California Mechanics’ Lien Case Treads Both Old and New Ground
July 27, 2020 —
Garret Murai - California Construction Law BlogPeople do the darnedest things. The next case, Carmel Development Company v. Anderson, Case No. H041005, 6th District Court of Appeals (April 30, 2020), involving a 10-plus year oral design and construction contract, inconsistent accounting practices, two mechanics liens, and side-agreements, takes us down some well traveled paths but also covers some new ground.
Carmel Development Company v. Anderson
Carmel Development Company, Inc. provided design and construction services at a luxury subdivision known as Monterra Ranch located in Monterey under an oral contract with developer Monterra LLC which spanned over more than a decade.
Between 1996 and 2008, Carmel was involved in the infrastructure design and construction of the subdivision including lot design and layout, the location of building envelopes on each lot, water and sewage system layout and design, and roadway design, construction and repair. When roughly half of the lots were developed and sold Monterra ran out of money and Carmel sued.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Architect Searches for Lost Identity in a City Ravaged by War
March 14, 2022 —
Donna Abu-Nasr & Mohamed Sheikh Nor - BloombergOmar Degan got used to being ridiculed when he sat down with developers. The architect wanted buildings to incorporate green spaces, use less glass but have bigger windows to allow in more air. They wanted to maximize profit.
Such a clash of visions between designer and constructor could, of course, happen anywhere. But the gulf between them was particularly wide in a place where people have been more focused on survival than sustainability.
Degan, 31, wants to transform the Somali capital of Mogadishu, a lofty ambition in a city that’s been defined by violence, piracy and terrorism over the past three decades. His persistence, though, has led to prominence by championing cultural heritage and buildings that are in tune with the environment during the frenzy of reconstruction in recent years.
Reprinted courtesy of
Donna Abu-Nasr, Bloomberg and
Mohamed Sheikh Nor, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Transition Study a Condo Board’s First Defense against Construction Defects
December 04, 2013 —
CDJ STAFFAccording to the advice provided by T. Allen Mott and Nicholas D. Cowie, condominium boards would be well advised to “hire an engineer or architect to perform a transition study,” since it would be preferable to repair any problems while warranties are still in effect. They also caution that the board must “determine whether the developer-created budget and reserve fund are adequate to cover the cost of maintaining the condominium’s construction over time.”
They note that discovered in time, some problems are easy to fix, but left unrepaired, they can result in “extensive, hidden property damage requiring associations to borrow money and assess unit owners to cover the entire cost of repairing the developer’s construction defects and resulting property damage. The goal, as they point out, is “an amicable repair resolution.”
Read the court decisionRead the full story...Reprinted courtesy of
Does the Miller Act Trump Subcontract Dispute Provisions?
May 16, 2018 —
Christopher M. Horton - Smith CurrieAll general contractors performing public building or public works contracts with the federal government must be familiar with the Miller Act. It is a requirement for doing business with the federal government. Pursuant to the Miller Act, a general contractor entering into a public building or public works contract with the federal government must furnish a payment bond in an amount equal to the contract price, unless the contracting officer determines that it is impractical to obtain a bond in that amount and specifies an alternative bond amount.
Miller Act payment bonds guarantee payment to certain subcontractors and suppliers supplying labor and materials to contractors or subcontractors engaged in the construction. As a result, subcontractors have an avenue of relief should they not get paid for work done on the project. Specifically, subcontractors have a right to bring an action against the surety within 90-days after the date on which the person did or performed the last labor or furnished or supplied the last of material for which the claim is made. Any such action must be brought no later than one year after the date on which the person did or performed the last labor or furnished or supplied the last of material. 40 United States Code § 3133.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher M. Horton, Smith CurrieMr. Horton may be contacted at
cmhorton@smithcurrie.com
Unlicensed Contractor Shoots for the Stars . . . Sputters on Takeoff
September 20, 2017 —
Garret Murai - California Construction Law BlogElon Musk . . .
Eccentric engineer.
Technology billionaire.
And, now, litigation bad ass.
Frequent readers of the California Construction Law Blog know that we’ve talked about the importance of being properly licensed when doing construction work and the risks to you if you don’t.
One California contractor recently found this out the hard way.
In Phoenix Mechanical Pipeline, Inc. v. Space Exploration Technologies Corp., California Court of Appeals for the Second District, Case No. B269186 (June 13, 2017), contractor Phoenix Mechanical Pipeline, Inc. (Phoenix) lost its boosters . . . err britches . . when it sued Elon Musk’s Space Exploration Technologies Corp. (Space X) due to its failure to have a California contractor’s license.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
New Law Impacting Florida’s Statute of Repose
June 29, 2017 —
Meredith N. Reynolds & K. Stefan Chin – Peckar & Abramson, P.C.On June 14, 2017, Governor Scott signed House Bill 377 into law, clarifying that Florida’s ten-year
Statute of Repose commences either when the work is completed or when final payment becomes
due, whichever is latest. The new law resolves a problem for contractors created by a recent Florida
court ruling that held the Statute of Repose to commence as late as when the owner made final
payment. The applicable amendments to Florida Statute Section 95.11 take effect on July 1, 2017
and apply to all causes of action that accrue on or after that date.
Perhaps the most critical component of a construction professional’s risk management program is
the length of time that it is liable for the work performed on a project. While contractual warranty
periods typically run one or two years from substantial completion, the true length of a contractor’s
post-completion obligation is measured by the “Statute of Repose,” which establishes the period of
time following the completion of construction that a lawsuit can be filed for construction defects.
Reprinted courtesy of
Meredith N. Reynolds, Peckar & Abramson, P.C. and
K. Stefan Chin, Peckar & Abramson, P.C.
Ms. Reynolds may be contacted at mreynolds@pecklaw.com
Mr. Chin may be contacted at kschin@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Mechanics Lien Release Bond – What Happens Now? What exactly is a Mechanics Lien and Why Might it Need to be Released?
January 04, 2021 —
William L. Porter - Porter Law GroupMechanics Lien Release Bond – What Happens Now? What exactly is a Mechanics Lien and Why Might it Need to be Released?
California law entitles unpaid contractors, subcontractors, and material suppliers to record a mechanics lien on property where they performed work or supplied materials. The mechanics lien attaches to the real property as a legal interest and secures the right to payment for the work performed and materials supplied. If payment is not forthcoming the mechanics lien allows the property where the work was performed and materials supplied to be sold under court order to satisfy the debt. It is a powerful remedy against owners and their agents who do not pay for work performed and materials supplied to improve the owner’s property.
A Mechanics Lien Release Bond Frees Property from a Mechanics Lien
Owners typically do not wish to have their property sold out from under them. Fortunately for owners, there is a method by which a mechanics lien can be substituted for another interest and sale of the property thereby avoided. This method is through the use of a mechanics lien release bond. California Civil Code §8424 allows a property owner or contractor effected by a mechanics lien to record a mechanics lien release bond equal to 125 percent of the lien amount with the County Recorder where the mechanics lien has been recorded. The effect of this is to substitute the mechanics lien release bond for the mechanics lien itself, thereby relieving the property from the possibility of that property being sold to satisfy the debt. Instead, any payment made will come from the release bond.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Although Property Damage Arises From An Occurrence, Coverage Barred By Business Risk Exclusions
July 08, 2011 —
Tred R. Eyerly - Insurance Law HawaiiThe homeowners hired the insured to raise the structure of their home twenty-four inches above the flood zone. Lafayette Ins. Co. v. Peerboom, 2011 U.S. Dist. LEXIS 58985 (S.D. Miss. June 2, 2011). When the insured’s crew returned from lunch one day, they found the house had fallen from hydraulic jacks being used to raise the structure a few inches at a time. There was substantial damage to the entire structure.
The homeowners sued, asserting several claims, including negligence and breach of contract. The complaint alleged the homeowners entered a contract with the insured to raise their structure while maintaining its integrity. However, the insured failed to use proper equipment, which caused the house to fall and be completely destroyed.
The insured tendered the claim to its insurer, Lafayette Insurance Company. Lafayette defended under a reservation of rights and filed suit for a declaratory judgment. Lafayette’s subsequent motion for summary judgment contended there was no “occurrence” alleged in the underlying complaint and, even if there was, the business risk exclusions barred coverage.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of