Failure to Meet Code Case Remanded to Lower Court for Attorney Fees
May 24, 2011 —
CDJ STAFFJudge Patricia J. Cottrell, ruling on the case Roger Wilkes, et al. v. Shaw Enterprises, LLC, in the Tennessee Court of Appeals, upheld the trial court’s conclusion that “the builder constructed the house in accordance with good building practices even though it was not in strict conformance with the building code.” However, Judge Cottrell directed the lower court to “award to Appellants reasonable attorneys' fees and costs incurred in their first appeal, as determined by the trial court.”
Judge Cottrell cited in her opinion the contract which specified that the house would be constructed “in accordance with good building practices.” However, after the Wilkes discovered water leakage, the inspections revealed that “that Shaw had not installed through-wall flashing and weep holes when the house was built.” The trial court concluded that:
“Separate and apart from the flashing and weep holes, the trial court concluded the Wilkeses were entitled to recover damages for the other defects they proved based on the cost of repair estimates introduced during the first and second trials, which the court adjusted for credibility reasons. Thus, the trial court recalculated the amount the Wilkeses were entitled to recover and concluded they were entitled to $17,721 for the value of repairs for defects in violation of good business practices, and an additional 15%, or $2,658.15, for management, overhead, and profit of a licensed contractor. This resulted in a judgment in the amount of $20,370.15. The trial court awarded the Wilkeses attorneys” fees through the Page 9 first trial in the amount of $5,094.78 and discretionary costs in the amount of $1,500. The total judgment following the second trial totaled $26,973.93.”
In this second appeal, Judge Cottrell concluded, that “the trial court thus did not have the authority to decide the Wilkeses were not entitled to their attorneys” fees and costs incurred in the first appeal.”
Read the court’s decision
Read the court decisionRead the full story...Reprinted courtesy of
Home Prices Up in Metro Regions
October 30, 2013 —
CDJ STAFFHousing prices in the largest metro regions beat expectations, rising 12.8% in August as compared to a year before. Analysts were expecting weaker increases; instead these have been the fastest increases in seven years.
The metropolitan area with the largest increase was Las Vegas, where houses increased in price by 29.2%. Three California regions — San Francisco, Los Angeles, and San Diego — also saw increases of greater than 20%.
Read the court decisionRead the full story...Reprinted courtesy of
JD Supra’s 2017 Reader’s Choice Awards
March 22, 2017 —
Garret Murai – California Construction Law BlogJD Supra, one of the world’s leading content distribution companies for the legal industry, announced its Readers’ Choice Awards for 2017 earlier this week. We were honored to be among a group of 200 authors selected from over 40,000 who published legal news, commentary and analysis on legal issues of importance to the clients we serve.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Builder Waits too Long to Dispute Contract in Construction Defect Claim
May 10, 2012 —
CDJ STAFFThe Louisiana Court of Appeals has affirmed the lower court’s judgment in the case of Richard v. Alleman. The Richards initiated this lawsuit under Louisiana’s New Home Warranty Act, claiming that they had entered into a construction contract with Mr. Alleman and that they quickly found that his materials and methods had been substandard. They sued for the cost of repairing the home and filing the lawsuit. Mr. Alleman countersued, claiming the Richards failed to pay for labor, materials, and services. By his claim, they owed him $12,838.80.
The trial court split the issues of liability and damages. In the first trial, the court concluded that there was a contact between Alleman and the Richards and that the New Home Warranty Act applied. Mr. Alleman did not appeal this trial.
The second trial was on the issue of damages. Under the New Home Warranty Act, the Richards were found to be entitled to $36,977.11 in damages. In a second judgment, the couple was awarded $18,355.59 in attorney’s fees. Mr. Alleman appealed both judgments.
In his appeal, Alleman contended that the trial court erred in determining that the Home Warranty Act applied. This was, however, not the subject of the trial, having been determined at the earlier trial. Nor did the court accept Alleman’s claim that the Richards failed to comply with the Act. The trial record made clear that the Richards provided Alleman with a list of problems with their home by certified mail.
The court did not establish whether the Richards told Alleman to never return to their home, or if Alleman said he would never return to the home, but one thing was clear: Alleman did not complete the repairs in the list.
A further repair was added after the original list. The Richards claimed that with a loud noise, a large crack appeared in their tile flooring. Mr. Alleman stated that he was not liable for this as he was not given a chance to repair the damage, the Richards hired the flooring subcontractors, and that the trial court rejected the claim that the slab was defective. The appeals court found no problem with the award. Alleman had already “refused to make any of the repairs.”
Finally Alleman made a claim on a retainage held by the Richards. Since Alleman did not bring forth proof at trial, the appeals court upheld the trial courts refusal to award a credit to Alleman.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Not Pandemic-Proof: The Ongoing Impact of COVID-19 on the Commercial Construction Industry
December 06, 2021 —
George B. Green Jr. - Construction ExecutiveThe impact of COVID-19 has been felt in nearly every industry and arena across the country, with the exception of construction—or so that is the general perception. Perceptions are often wrong though, and this one is no different. The truth is that the construction industry has been hit just as hard, if not harder, than every other industry.
As the COVID-19 pandemic struck in the spring of 2020, construction projects plowed forward full steam ahead. Roadwork seemed to increase and developers continued to systematically acquire property and initiate large-scale projects. Perhaps it was these observations that led many to the conclusion that construction was pandemic-proof as the rest of society attempted to cobble together something that vaguely resembled a normal business year. But the construction industry has endured many challenges over the last 18 months, and unfortunately, the challenges do not appear to be evaporating anytime soon.
The industry has been primarily affected in the areas of scheduling, manpower and permitting, which has ultimately affected pricing. The entire way jobs are scheduled has been turned upside down. The supply chain issues that many have experienced for everyday household items have hit the construction industry as well.
Reprinted courtesy of
George B. Green Jr., Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Green may be contacted at
ggreen@wwhgd.com
New Case Law Alert: Licensed General Contractors Cannot Sue Owners to Recover Funds for Work Performed by An Unlicensed Subcontractor
May 30, 2022 —
Michele A. Ellison & Samantha R. Riggen - Gibbs GidenThe opinion in Kim v. TWA Construction, Inc. (2022 Cal. App. LEXIS 412) issued by the Court of Appeal of California Sixth Appellate District, on May 13, 2022, makes it clear that a properly licensed general contractor cannot bring an action for compensation from an owner for work performed by an unlicensed subcontractor.
California licensing law has long made explicit that an unlicensed contractor cannot bring or maintain any action to collect or recover compensation for work that contractor performed unless they were duly licensed at all times during the performance of that work. This new ruling extends the scope of this restriction to licensed contractors who hired unlicensed subcontractors.
The Underlying Dispute
The case involved a dispute between property owners and their former general contractor and its principal (collectively “TWA”). The property owners hired TWA to construct a home, and during the early stages of the project, TWA hired an unlicensed subcontractor to perform tree trimming services and to remove a large eucalyptus tree. The subcontractor partially removed the eucalyptus tree, but was stopped by a neighbor, and it was discovered that the tree was partly located on the neighbor’s property. The neighbor brought suit against the property owners, and eventually TWA, for the damage. The property owners subsequently filed a cross-complaint against TWA, and TWA in turn filed a cross-complaint against the property owners.
Reprinted courtesy of
Michele A. Ellison, Gibbs Giden and
Samantha R. Riggen, Gibbs Giden
Ms. Ellison may be contacted at mellison@gibbsgiden.com
Ms. Riggen may be contacted at sriggen@gibbsgiden.com
Read the court decisionRead the full story...Reprinted courtesy of
Unbilled Costs Remain in Tutor Perini's Finances
October 23, 2018 —
Scott Van Voorhis – Engineering News-RecordTutor Perini is struggling to shake off long-running concerns over the hundreds of millions in unbilled costs that have been on the contractor’s balance sheet for years. The Sylmar, Calif.-based construction giant reported more than $1 billion in unbilled costs or receivables at the end of the second quarter, up by more than $100 million from the start of the year, according to the company’s federal filings. That was $100 million higher than at the end of 2016, when the amount was $832 million.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, ENRENR may be contacted at
ENR.com@bnpmedia.com
Digitalizing Cross-Laminated Timber Construction
August 28, 2018 —
Aarni Heiskanen - AEC BusinessA Finnish experimentation project has made cross-laminated timber construction more productive and creative by using digital modeling.
The office of &’ [Emmi Keskisarja & Janne Teräsvirta & Company Architects Ltd] looks rather like a prototype workshop. Intriguing scale models, a 3D printer, and a small CNC machine all give clues about the architects’ current project. They’re determined to make wood construction more collaborative and creative using digital technologies and cross-laminated timber (CLT).
Plenty of Room for Improvement
“I’m going to present our KIRA-digi project at WDBE 2018 in September. Incidentally, our wooden installation will be on display during Helsinki Design Week,” says Keskisarja. “We want to communicate with the public, not just within our professional circles, as architects typically do. The theme of the week is trust, something that’s missing in today’s construction.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi