It’s Time to Start Planning for Implementation of OSHA’s Silica Rule
May 03, 2017 —
Nathan Owens & Louis “Dutch” Schotemeyer – Newmeyer & Dillion LLPGetting a notification from OSHA that your company is being investigated for a health or safety violation is an unwanted disruption to your business that could lead to a hefty monetary fine. Worse yet, if your company is found to have committed multiple violations, OSHA may categorize your company as a severe violator, which makes you subject to follow-up inspections. In the last 6 years, OSHA has added 520 companies to the Severe Violator Enforcement Program - sixty percent of which are in the construction industry.
New OSHA regulations impacting the construction industry may result in more companies facing investigations and fines, or worse yet, laying off workers and unable to compete for new work. In 2013, OSHA proposed a new mandate to reduce silicosis in workers. The mandate, which was revised multiple times before being made final in March 2016, requires that employers ensure their workers are exposed to no more than 50 micrograms of crystalline silica in an eight hour period (down from the current standard of 250 micrograms). Under the new mandate, employers are also held to heightened reporting requirements, protective measures and medical testing for employees with extended exposure to silica.
In the construction industry alone, OSHA believes the new mandate will prevent 1,080 cases of silicosis and more than 560 deaths. Builder and trade groups believe the new mandate will result in the loss of tens of thousands of jobs and cost the building industry billions of dollars. The National Association of Home Builders estimates that the Silica Rule will cost homebuilders $1,500 per start. While the two sides mount their arguments and seek support, how to implement the rule and its long term feasibility are still contested questions.
Recognizing the challenges employers will have with the heightened requirements of the Silica Rule, OSHA just announced that enforcement is being delayed 90 days to develop additional guidance for implementation of the rule in the construction industry. The new start date for enforcement of the Silica Rule is September 23, 2017.*
Many in the industry are hoping the Trump administration repeals the Silica Rule like they have “blacklisting” and the Volks rule. However, until that happens, OSHA expects your company to implement processes to ensure compliance by the new start date.
*The Silica Rule was adopted by Cal/OSHA in August 2016 even though Cal/OSHA’s own silica standard had been in place since 2008. Cal/OSHA adopted the federal standard with the June 23, 2017 effective date; however; in an effort to synchronize with OSHA, Cal/OSHA recently announced that the effective date in California will also be September 23, 2017.
Nathan Owens is the Las Vegas Managing Partner of Newmeyer & Dillion, and represents businesses and individuals operating in a wide array of economic sectors including real estate, construction, insurance and health care in all stages of litigation in state and federal court. For questions related to the OSHA and the Silica Rule, you can reach him at Nathan.Owens@ndlf.com.
Louis “Dutch” Schotemeyer is an associate in Newmeyer & Dillion’s Newport Beach office. Dutch’s practice concentrates on the areas of business litigation, labor and employment law, and construction litigation. For questions related to OSHA or the Silica Rule, you can reach him at Dutch.Schotemeyer@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Dreyer v. Am. Natl. Prop. & Cas. Co. Or: Do Not Enter into Nunn-Agreements for Injuries that Occurred After Expiration of the Subject Insurance Policy
January 20, 2020 —
Jean Meyer - Colorado Construction LitigationWhile Nunn-Agreements[1] may be appealing for both plaintiffs and defendants where an insurer unreasonably fails to defend a lawsuit, a recent opinion from The Honorable Marcia Krieger in the United States District Court of Colorado[2] (“Opinion”) demonstrates the importance of first confirming that there exists a viable insurance claim before proceeding with such a Nunn- Agreement.
The facts giving rise to the Opinion were as follows. In March 2015, a Homeowner couple (the “Homeowners”) suffered damages to their home resulting from a brushfire. Fortunately, the Homeowners were insured, they submitted their claim to their homeowners’ insurance carrier which was in effect at the time of the brushfire (the “Insurance Carrier”), and the Insurance Carrier paid the claim. Ostensibly as part of the Homeowners’ remediation efforts to their home they removed a large bush which left a hole in the ground. After paying the claim, in August 2015 the Insurance Carrier cancelled or elected not to renew the Homeowners’ policy. In October 2015, a repairman working on the Home (the “Repairman”) was injured after his ladder fell over allegedly because of the hole in the ground caused by the bush that had been removed.
As a result of injuries caused by the fall from the ladder, the Repairman brought suit against the Homeowners. In response to the Repairman’s claim, the Homeowners again tendered to their Insurance Carrier. This time, however, the Insurance Carrier denied coverage on the basis that the Repairman’s injuries occurred after the expiration of the relevant policy. Without insurance coverage, the Homeowner’s entered into a Nunn-Agreement with the Repairman, conceding liability, and assigning any claims they might have had against the Insurance Carrier in lieu of execution of any judgment against the Homeowners.
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
Phoenix Flood Victims Can’t Catch a Break as Storm Nears
September 17, 2014 —
Brian K. Sullivan – BloombergA week ago, Hurricane Norbert pumped tropical moisture across the U.S. Southwest, touching off record rainfall in Phoenix and Tucson that killed at least two people, flooded hundreds of homes and shut highways throughout the region.
This week, Hurricane Odile moved onto the Baja California peninsula after becoming the strongest system since 1967 to hit that part of Mexico, the U.S. National Hurricane Center said.
While it isn’t time to get the rowboat out again for the morning commute, the earth in the desert Southwest doesn’t absorb water very well, the way a Florida swamp or Louisiana bayou might. A lot of rain can be far more unpredictable.
Read the court decisionRead the full story...Reprinted courtesy of
Brian K. Sullivan, BloombergMr. Sullivan may be contacted at
bsullivan10@bloomberg.net
Bad Faith Claim for Inadequate Investigation Does Not Survive Summary Judgment
May 20, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe insured's claim for bad faith investigation regarding their hail damage claim did not survive the insurer's motion for summary judgment. Amarillo Hospitality Tenant, LLC v. Mass. Bay Ins. Co., 2015 U.S. Dist. LEXIS 56228 (N. D. Tex. April 29, 2015).
A hailstorm caused damage to the Courtyard Marriot. The day after the storm, the insured inspected the roof of the hotel and observed damage to a sign and some aluminum vent tubes. No damage to the roof itself was observed. Subsequently, leaks were found on the tenth floor of the hotel. A public adjuster concluded that the roof had sustained damage during the hailstorm.
The insured filed a claim with Massachusetts Bay Insurance Company. The insurer paid for the cost of repairing the damaged sign. To determine whether the damage to the roof was caused by the hailstorm, the insurer hired Donna Engineering, who conducted two inspections of the roof. Both inspections concluded that the hailstorm did not cause damage to the roof. Consequently, the claim was denied.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Florida Court Gives Parties Assigned a Subrogation Claim a Math Lesson
August 04, 2021 —
Lian Skaf - The Subrogation StrategistAlthough the focus of most subrogation cases is usually on proving liability, determining the appropriate measure of damages is just as important. Sometimes turning on a nuanced argument for recoverability, an adverse holding can significantly boost or reduce the total damages in a case. The Court of Appeal of Florida, Fourth District (Court) recently decided such an issue in a case involving subrogation, holding that the defendants owed much more than they originally anticipated.
In Five Solas v. Ram Realty Servs., No. 4D19-2211 2021, 2021 Fla. App. LEXIS 7546, the Court reviewed the appropriate setoff in damages that the defendants were entitled to when measuring the recoverable damages. The Court reversed the lower court’s holding, which held that the defendants were entitled to a setoff that limited the jury’s award to $104,481.75. Instead the Court held that the defendants were only entitled to a setoff equal to the excess recovery over replacement cost.
The case involves, among other things, property damage sustained by building owner Five Solas (Owner) and its lessee William Price, P.A. from a collapsed wall originating from the property of the defendants, Ram Realty Services, LLC and Sodix Fern, LLC d/b/a Alexander Lofts (collectively referred to as Defendants). Owner’s carrier, Foremost Insurance Company (Foremost), paid out its policy limit of $430,518.25 to Owner for damage to the building. Owner then pursued its claim against the tortfeasors for the remaining damages not paid by its carrier.[1] Foremost also pursued a subrogation claim, but settled its subrogation claim with Defendants, assigning its subrogation rights to Defendants.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Muir named Brown and Caldwell Eastern leader
January 09, 2023 —
Brown and CaldwellHARTFORD, Conn., Jan. 04, 2023 — Leading environmental engineering and construction services firm Brown and Caldwell today announces Senior Vice President Eric Muir has been promoted to leader of its growing Eastern business.
The largest of the company's regions with over 40 offices east of the Mississippi River, the Eastern business consists of clients in the water, wastewater, stormwater, environmental services, and water resources sectors.
Muir has a 20-year background in delivering highly technical civil and environmental engineering projects. He has held leadership and technical roles on some of the most complex projects encompassing water and wastewater treatment, distribution and collection, pumping, and conveyance systems. His experience includes master planning, detailed design, permitting, and construction services.
Since joining Brown and Caldwell in 2018, Muir's business development expertise and client-centric focus have played a key role in setting the company's regional strategic direction to achieve strong financial results.
"Eric is a highly strategic and inclusive leader, passionate about mentoring employees to reach their full potential," said Brown and Caldwell Chief Operating Officer Euan Finlay. "His deep knowledge of clients' environmental obstacles will enhance the positive impacts our teams have on the communities we serve."
Based in Connecticut, Muir will manage overall operations and lead the implementation of the firm's strategy in the East. He will continue the region's growth and lead efforts to make Brown and Caldwell the company of choice for clients, employees, and partners. He will work alongside regional leadership to align the firm's talent pool with clients to provide innovative, cost-effective solutions to challenges related to water quality, biosolids management, and aging infrastructure.
About Brown and Caldwell
Headquartered in Walnut Creek, California, Brown and Caldwell is a full-service environmental engineering and construction services firm with 52 offices and 1,800 professionals across North America and the Pacific. For 75 years, our creative solutions have helped municipalities, private industry, and government agencies successfully overcome their most challenging water and environmental obstacles. As an employee-owned company, Brown and Caldwell is passionate about exceeding our clients' expectations and making a difference for our employees, our communities, and our environment. For more information, visit www.brownandcaldwell.com
Read the court decisionRead the full story...Reprinted courtesy of
Airbnb Declares End to Party!
January 27, 2020 —
Patrick J. Paul - Snell & Wilmer Real Estate Litigation BlogAs municipalities around the country evaluate changes to their respective codes in an effort to exert greater control over bad actors in the vacation rental market, Airbnb announced on November 2nd that it is banning party houses. The move comes in response to the shooting deaths of five people at a Halloween party hosted at an Airbnb rental house in Orinda, CA. CEO Brian Chesky announced on Twitter that starting November 2, Airbnb would ban “party houses” and redouble the company’s efforts to “combat unauthorized parties and get rid of abusive host and guest conduct.” twitter.com/bchesky
The four-bedroom rental reportedly had been rented on Airbnb by a woman who advised the owner her family members had asthma and needed to escape smoke from a wildfire burning in Sonoma County about 60 miles north of Orinda earlier in the week. Nevertheless, the homeowner was suspicious of a one-night rental on Halloween and reminded the renter that no parties were allowed. Having received complaints from neighbors and witnessing some party activity via his camera doorbell, the homeowner called police who were en route to the home, but arrived after the shooting. The Halloween party apparently was advertised on social media as an “Airbnb Mansion Party,” with an admission fee of $10 per person.
Independently owned vacation rentals are currently growing at a faster rate than hotels or motels, and in some instances are owned by out-of-state investors seeking not only a real estate return on investment, but also a return on investment associated with revenue streams generated by “pay to play” parties promoted on social media.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick J. Paul, Snell & WilmerMr. Paul may be contacted at
ppaul@swlaw.com
Revisiting Termination For Convenience Clauses In Uncertain And Ever-Changing Economic Times
February 27, 2023 —
Adam M. Tuckman & Brittney M. Wiesner - ConsensusDocsIn these times of persistent inflationary forces and efforts to tame the consequences through rising interest rates, economic uncertainty abounds in the United States and around the world. As an approximately $1 trillion contributor to the economy in the United States (4.2% of GDP in 2021) alone according to the Associated General Contractors of America, the health and the growth of the construction industry is certainly susceptible to these rapidly changing macroeconomic conditions.
Presently, an unanswered question is how project developers will react to unpredictable fluctuations in project costs and interest rates. Although it seems unlikely to be a prevalent response, it is possible that substantial increases in borrowing, labor, or material costs would cause owners to pull the plug on projects that are in the advanced stages of construction. For projects in the nascent stages of development or construction, however, the calculous for owners becomes more tenuous. Both public and private owners may find it more prudent to indefinitely suspend or cancel pending or ongoing projects due to any, or a combination of, forecasted increases in project costs, shrinking funding, higher borrowing costs, or macro-economic uncertainty. Facing this quandary, how would an owner already under contract with a constructor and design team suspend or cancel its project? One potential approach is to invoke a termination for convenience clause found in the parties’ contract.
Reprinted courtesy of
Adam M. Tuckman, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs) and Brittney M. Wiesner, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)
Mr. Tuckman may be contacted at atuckman@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of