“Since You Asked. . .”
October 15, 2024 —
Daniel Lund III - Lexology… you must now pay.
So said a California appellate court, affirming the trial court’s decision against a subcontractor suing for unpaid subcontract sums. Instead of being awarded those unpaid amounts, the subcontractor lost the case and was tagged with a $1.55 million attorney’s fees award and $270,000 costs award in favor of the defendants.
What went wrong?
California law requires a licensed contractor to maintain at all times proper workers’ compensation insurance coverage. The failure to maintain the coverage and have the certificate of coverage on file with the California Contractors State License Board results in “automatic and immediate suspension” of the contractor license. Retroactive reinstatement of the license may occur only if the contractor provides proof of the insurance within 90 days of the effective date of the insurance certificate – unless the contractor can show that failure to have the certificate on file was “due to circumstances beyond the control of the licensee.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Contractual Waiver of Consequential Damages
January 02, 2019 —
David Adelstein - Florida Construction Legal UpdatesContractual waivers of consequential damages are important, whether they are mutual or one-sided. I believe in specificity in that the types of consequential damages that are waived should be detailed in the waiver of consequential damages provision. Standard form construction agreements provide a good template of the types of consequential damages that the parties are agreeing to waive.
But, what if there is no specificity in the waiver of consequential damages provision? What if the provision just states that the parties mutually agree to waive consequential damages or that one party waives consequential-type damages against the other party? Let me tell you what would happen. The plaintiff will argue that the damages it seeks are general damages and are NOT waived by the waiver of consequential damages provision. The defendant, on the other hand, will argue that the damages are consequential in nature and, therefore, contractually waived. FOR THIS REASON, PARTIES NEED TO APPRECIATE WHAT DAMAGES ARE BEING WAIVED OR LIMITED, AND POTENTIALLY THOSE DAMAGES NOT BEING WAIVED OR LIMITED, WHEN AGREEING TO A WAIVER OF CONSEQUENTIAL DAMAGES PROVISION!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Building Materials Price Increase Clause for Contractors and Subcontractors – Three Options
June 21, 2021 —
William L. Porter - Porter Law GroupWith the arrival of inflation come concerns regarding increases in the price of building materials within the construction industry. Contractors, subcontractors and others who contract to perform construction work can suffer significant losses when the prices they must pay for materials rises significantly between the time they sign the contract and actually purchase the materials. The general rule is that, unless there exists a contract clause allowing contractors or subcontractors to pass significant price increases for materials on to others, contractors and subcontractors are stuck with the price stated in the contract or subcontract. When prices rise, the contractor or subcontractor eats the difference. Rising prices can thus turn a profitable project into a catastrophic failure. How are contractors and subcontractors to protect themselves?
Once a contract is executed, there is usually little that can be done to change the document to address rising prices. Effort must therefore turn to future protection. The best technique for dealing with increasing future prices for building materials is by adding a price escalation clause to contracts and subcontracts. While this will not help for past contracts or subcontracts, it can certainly offer significant protection going forward.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
San Diego Developer Strikes Out on “Disguised Taking” Claim
October 26, 2017 —
Michael C. Parme – Haight Brown & Bonesteel LLPIn Dryden Oaks, LLC v. San Diego County Regional Airport Authority et al.(D068161, filed 9/26/17, publication order 10/19/17), the California Court of Appeal, Fourth Appellate District held that the County of San Diego (County) and the San Diego Regional Airport Authority (Authority) were entitled to summary judgment on a developer’s “disguised taking” theory of inverse condemnation.
In 2001, the developer purchased two large lots (designated Lot 24 and Lot 25) adjacent to the end of a runway at the Palomar Airport in Carlsbad. Plaintiff obtained the necessary permits from the City of Carlsbad and successfully completed construction of an industrial building on Lot 24 in 2005. However, the plaintiff never began development of Lot 25 and the building permit for the property expired in 2012. The developer was then unable to renew the building permit because the Authority had adopted the Airport Land Use Compatibility Plan (ALUCP) in the interim period, which reclassified the Lots as part of a Runway Protection Zone (RPZ). The developer received a letter explaining that “despite the earlier approval the proposed development was no longer feasible because the ALUCP was more restrictive than the prior compatibility plan and the application's proposed use of ‘research and development’ was not permissible.”
Read the court decisionRead the full story...Reprinted courtesy of
Michael C. Parme, Haight Brown & Bonesteel LLPMr. Parme may be contacted at
mparme@hbblaw.com
You Cannot Always Contract Your Way Out of a Problem (The Case for Dispute Resolution in Mega and Large Complex Construction Projects)
September 16, 2024 —
Lisa D. Love - The Dispute ResolverMost experienced commercial transaction and construction attorneys strive to negotiate a concisely written and well-drafted contract that addresses all scenarios and issues that creative and highly contemplative professionals can conjure. Although contracts are extremely important in construction projects, “you can’t generally contract your way out of a problem,” states Michael Loulakis, a founder of Capital Project Strategies, LLC and a nationally recognized expert on project delivery systems in complex public sector design-build projects and public-private partnership programs. Loulakis adds, “the contract certainly matters. But particularly when the losses are big, litigators prosecuting the contractors often find effective ways to argue that facts and circumstances trump the contract.” However, “the difference between the best construction projects and the worst construction projects is not the written words of the contracts but how the parties have committed to engage collaboratively and with trust to complete the project,” notes Robynn Thaxton, an attorney and consultant with Thaxton Parkinson PLLC and Progressive Design-Build Consulting, LLC and one of the leading experts in construction law and alternative procurement on a national basis.[i]
In large, complex construction projects, the need for parties to collaboratively resolve disputes is highlighted by the judicial acceptance of the “Doctrine of the Contextual Contract”[ii] to interpret construction contracts. “As construction’s increasing technological and managerial complexity came to be recognized, some common law courts began turning away from strict interpretation of language within the four corners of a contract and moving toward recognizing in the enforcement of contracts the construction industry’s own experience, customs, practices and implied conditions and duties and the factual context underlying the contract. Courts [began the journey] along the road from ‘text’ to ‘context.’”[iii] Thus, the precise wording of the contract has become less important and industry practices and other conditions provide insight for resolving disputes. Consequently, despite the specific language of any construction contract and the clear allocation of responsibilities and risks, early dispute evaluation and resolution are critical to a successful project.
Read the court decisionRead the full story...Reprinted courtesy of
Lisa D. Love, JAMS
Newmeyer & Dillion Selected to 2017 OCBJ’s Best Places to Work List
July 26, 2017 —
Newmeyer & Dillion LLPProminent business and real estate law firm Newmeyer & Dillion LLP is proud to be one of the selected companies in the
Best Places to Work in Orange County – 2017 Survey in the category of medium sized companies. This marks the sixth consecutive year Newmeyer & Dillion LLP has made the list, affirming that its profound commitment to professionalism and client service is shared among its workforce. The firm was honored in the July 24 issue of the Orange County Business Journal.
Jeff Dennis, Newmeyer & Dillion's Managing Partner, commends the effort and commitment of each employee in achieving this result. "We strive to make Newmeyer & Dillion a great place to be, but we only set the goal. It is our employees and their ongoing loyalty and commitment to our mission that makes it happen. Together, we create a culture here that cannot be matched anywhere else."
Created in 2009, the awards program evaluates entries based on workplace policies, practices, demographics, and also collects employee surveys to measure overall satisfaction and experience. The Best Companies Group worked alongside the Orange County Business Journal in collecting and analyzing the data and is a partner in the project.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Motion for Judgment on the Pleadings for Construction Defect Claim Rejected
January 22, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe magistrate judge recommended that the insurer's motion for judgment on the pleadings be denied in a case involving coverage for the insured subcontractor's alleged faulty workmanship. Evanston Ins. Co. v. Sonny Glasbrenner, Inc., 2023 U.S. Dist. LEXIS 190019 (M.D. Fla. Oct. 20, 2023).
Cone & Graham (C&G), the general contractor, subcontracted with Sonny Glasbrenner, Inc. (SGI) to work on the project. The project involved the rehabilitation of a bridge due to deterioration of the existing concrete bridge deck by adding additional cross bracing to further stiffen the steel girders and using special lightweight concrete. C&G contracted SGH to demolish the existing concrete bridge deck. SGI completed the work.
Thereafter, C&G made a demand to SGI for alleged damaged caused by SGI's work. C&G alleged that SGI was negligent in performing the demolition work, causing substantial damage to the existing bridge girders. C&G sued SGI.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Avoid L&I Violations by Following Appropriate Safety Procedures
November 07, 2022 —
Reeya Patel - Ahlers Cressman & Sleight PLLCDepartment of Labor and Industries of the State of Washington v. Roof Doctor, Inc. d/b/a Roof Doctors, Inc. of Tacoma (Unpublished opinion)
Roof Doctor, a company engaging maintenance of roofs, was hired to complete work for a commercial building in Tacoma in February 2018. During the job, Roof Doctor was cited for two violations by a Washington State Department of Labor and Industries’ (L&I) compliance inspector and seven additional asbestos violations. Each citation was rated with a probability of 1 – 3 to determine the likelihood of injury, illness, or disease. The ratings allowed issuance of an appropriate monetary penalty.
The disputes among the parties on appeal were as follows:
First, L&I and Roof Doctor disputed the asbestos probability ratings and calculated penalties. L&I produced as evidence, the fact that nine employees were physically hanging roofing material with asbestos, but none had training or knew that the material contained asbestos. L&I did agree that that most of the employees were experienced in handling roofing material and knew of the dangers that asbestos presented. Roof Doctor explained that because the employees were working outdoors, the danger of asbestos exposure was mitigated due to a low probability that a high concentration of asbestos could be inhaled by the employees when outdoors.
Read the court decisionRead the full story...Reprinted courtesy of