Michael S. Levine, Andrea DeField & Daniel Hentschel - Hunton Insurance Recovery BlogA coverage dispute arising as a result of property damage from Hurricane Frances, which occurred in 2004, will continue following a Florida appellate court decision in an action brought against Citizens Property Insurance Corp.
The insureds, Manor House, LLC, Ocean View, LLC, and Merrit, LLC, presented a claim to Citizens for damage sustained at nine apartment buildings as a result of Hurricane Florence. After payments for a portion of the property damage were sustained, Citizens continued to dispute the full amount due. Meanwhile, the insureds suffered lost rental income because of the delay. Ultimately, the insureds filed suit against Citizens alleging, among other things, breach of contract and fraud, and sought to recover extra-contractual damages for loss of rental income due to the delay in adjusting and repairing the damaged property.
The trial court granted Citizens’ motion for partial summary judgment on several issues, including Citizens’ motion for partial summary judgment regarding appraiser and umpire fees; motion for partial summary judgment to prevent the insureds from pursuing a claim for extra-contractual, consequential damages; and motion for judgment on the pleadings on the insured’s claim for fraud.
Reprinted courtesy of Hunton Andrews Kurth attorneys
Michael S. Levine,
Andrea DeField and
Daniel Hentschel
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. DeField may be contacted at adefield@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Collapse of Breezeway Attached to Building Covered
February 24, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court found that a breezeway that collapsed during a party was covered by the commercial property policy. DENC, LLC v. Philadelphia Indem. Ins. Co., 2019 U.S. Dist. LEXIS 179083 (M.D. N.C. Oct. 15, 2019).
DENC owned an apartment complex that was insured by Philadelphia under an all-risk policy. During an early morning party, a large number of students gathered on the second-floor breezeway for a party. The students started jumping in the breezeway when a certain song started playing. The floor abruptly collapsed underneath the students.
Philadelphia sent an adjuster to inspect the breezeway a couple days later. He wrote to Philadelphia that "the sole and proximate cause of the loss is water damage occurring over an extended period of time causing the second floor breezeway to sage and the light weight concrete to crack." Shortly thereafter, the building was condemned. A structural engineer found multiple ways in which water had seeped into the breezeway's wood framing and photographed the resulting biological growth and wood decay. He concluded that the building had sustained significant long-term water intrusion which resulted in the wood framing inability to support the loads. The water intrusion was caused by the failure to properly install a water management system on the walls, a properly integrated waterproof system for the walkway slab and framing configuration, and improper venting of dryers.
DENC retained an engineer who testified that the breezeway was sagging because the concrete had broken.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
San Francisco International Airport Reaches New Heights in Sustainable Project Delivery
November 21, 2022 —
Aileen Cho - Engineering News-RecordTen years ago, Geoff Neumayr decided he was tired of “doing design and construction by combat.” San Francisco International Airport had completed a master plan for the complex and the front of the airport facilities doing things the traditional way.
Reprinted courtesy of
Aileen Cho, Engineering News-Record
Ms. Cho may be contacted at choa@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
2024 Construction Law Update
December 23, 2023 —
Garret Murai - California Construction Law BlogWe would like to wish you and yours a happy holiday season as we approach 2024.
The first half of the 2023-2024 legislative session saw the introduction of 3,028 bills, which, according to legislative observers, are the most bills introduced in a session in more than a decade, perhaps reflecting the fact that California has a record number of new legislators with over a quarter taking the oath of office for the first time. Of these bills, Governor Newsom signed nearly 400 into law including several impacting the construction industry related to climate change and housing affordability.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Final Furnishing Date is a Question of Fact
November 10, 2016 —
David Adelstein – Florida Construction Legal UpdatesConstruction liens need to be recorded within 90 days from the lienor’s final furnishing date on the project. This date is exclusive of punchlist or warranty work. The final furnishing date needs to be proven at trial to establish that the construction lien was timely recorded. If there is an evidentiary dispute as the final furnishing date (the contractor claims the date was “x” to establish the lien was timely and the owner claims the date was “y” to establish the lien was untimely), then the date is a question of fact to be determined by the jury.
For instance, in Best Drywall Services, Inc. v. Blasczyk, 2016 WL 6246701 (Fla. 2d DCA 2016), a contractor and owner entered into an oral agreement for a residential renovation project. The contractor recorded a construction lien after its final two invoices went unpaid. During trial, the contractor offered conflicting evidence as to when its final furnishing date on the project was. Numerous dates were offered in the record including dates that were more than 90 days prior to the date the contractor recorded its lien, meaning the lien was arguably untimely. As a result, the trial judge entered a directed verdict in favor of the owner and against the contractor on the contractor’s lien claim finding the lien was untimely recorded.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
Federal Defend Trade Secrets Act Enacted
July 14, 2016 —
Michael B. McClellan & Jason L. Morris – Newmeyer & Dillion LLPOn May 11, 2016, President Obama signed the Defend Trade Secrets Act (“DTSA”) into law,
creating a private federal civil cause of action for trade secret misappropriation. This landmark
legislation, a product of bipartisan backing and significant support from the business
community, will affect businesses and individuals operating in almost every economic sector
across the country. The DTSA will potentially be at issue any time an employee with access to
confidential, proprietary, and trade secret information moves on to a competitor or launches
a startup that competes with the former employer. This will be true so long as the product
or service that the trade secret relates to is either used in or intended for use in interstate
or foreign commerce. Under present commerce clause jurisprudence, the vast majority of
businesses providing products and services in the United States will be affected by this new law.
The DTSA will provide, for the first time, a codified federal civil remedy for
misappropriation of trade secrets. Although most states have adopted some version of the
Uniform Trade Secrets Act (“UTSA”), there remains significant variation between the states in
their application of the UTSA and litigants face significantly different statutory frameworks
depending upon which state holds jurisdiction over the dispute. In addition, prior to this
new law, litigants were limited to pursuing their claims for misappropriation of trade secrets
in state courts, unless federal diversity jurisdiction applied to the dispute. The DTSA changes
that dynamic, providing original federal subject matter jurisdiction over trade secret disputes.
Reprinted courtesy of
Michael B. McClellan, Newmeyer & Dillion and
Jason L. Morris, Newmeyer & Dillion
Mr. McClellan may be contacted at Michael.mcclellan@ndlf.com
Mr. Morris may be contacted at Jason.morris@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Singer Ordered to Deposition in Construction Defect Case
December 30, 2013 —
CDJ STAFFThe pop singer Rihanna has sued the former owners of her Los Angeles home and the firm that inspected it before her purchase alleging water intrusion problems that were supposed to be fixed before close of escrow. The lawsuit was filed under the singer’s legal name, Robyn Fenty. According to Gregory Pyfrom, the attorney for LaRocca Inspection Associates, he has tried to depose her over the last two years, without success. He is seeking $7,500 in compensation to his clients for the singer’s failure to schedule a deposition.
Rihanna’s attorney, Miles Cooley, described this as “a smear campaign,” and claims that the parties had agreed not to depose her “until after the matter was mediated.” Mr. Cooley says that mediation has been delayed by Mr. Pyfrom’s vacation plans.
LaRocca Inspection Associates has countersued Rihanna, claiming that if she had alerted them earlier to problems they would have performed an additional inspection. The judge in the case has now ordered that the parties agree to a date on which to depose Ms. Fenty.
Read the court decisionRead the full story...Reprinted courtesy of
Court of Appeals Discusses Implied Duty of Good Faith and Fair Dealing in Public Works Contracting
August 17, 2017 —
Lindsay K. Taft - Ahlers & Cressman PLLCThe implied duty of good faith and fair dealing is implied in every contract, including construction contracts. Generally speaking, this implied duty requires parties cooperate with one another so that they each obtain the full benefit of their contracted bargain. Recently, the Court of Appeals (Division II) in Nova Contracting, Inc. v. City of Olympia discussed this duty’s application to a public works contract.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay K. Taft, Ahlers & Cressman PLLCMs. Taft may be contacted at
ltaft@ac-lawyers.com