The Construction Project is Late—Allocation of Delay
November 17, 2016 —
David Adelstein – Florida Construction Legal UpdatesThe construction project is late. Very late. The owner is upset and notifies the contractor that it is assessing liquidated damages. The contractor, in turn, claims that the project is late because of excusable, compensable delays and, perhaps, excusable, noncompensable delays. This is a common and unfortunate story between an owner and contractor on any late construction project. Now the fun begins regarding the allocation of the delay!
Through previous articles, I discussed that in this scenario the burden really falls on the contractor to establish that the liquidated damages were improperly assessed against it and, thus, it is entitled to additional time and/or extended general conditions as a result of excusable delays. Naturally, this requires the contractor to develop a critical path analysis (time impact analysis) allocating the impacts / delays (and the reasons for the impacts/ delays) to the project completion date. The reason the burden really falls on the contractor is because the owner’s burden is relatively easy – the project was not complete on time pursuant to the contract and any approved changed orders.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
Texas Supreme Court Declines to Waive Sovereign Immunity in Premises Defect Case
April 10, 2023 —
Starr M. Forster - Lewis BrisboisHouston, Texas (March 30, 2023) – The Supreme Court of Texas recently upheld a Thirteenth Court of Appeals’ judgment finding that the plaintiffs in a premises defect case brought against the Texas Department of Transportation (TxDOT) had failed to raise a fact issue regarding the creation of a dangerous condition and, consequently, failed to establish waiver of the defendant’s sovereign immunity.
Daniel K. Christ and Nicole D. Salinas v. Tex. DOT, et al., No. 21-0728, 66 Tex. Sup. Ct. J. 306, 2023 Tex. LEXIS 128, at *1 (Feb 10, 2023).
Background
Plaintiffs Daniel Christ and his wife, Nicole Salinas (the Christs), were riding their motorcycle through a construction zone when they collided with a vehicle that crossed into their lane. TxDOT’s traffic control plan for the related construction project called for the placement of concrete barriers between opposing travel lanes; however, once construction on the project began, TxDOT’s contractor determined there was not enough space for the concrete barriers and revised the traffic control plan to substitute yellow stripes and buttons for the concrete barriers. TxDOT never approved the revised traffic control plan in writing; however, TxDOT’s contractor contended TxDOT orally approved of the change. The Christs sued the driver of the other vehicle, TxDOT, and TxDOT’s contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Starr M. Forster, Lewis BrisboisMs. Forster may be contacted at
Starr.Forster@lewisbrisbois.com
Design-Assist, an Ambiguous Term Causing Conflict in the Construction Industry[1]
December 02, 2019 —
John P. Ahlers - Ahlers Cressman & Sleight PLLC“Design-Assist” is one of the recent cost-saving trends being touted for construction projects and, in particular, construction projects utilizing alternative procurement methods. If an internet search for the term, “design-assist” is made, the result will be numerous construction industry articles and white papers lauding “design-assist” as a recent cost-saving trend in construction procurement. From a legal perspective, however, the term “design-assist” is notably absent from court opinions and most state licensing laws. With the exception of the ConsensusDocs, few standard form contracts even include the term “design-assist” in their text.
The ConsensusDocs agreement provides examples of the Constructor’s obligations to perform “assisting activities” (the term “design-assist” is not used) and states that, notwithstanding the performance of such “assisting activities” by the Constructor, the responsibility of the design remains with the Designer unless otherwise stated in the Contract:
- Article 4.5 DESIGN PROFESSIONAL’S RESPONSIBIITIES The Designer shall furnish or provide all design and engineering services necessary to design the Project in accordance with the Owner’s objectives … the Designer shall draw upon the assistance of Constructor and others in developing the design, but the Designer shall retain overall responsibility for all design decisions….
- Article 4.6 CONSTRUCTOR’S RESPONSIBILITIES [T]he Constructor shall assist the Designer in the development of the Project Plan and Project Design but shall not provide professional services which constitute the practice of architecture or engineering unless the Constructor needs to provide such services in order to carry out its responsibilities … or unless specifically called for by the Contract Documents.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
Design Professional Liens: A Blueprint
March 12, 2015 —
Garret Murai – California Construction Law BlogIf you work in the construction industry in California you’re likely familiar with
mechanics liens.
But there’s one other type of lien available on construction projects in California: The design professional lien.
So, here’s a blueprint of what you need to know.
What is a design professional lien?
A design professional lien, like a mechanics lien, creates a security interest in real property for services rendered by a design professional prior to commencement of construction. If the design professional is not paid, the design professional can file a lawsuit to foreclose on the design professional lien to have the property sold and the proceeds from the sale used to satisfy the amount of the design professional lien.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
July Sees Big Drop in Home Sales
August 27, 2013 —
CDJ STAFFThe Commerce Department reported a 13.9 percent drop in sale of new homes for July. Over the course of the last 12 months, home sales had risen 7 percent. According to economists, an annual rate of about 700,000 homes would be a sign of a healthy economy. The July sales fell well short of that, at an annual rate of 394,000. New home starts were also down.
Experts attribute the decline in sales and building to increases in mortgage rates, even though the rates remain historically low. Despite the slump in home sales in July, builder confidence rose to a high in August.
Read the court decisionRead the full story...Reprinted courtesy of
Material Prices Climb…And Climb…Are You Considering A Material Escalation Provision?
May 31, 2021 —
David Adelstein - Florida Construction Legal UpdatesAs you may know, material prices have been climbing. And they continue to climb based on the volatility of the material market. On top of that, there are lead times in getting material due to supply chain and other related concerns. The question is, how are you addressing these risks? These are risks that need to be addressed in your contract.
As it relates to climbing material prices, one consideration is a material escalation provision. The objective of this provision is to address the volatility of the material market in economic climates, such as today’s climate, where the price of material continues to climb. Locking down a material price today will be different than locking down the same price months from today. This volatility and risk impacts pricing and budgets. Naturally, an owner and contractor would like to be in a position to lock down supplier prices as soon as possible—both to secure pricing and to account for items with long lead times or that recent data forecasts a long lead time due to supply chain concerns. However, this is not always possible or practical and can depend on numerous issues such as when the owner contracts with the contractor, when the owner issues the notice to proceed (and permits are issued), final construction documents and revisions to the construction documents, the type of material, whether there is staging or storage available for the materials, and the current status including climitazation of the project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Homebuyers Get Break as Loan Rates Defy Fed Tapering: Mortgages
February 14, 2014 —
Kathleen M. Howley – BloombergAshley Underwood is taking advantage of the unexpected drop in mortgage rates by rushing to buy her first home before they go up again.
“I’m ready to cancel plans at a moment’s notice to go look at a house,” said Underwood, 27, who lives in Indianapolis, Indiana. “I didn’t expect to see rates falling again, and I want to lock in something before I lose out.”
The drop in the last month proved forecasters wrong, said Douglas Duncan, chief economist of Fannie Mae in Washington. After the Federal Reserve announced in December that it would begin tapering purchases of mortgage-backed securities, all the major housing forecasters said rates would jump this quarter. Economists didn’t foresee that investors would react to the Fed’s retreat by moving money from emerging markets into U.S. Treasuries, driving down home-loan rates.
Read the court decisionRead the full story...Reprinted courtesy of
Kathleen M. Howley, BloombergMs. Howley may be contacted at
kmhowley@bloomberg.net
Indemnity: What You Don’t Know Can Hurt You!
September 19, 2022 —
Caitlin Kicklighter & Bill Shaughnessy - ConsensusDocsRisk allocation between the parties is a critical component of any construction contract. Indemnity obligations can be some of the important risk-shifting provisions of any design or construction contract. Indemnity provisions typically require one party, the Indemnitor, to agree to “hold harmless,” and/or reimburse another party, the indemnitee, from claims and liability arising out of the party’s work. Considering the financial consequences that an indemnity provision can have on a construction project, it is critical that all parties to a construction contract know the legal implications of the contract indemnity provisions and understand any limitations in enforcing the indemnity provisions depending on the controlling jurisdiction. While most indemnity clauses and obligations are enforceable, many states have enacted anti-indemnity statutes prohibiting or restricting specific indemnification provisions. These anti-indemnity statutes afford protection to contractors and subcontractors not generally in a position to protect themselves from overly extensive indemnity obligations.
This article highlights several examples of indemnity provisions typically seen in construction contracts, the measures are taken by a growing number of states to protect parties with less bargaining power in the form of anti-indemnity statutes, and offers practical considerations when negotiating or drafting indemnity provisions.
[1]
Reprinted courtesy of
Caitlin Kicklighter, Emory Law Student (2024 Graduate), (ConsensusDocs) and
Bill Shaughnessy, Jones Walker LLP (ConsensusDocs)
Mr. Shaughnessy may be contacted at bshaughnessy@joneswalker.com
Read the court decisionRead the full story...Reprinted courtesy of