Understanding Entitlement to Delays and Proper Support
December 10, 2024 —
Andrew G. Vicknair - The Dispute ResolverIn a previous
post, we discussed delays on construction projects including (1) critical versus non-critical delays, (2) excusable versus non-excusable delays, and (3) compensable versus non-compensable delays. We also reviewed the common methods of delay analysis include (1) the Total Cost Method, (2) the Modified Total Cost Approach, and (3) the Measured Mile Method.
Once you have determined the type of delay and the method to be used to analyze and quantify the delay, it is important to understand the type of documents/evidence needed to support your claim for delay.
If a party determines that they are entitled to some type of recovery for the delay, the party making a claim for delay, such as a contractor, must have the proper documentation/evidence to assist in proving entitlement for damages from the delay. Without the proper back-up, contractors are generally unable to recover all of the additional costs and expenses associated with the delays or, at best, recover only an “equitable” amount. Generally, damages must be proved with reasonable certainty and may not be based on speculation or conjecture. Thus, it is crucial for a party asserting a delay to have the proper documentation to support a delay claim, if the goal is to recover the damages associated with the delay.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew G. Vicknair, D'Arcy Vicknair, LLCMr. Vicknair may be contacted at
agv@darcyvicknair.com
Defining Constructive Acceleration
March 22, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to the definition of “constructive acceleration,” the case of Fraser Const. Co. v. U.S., 384 F.3d 1354 (Fed.Cir. 2004) is a cited case and contains an instructive definition, quoted below, for proving a constructive acceleration claim.
In a nutshell, a constructive acceleration claim is when the contractor incurs added costs for trying to complete the contract on time when it should be provided extensions of time to perform based on excusable delay (i.e., delay not caused by the contractor). These added costs could be bringing in additional supervision to manage the work, adding manpower to perform the work, working overtime, working weekends, adding more shift work, stacking trades, etc. However, just because a contractor claims they have been constructively accelerated does not make it so. The contractor has to actually ask for an extension of time based on an excusable delay and the owner either denied the extension or unreasonably sat on the request for an extension of time; thus, the contractor incurred significant costs to accelerate in order to finish the project on time because it was deprived of a requested time extension for excusable delay.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Arizona Contractor Designs Water-Repellant Cabinets
September 09, 2011 —
CDJ STAFFDubbing his product “Baltic Duck,” a Mesa, Arizona building contractor is offering household cabinets made with specially treated water-repellent plywood instead of the usual particle board. Pete Celano calls his product Baltic Duck because the plywood is made in the Baltic region of Eastern Europe. To further protect the cabinets from moisture, a silicone-based sealant is applied to the corners and edges.
Celano’s cabinets use standard decorative fronts. The design of the cabinets allows spilled liquids to drain away without encountering the decorative wood.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Indiana Court of Appeals Holds That Lease Terms Bar Landlord’s Carrier From Subrogating Against Commercial Tenant
April 03, 2019 —
Gus Sara - The Subrogation StrategistIn Youell v. Cincinnati Ins. Co., 2018 Ind. App. LEXIS 497 (2018), the Court of Appeals of Indiana considered whether a landlord’s carrier could bring a subrogation claim against a commercial tenant for fire-related damages when the lease, which did not reference subrogation, explicitly required the landlord to maintain fire insurance coverage for the leased premises. The court held that subrogation was barred because the provision requiring the landlord to maintain fire insurance established an agreement to provide both parties with the benefits of insurance. The Youell case establishes that, in Indiana, if the lease explicitly states that the landlord will maintain fire casualty insurance for the building, the lease evidences an agreement by the parties to shift the risk of loss to the insurer. This agreement bars a landlord’s insurance carrier from subrogating against a commercial tenant in the event of a casualty.
In 2013, the building owner, Greg Dotson, began leasing a commercial building to Robert Youell for his tire business, Best One Giant Tire, Inc. (collectively, Youell). The lease agreement required that the landlord maintain fire and extended coverage insurance on the building and the leased premises. The lease also required the tenant to purchase fire and extended coverage insurance for its personal property. The lease did not mention subrogation. Dotson obtained a property insurance policy through Cincinnati Insurance.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com
Cold Weather Causes Power Blackouts, Disruptions on Jobsites
February 22, 2021 —
Autumn Cafiero Giusti - Engineering News-RecordA February cold snap in the central U.S. has created record power demand, resulting in outages from Texas to North Dakota and contractors bracing for delays and damage from weather impacts.
Reprinted courtesy of
Autumn Cafiero Giusti, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
What Every Project Participant Needs to Know About Delay Claims
August 05, 2024 —
Andrew G. Vicknair - The Dispute ResolverA “delay” on a construction project is defined as the stretching out of the time for completion of certain key milestone scopes of work which can impact the completion date of an entire project, due to some circumstances or events that were not reasonably anticipated when the project began. 2 Construction Law ¶ 6.01 (Matthew Bender, 2024). While delays can be caused by any number of events, the most common are defective plans and specifications; design changes; severe weather and other, similar unforeseeable events; unforeseen or differing site conditions; unavailability of materials or labor; labor inefficiencies or stoppages; contractor negligence; and owner influences, including construction changes or outright interference by the owner or its agents. If the project schedule is not recovered following a delay, then the project schedule will likely be extended, resulting in an increase in the contractor’s costs of performance. A contractor that has experienced a delay on a project can take certain actions to pursue recovery of any damages the contractor may have incurred. However, to do so it is important to understand the different types of delays and the methods for establishing the delays.
I. Types of Delays
Delays may be categorized as (1) critical versus non-critical delays, (2) excusable versus non-excusable delays, and (3) compensable versus non-compensable delays. A critical delay is a delay that affects the project completion date and delays the entire project. In essence, a critical delay is one that will extend the critical path of a project. A non-critical delay is a delay that has no effect on the project’s critical path. Courts have recognized that delays to work not on the critical path will generally not delay the completion of a project. G.M. Shupe, Inc. v U.S., 5 Cl. Ct. 662, 728 (1984). Such a non-critical delay may affect the completion of certain activities, but does not affect the completion date of the entire project. In order for a delay to provide the basis for a claim for additional time or money, the delay must impact critical path activities on the project schedule.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew G. Vicknair, D'Arcy Vicknair, LLCMr. Vicknair may be contacted at
agv@darcyvicknair.com
SB 939 Proposes Moratorium On Unlawful Detainer Actions For Commercial Tenants And Allows Tenants Who Can't Renegotiate Their Lease In Good Faith To Terminate Their Lease Without Liability
June 01, 2020 —
Rhonda Kreger – Newmeyer DillionSB 939 is currently working its way through the Senate Judiciary Committee. The legislation would impose new obligations on landlords, and provide protections for commercial tenants who meet specified criteria. SB 939 would impose a moratorium on eviction of those qualified commercial tenants while emergency COVID-19 orders are in effect. Any eviction actions commenced after the date of the emergency COVID-19 order, but before the adoption of SB 939, would be void and unenforceable. The Senate Judiciary Committee has scheduled a hearing for SB 939 on May 22, 2020, at 9:00 a.m.
Who qualifies as a commercial tenant under SB 939?
To qualify under this legislation, a commercial tenant must be a business that operates primarily in California. The commercial tenant must be a small business, nonprofit, an eating or drinking establishment, place of entertainment, or performance venue. Publicly traded companies or any company owned by, or affiliated with a publicly traded company, do not qualify. The commercial tenant must have experienced a decline of at least 40 percent monthly revenue, either as compared to two months before the emergency COVID-19 order, or other local government shelter-in-place orders took effect, or as compared to the same month in 2019. If the commercial tenant is an eating or drinking establishment, place of entertainment, or performance venue, the commercial tenant must also show a decline of 25 percent or more in capacity due to social or physical distancing orders or safety concerns, and show that it is subject to regulations to prevent the spread of COVID-19 that will financially impair the business when compared to the period before the emergency COVID-19 order or other local shelter-in-place orders took effect.
What eviction actions are prohibited while emergency COVID-19 orders are in effect?
If adopted, SB 939 would add Section 1951.9 to the Civil Code. This section would make it unlawful to terminate a tenancy, serve notice to terminate a tenancy, use lockout or utility shutoff actions to terminate a tenancy or otherwise evict a tenant of commercial real property, including a business or nonprofit, during the pendency of the COVID-19 emergency order proclaimed by Governor Newsome on March 4, 2020. Exceptions apply if a tenant poses a threat to the property, other tenants or a person, business or other entity. Any violations of this eviction prohibition would be against public policy and unenforceable.
Any eviction started after proclamation of the state of emergency but before the effective date is deemed void, against public policy and is unenforceable.
Does SB 939 impose new penalties or remedies?
Any landlord who harasses, mistreats or retaliates against a commercial tenant to force the tenant to abrogate the lease would be subject to a fine of $2,000 for each violation. Further, any such violation would be an unlawful business practice and an act of unfair competition under Section 17200 of the Business and Professions Code and would be subject to all available remedies or penalties for those actions under state law.
When is a commercial tenant required to pay unpaid rent due to COVID-19?
If a commercial tenant fails to pay rent during the emergency COVID-19 order, the sum total of the past due rent must be paid within 12 months following the date of the end of the emergency proclamation, unless the commercial tenant has successfully negotiated an agreement with its landlord to pay the outstanding rent at a later date. Nonpayment of rent during the state of emergency cannot be used as grounds for eviction. Notwithstanding lease terms to the contrary, landlords may not impose late charges for rent that became due during the state of emergency.
Are landlords required to provide notice of protections adopted under SB 939?
Landlords would be required to provide notice to commercial tenants of the protections offered under SB 939 within 30 days of the effective date. SB 939 does not preempt local legislation or ordinances restricting the same or similar conduct which impose a more severe penalty for the same conduct. Local legislation or ordinances may impose additional notice requirements.
Does SB 939 impose new protections for commercial tenants when negotiating lease modifications?
If enacted, SB 939 would permit commercial tenants to open negotiations for new lease terms, and provide commercial tenants the ability to terminate the lease if those negotiations fail. A commercial tenant who wishes to modify its commercial lease, may engage in good faith negotiations with its landlord to modify any rent or economic requirement regardless of the term remaining on the lease. The commercial tenant must serve a notice on the landlord certifying that it meets the required criteria, along with the desired modifications.
If the commercial tenant and landlord do not reach a mutually satisfactory agreement within 30 days, then within 10 days, the commercial tenant may terminate the lease without any liability for future rent, fees, or costs that otherwise may have been due under the lease by providing a written termination notice to the landlord. The commercial tenant would be required to pay previously due rent, in an amount no greater than the sum of the following: (1) the actual rent due during the emergency COVID-19 order, or a maximum of three months of the past due rent during that period, and (2) all rent incurred and unpaid during a time unrelated to the emergency COVID-19 order through the date of the termination notice. The payment is due within 12 months from date of the termination notice. The commercial tenant would be required to vacate the premises within 14 days of the landlord's receipt of the termination notice. Upon service of the notice, any lease, and any third party guaranties of the lease would terminate. If the landlord and commercial tenant reach an agreement to modify the lease, the commercial tenant would not have the option to later terminate the lease under this provision.
When is the next Senate Judiciary Committee Meeting for SB 939?
The Senate Judiciary Committee set a hearing for SB 939 on May 22, 2020 at 9:00 a.m. The Senate will livestream the hearing on its website at www.sen.ca.gov. Public comments or testimony may be submitted in writing to the Judiciary Committee by emailing Erica.porter@sen.ca.gov. Alternatively, the public may participate via telephone during the public comment period. Any changes to the Judicial Committee schedule may be found at: https://www.senate.ca.gov/calendar.
Newmeyer Dillion continues to follow COVID-19 and its impact on your business and our communities. Feel free to reach out to us at NDcovid19response@ndlf.com or visit us at www.newmeyerdillion.com/covid-19-multidisciplinary-task-force/.
Rhonda Kreger is Senior Counsel on Newmeyer Dillion's transactional team at our Newport Beach office. Her practice focuses on all aspects of commercial real estate law, with a particular emphasis on the representation of residential developers, merchant builders and institutional investors. You can reach Rhonda at rhonda.kreger@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Latest Updates On The Coronavirus Pandemic
March 30, 2020 —
ENR Editors - Engineering News-RecordCoronavirus has struck a heavy blow against the world economy as it forces countries into lockdown with "closed for business" signs, hollows out the tourism, travel and hospitality sectors, turns out the lights on business gatherings and events, sends employees home to work and drives the stock market into a dizzying tumble.
ENR Editors
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story for ENR's ongoing reporting, analysis and commentary on construction sector developments
Read the court decisionRead the full story...Reprinted courtesy of