independent. His client should be you and not ‘the sale.’” In the second part, Shelton discussed the complexities of statutes of limitations and statutes of repose.
Read the full story, Part 1...
Read the full story, Part 2... Read the court decisionRead the full story...Reprinted courtesy of