“Families First Coronavirus Response Act”: Emergency Paid Leave for Construction Employers with Fewer Than 500 Employees
March 30, 2020 —
Sidney Lewis & Alex Glaser, Jones Walker LLP - ConsensusDocsCOVID-19 has already taken a toll on construction projects across the nation. Construction industry participants, including general contractors, now face risks and challenges that are exceedingly difficult to anticipate and plan for. The spread of this virus has and will continue to create new labor force issues and amplify existing ones.
On March 18, 2020, the House of Representatives passed H.R. 6021, the “Families First Coronavirus Response Act,” which, contains provisions related to mandatory paid leave for employers with fewer than 500 employees. This legislation and the substantial obligations it imposes apply to the overwhelming number of general contractors in the nation—those with less than 500 full-time employees! The bill mandates up to 80 hours of “emergency paid leave” related to COVID-19, and not just for those who contract the illness. However, contractors with less than 50 employees may seek exemption.
Reprinted courtesy of
Sidney Lewis, Jones Walker LLP and
Alex Glaser, Jones Walker LLP
Mr. Lewis may be contacted at slewis@joneswalker.com
Mr. Glaser may be contacted at aglaser@joneswalker.com
Read the court decisionRead the full story...Reprinted courtesy of
1st District Joins 2nd District Court of Appeals and Holds that One-Year SOL Applies to Disgorgement Claims
June 14, 2021 —
Garret Murai - California Construction Law BlogWe’re beginning to see a trend.
This past year, the 2nd District Court of Appeals, in Eisenberg Village of the Los Angeles Jewish Home for the Aging v. Suffolk Construction Company, 53 Cal.App.5th 1201 (2020), held for the first time that a one (1) year statute of limitations period beginning upon substantial completion of a project applies to disgorgement claims under Business and Professions Code section 7031. In San Francisco CDC LLC v. Webcor Construction L.P., the 1st District Court of Appeals became the second Court of Appeals in the state to hold that a one (1) year statute of limitations beginning upon completion or cessation of work on a project applies to disgorgement claims under Business and Professions Code section 7031.
The San Francisco CDC LLC Case
The Defect Action
In September 2005, San Francisco CDC LLC entered into a $144 million construction contract with Webcor Construction, Inc. doing business as Webcor Builders to build the InterContinental Hotel in San Francisco, California.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
NJ Transit’s Superstorm Sandy Coverage Victory Highlights Complexities of Underwriting Property Insurance Towers
February 24, 2020 —
Traub LiebermanIn New Jersey Transit Corp. v. Certain Underwriters at Lloyd’s, London, 2019 WL 6109144 (N.J. App. Div. Nov. 18, 2019), New Jersey Transit (“NJT”) defeated the claim of several of its insurers that a $100 million flood sublimit applied to its Superstorm Sandy damages and recovered the full $400 million limits of its property insurance tower. The decision is a big win for the beleaguered transit agency, and for insurance professionals working with complex insurance towers, the decision highlights critical underwriting issues that can dramatically affect the amount of risk transferred by the policyholder or assumed by the insurer.
In NJ Transit, NJT secured a multi-layered property insurance program providing $400 million in all-risk coverage. The first and second layers provided $50 million each, the third and fourth layers provided $175 million and $125 million, respectively, with several insurers issuing quota shares in each layer. The program contained a $100 million flood sublimit, and “flood” was defined to include a “surge” of water. The program did not contain a sublimit for damage caused by a “named windstorm,” which was defined to include “storm surge” associated with a named storm. After NJT made its Superstorm-Sandy claim, some of the third- and fourth-layer insurers advised NJT that the $100 million flood sublimit applied to bar coverage under their policies. NJT sued these excess insurers and won at the trial and appellate levels.
In holding that the $100 million flood sublimit did not apply, the court applied the rule of construction that the specific definition of “named windstorm,” which included the terms “storm surge” and “wind driven water,” controlled over the policies’ more general definition of “flood.” In ascertaining the parties’ intent, the court noted that the omission of the term “storm surge” in the definition of “flood” evidenced an intention that the flood sublimit would not apply to storm surges. Based on this finding, the court rejected several arguments made by the insurers that other policy provisions evidenced the parties’ intent to apply the flood sublimit to all flood-related losses, regardless of whether the loss was caused by a storm surge.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Million-Dollar U.S. Housing Loans Surge to Record Level
July 30, 2014 —
Alexis Leondis – BloombergBanks are handing out mortgages of as much as $10 million to the wealthy in record numbers while first-time homebuyers struggle to get loans.
Erin Gorman, managing director at Bank of New York Mellon Corp., said she’s fielding more requests for home loans of at least $2 million than ever before. She recently provided a mortgage of more than $6 million for a client’s purchase of a second property in Colorado.
“These high-net-worth borrowers do act differently than first-time buyers, who borrow because they have to,” said Gorman, who serves as the national mortgage sales director at Bank of New York Mellon’s wealth management group based in Boston. “High-net-worth borrowers don’t have to borrow. They choose to, so they’re very strategic about what, why, and when they borrow.”
Read the court decisionRead the full story...Reprinted courtesy of
Alexis Leondis, BloombergMs. Leondis may be contacted at
aleondis@bloomberg.net
Another Las Vegas Tower at the Center of Construction Defect Claims
November 07, 2012 —
CDJ STAFFAccusations are coming from both sides over construction defects at a Las Vegas tower, only this time, it’s not the Harmon Towers, it’s Hilton Grand Vacations, which is part of the Planet Hollywood Resort. The project was originally dubbed PH Towers Westgate, and it was developed by Westgate Resorts, which is suing the contractor, Tutor-Saliba for $10 million over late completion and construction defects.
Among the defects Westgate is claiming are cracked floor tiles in the valet lobby and cracks and delamination of the pool deck. Tutor-Saliba argues that the failure of the valet lobby floor is due to Westgate specifying only 1/16th inch-wide grouting, instead of the specified ¼ inch, and Westgate’s refusal to allow expansion joints on the pool deck has lead to problems there. Westgate’s attorney, Robert Schumacher, attributes the problems to “shoddy construction practices.”
According to the article in the Las Vegas Review Journal, plans were only 60 percent complete when construction began, leading to “thousands of change orders.” Despite not meeting an August completion deadline, Tutor-Saliba is claiming it is owed a $1.5 million bonus nevertheless.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Attorneys Recognized in the 2023 Edition of The Best Lawyers in America®
September 19, 2022 —
Traub LiebermanTraub Lieberman is pleased to announce that five Partners have been selected by their peers for inclusion in the 2023 edition of The Best Lawyers in America®. In addition, four attorneys have been included in the 2023 Best Lawyers®: Ones to Watch list. These recognitions include attorneys from the firm’s Hawthorne, NY; Chicago, IL; Palm Beach Gardens, FL; and St. Petersburg, FL offices.
2023 Best Lawyers®
Hawthorne, NY
- Lisa L. Shrewsberry – Commercial Litigation
Chicago, IL
- Brian C. Bassett – Insurance Law
Palm Beach Gardens, FL
- Rina Clemens – Personal Injury Litigation – Defendants
St. Petersburg, FL
- Scot E. Samis – Appellate Practice
- Lauren S. Curtis – Insurance Law
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Colorado Supreme Court Decision Could Tarnish Appraisal Process for Policyholders
September 16, 2019 —
Michael V. Pepe - Saxe Doernberger & Vita, P.C.On June 24, 2019, the Colorado Supreme Court ruled that the plain language of appraisal provisions in insurance policies, requiring “impartial appraisers,” direct appraisers to be “unbiased, disinterested, and unswayed by personal interest,” regardless of who hires them, and prohibits the party-appointed appraisers from acting as advocates.
A common and attractive alternative dispute resolution option, the appraisal process usually entails the policyholder and insurer each hiring their own appraiser, who estimates how much the claim is worth. These appraisers also select a third-party umpire, and if they cannot agree upon one, a court appoints one. The umpire analyzes the conflicting estimates and presents a number to resolve the dispute. If two of the three parties agree with the outcome, the number becomes binding.
Owners Ins. Co. v. Dakota Station II Condo. Ass'n, Inc.1 began when Dakota Station II Condominium Association Inc. (“Dakota”) and its insurer, Owners Insurance Company (“Owners”) could not agree on how to value two claims arising out of weather damage. To settle the differences and come to a resolution, Dakota invoked the appraisal provision in the insurance policy instructing each party to select its own “competent and impartial appraiser.” Ultimately, a court-appointed umpire considered six cost categories in dispute and adopted four of Owners’ estimates and two of Dakota’s.
Read the court decisionRead the full story...Reprinted courtesy of
Michael V. Pepe, Saxe Doernberger & Vita, P.C.Mr. Pepe may be contacted at
mvp@sdvlaw.com
No Coverage For Construction Defects Under Alabama Law
September 14, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court found there was no coverage for alleged defects caused by the insured homebuilder. Canal Indem. Co. v. Carbin, 2017 U.S. Dist. LEXIS 126662 (N.D. Ala. Aug. 10, 2017).
Carbin Construction filed suit against Aaron and Sherry Ford, asserting mechanic's and materialman's liens, and seeking sums allegedly due for work performed under a construction contract. The Fords filed a counterclaim, alleging that over a year had passed since Carbin was to complete construction, and that Carbin refused to do any further work on the house until he was paid an additional $11,771.43. The Fords further contended that Carbin had walked off the job after receiving 96.6 percent of the money owed under the contract although only 88 percent of the construction work had been completed. Carbin tendered the counterclaim to Canal. Canal then filed suit seeking a declaration that it had no duty to defend.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com