Insurer's Attempt to Limit Additional Insured Status Fails
December 01, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe court disagreed with the insurer's attempt to limit additional insured status based upon the contract between the parties. Mays v. In re All C-Dive LLC, 2017 U.S. Dist. LEXIS 185874 (E.D. La. Nov. 9, 2017).
Five employees of C-Dive LLC filed a lawsuit after belng injured in a pipeline explosion aboard a vessel servicing a pipeline owned by Gulf South Pipeline Company. During the work, there was a release of gas that caused an explosion and injured the employees.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Toolbox Talk Series Recap – Arbitration Motion Practice
August 07, 2023 —
Michael Zehner - The Dispute ResolverIn the June 22, 2023 edition of the Toolbox Talk Series,
Adrian Bastianelli, Peckar & Abramson, P.C., and
Brian Cashmere, Williams Mullen, moderated by Jennifer Millender of the American Arbitration Association (“AAA”), discussed motion practice in arbitration. Specifically, they offered advice on how to choose the right issue for a motion, how to get approval for a motion, how to write the motion, and how to get the arbitrator to grant it. They also discussed the pros and cons of motion writing in arbitration settings.
1. How to choose the “right issue” for a motion in arbitration
The panel discussed what type of issues can, or should, be brought up in a motion in arbitration. Cashmere stated that a clear and concise issue is best for this type of review. For example, statute of limitations, notice, or contract interpretation issues may make great summary judgment or partial summary judgment motions. Essentially, an issue that the arbitrator may resolve via primarily a question of law is more likely to succeed. Bastianelli warned against submitting just any “available” motion, as the practice may turn the arbitrator against you. Both panelists mentioned the need to consider strategy before filing a motion—ask, “how will filing this motion help or hurt reachingArbi final resolution.” Cashmere noted that sometimes the threat of bringing the issue to a hearing can put pressure on the adverse party in a way that is favorable to your client’s goals; possibly even more so than actually submitting the issue.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Zehner, BBG Construction LawMr. Zehner may be contacted at
mzehner@bbglaw.com
Kansas Man Caught for Construction Scam in Virginia
December 20, 2012 —
CDJ STAFFA Virginia court sent charges of construction fraud against a Kansas man to a grand jury. Larry Foster visited homes in Bedford County, Virginia, tested the water, and told homeowners that they needed new water filtration systems. The homeowners paid, but Mr. Foster never delivered. One homeowner who testified paid him $1,690. Another paid even more, giving $3,090 to Mr. Foster. In order to dupe his victims, Foster used the address of a chiropractor as a business address, unbeknownst to the actual business there.. He is wanted for charges in other states as well.
Read the court decisionRead the full story...Reprinted courtesy of
Fact of Settlement Communications in Underlying Lawsuits is Not Ground for Anti-SLAPP Motion in Subsequent Bad Faith Lawsuit
August 24, 2020 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Trilogy Plumbing, Inc. v. Navigators Specialty Ins. Co. (No. G057796, filed 5/27/20, ord. pub. 6/18/20), a California appeals court ruled that an insurance bad faith lawsuit alleging a variety of claim handling misconduct in defending the insured was not subject to an insurer’s special Strategic Lawsuit Against Public Participation (SLAPP) motion to strike because, while the alleged acts were generally connected to litigation, they did not include any written or oral statement or writing made in connection with an issue under consideration or review by a judicial body and, therefore, did not constitute protected activity under California’s anti-SLAPP statute.
In Trilogy Plumbing, the policyholder was sued in 33 different construction defect lawsuits, some of which Navigators defended, and others which were denied or had the defense withdrawn. The Navigators’ policies were subject to a $5,000 deductible, and Trilogy alleged that Navigators breached the contracts by “demanding deductible reimbursement amounts greater than the policies’ $5,000 stated deductible, and by seeking reimbursement of ordinary defense fees and expenses as if they were subject to deductible reimbursement,” “claiming a right to seek reimbursement from Trilogy for defense fees and expenses Navigators paid for the benefit of third-party additional insureds,” “providing conflicted defense counsel who took instructions only from Navigators without disclosing conflicts of interest,” “failing to reasonably settle cases and by withdrawing [the] defense as a strategic means of trying to force Trilogy to fund its own settlements,” “misrepresenting its deductible provisions,” “refusing to account for deductible amounts it charges and collects,” and others.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Around the State
March 27, 2019 —
Richard Glucksman & Chelsea Zwart – Construction Claims MagazineIn late 2018, Governor Jerry Brown signed two potentially impactful Senate bills relating to the construction of apartment buildings. These bills, discussed further below, were introduced, in part, in response to the Berkeley balcony collapse in June 2015, which was determined by the California Contractors State License Board to have been caused by the failure of severely rotted structural support joists—the repairs of which were deferred by the property manager despite indications of water damage.
In addition, 2018 saw the passage of California’s updated 2019 Building Energy Efficiency Standards. The new standards, which take effect in 2020, require, in part, the installation of solar systems on certain homes. The goal of the standards is to significantly decrease the energy usage in new homes while contributing to California’s greenhouse gas emissions reduction plans. Relatedly, new legislation, effective in 2019, aims to increase consumer protections for homeowners purchasing solar energy systems.
Reprinted courtesy of
Richard H. Glucksman, Chapman, Glucksman, Dean, Roeb & Barger and
Chelsea Zwart, Chapman, Glucksman, Dean, Roeb & Barger
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Ms. Zwart may be contacted at czwart@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractor Liable for Soils Settlement in Construction Defect Suit
February 10, 2012 —
CDJ STAFFThe California Court of Appeals ruled on January 9 in Burrow v. JTL Dev. Corp., a construction defect case in which houses suffered damage due to improperly compacted soil, upholding the decision of the lower court.
Turf Construction entered into a deal with JTL to develop a parcel they acquired. A third firm, Griffin Homes, withdrew from the agreement “when a geotechnical and soils engineering firm reported significant problems with soil stability on 14 of the lots.” Turf Construction then took over compacting and grading the lots. Turf “had never compacted or graded a residential tract before.” Robert Taylor, the owner of Turf, “testified he knew there was a significant problem with unstable soils.”
After homes were built, the plaintiffs bought homes on the site. Shortly thereafter, the homes suffered damage from soil settlement “and the damage progressively worsened.” They separately filed complaints which the court consolidated.
During trial, the plaintiff’s expert said that there had been an inch and a half in both homes and three to five inches in the backyard and pool areas. “He also testified that there would be four to eight inches of future settlement in the next fifteen to twenty years.” The expert for Turf and JTL “testified that soil consolidation was complete and there would be no further settlement.”
Turf and JTL objected to projections made by the plaintiffs’ soil expert, William LaChappelle. Further, they called into question whether it was permissible for him to rely on work by a non-testifying expert, Mark Russell. The court upheld this noting that LaChappelle “said that they arrived at the opinion together, through a cycle of ‘back and forth’ and peer review, and that the opinion that the soil would settle four to eight inches in fifteen to twenty years was his own.”
Turf and JTL contended that the court relied on speculative damage. The appeals court disagreed, stating that the lower court based its award “on evidence of reasonably certain damage.”
Turf also that it was not strictly liable, since it did not own or sell the properties. The court wrote that they “disagree because Turf’s grading activities rendered it strictly liable as a manufacturer of the lots.” The court concluded that “Turf is strictly liable as a manufacturer of the lots.”
Judge Coffee upheld the decision of the lower court with Judges Yegan and Perren concurring.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Crossrail Audit Blames Busted Budget and Schedule on Mismanagement
August 13, 2019 —
Peter Reina - Engineering News-RecordIn a new report on London’s Crossrail, the U.K. National Audit Office says the beleaguered transportation project is around two years late and nearly 20% over budget because of poor management. The NAO, charged by Parliament with monitoring public spending, pointed to ill-conceived “aspirational” plans that proved to be unfit for the technologically challenging and vast program when things went wrong.
Read the court decisionRead the full story...Reprinted courtesy of
Peter Reina, ENR
Protect Your Right To Payment By Following Nedd
August 03, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogIn order to preserve your right to payment, you must satisfy the contractual requirements supporting a change order for the increased costs or time due to the delay. The key to the successful presentation of change order claims is educating your team on the following:
1. NOTICE
- Review the change order and notice provisions of your contracts. Make your contract searchable and insert the term “Noti” and look for the items listed below.
- Who: Check the designated representative for notice.
- It may not be the project manager.
- Confirm who can authorize the change order.
- Is owner approval required?
- Ensure that the party approving the change order has authority to do so.
- What: Check for specific information required by the contract.
- Provide ALL information available.
- If certain information is not yet available, state that the information will be provided when available.
- Reserve all rights to amend and submit additional information.
- Request both an increase to the Contract Sum and Contract Time.
- Make the request even if you do not believe the delay or time necessary will cause a significant impact.
Read the court decisionRead the full story...Reprinted courtesy of
Denise Motta, Gordon Rees Scully Mansukhani, LLPMs. Motta may be contacted at
dmotta@grsm.com