Craig Martin – Construction Contractor AdvisorNew Hampshire is the first court of 2015 to weigh in on construction defect coverage issues. The case, Cogswell Farm Condominium Association v. Tower Group, involved a typical situation. Lemery Building Company was hired to build 24 residential condominium units. After construction, the condominium association sued the builder asserting that the weather barrier, including the water/ice shield, flashing, siding, and vapor barrier, was defectively constructed and resulted in damage to the units due to water leaks. The condominium association also sued Lemery’s insurer for a determination as to whether the builder’s Commercial General Liability (CGL) insurer had to provide coverage for the claim.
The trial court ruled against the condominium association, finding that the “your work” exclusion applied. The exclusion in the builder’s CGL policy provided that there was no coverage for property damage to “[t]hat particular part of any property that must be restored, repaired or replaced because ‘your work’ was incorrectly performed on it.”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Water Intrusion Judged Not Related to Construction
October 09, 2013 —
CDJ STAFFA Wisconsin couple has lost their lawsuit against the city of Stoughton. Jerry and Maxine King claimed that construction of the Stoughton Fire Station lead to flooding of their basement. The city conceded that in 2008, the contractor failed to “have in place some of the measures that could have prevented the water from running onto the King property.” The contractor’s insurance company compensated the Kings.
Subsequently, the Kings complained of further water damage. But Matt Dregne, Stoughton’s attorney, said that the Kings “didn’t repair the basement.” The judge in the case dismissed the suit with prejudice, disallowing any further suits from the Kings on these circumstances.
Read the court decisionRead the full story...Reprinted courtesy of
Ongoing Operations Exclusion Bars Coverage
December 09, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer denied the insured contractor's claim seeking a defense for faulty workmanship based upon the ongoing operations exclusion. PJR Constr. of N.J. v. Valley Forge Ins. Co., 2019 U.S. Dist. LEXIS 127973 (D. N. J. July 31, 2019).
PJR Construction was the general contractor to build a swim club and pavilion building for Cambridge Real Property, LLC. PJR began construction on May 29, 2012, and was to complete the construction by March 1, 2013. The project took much longer than anticipated. PJR was denied access to the site on November 13, 2014. Cambridge contended PJR tolerated shoddy workmanship and breached the terms of the contract documents. Cambridge estimated that the project was between 55% and 74.3% complete.
PJR and Cambridge went to arbitration. PJR sought a defense from the insurers. Coverage was denied based upon exclusions j (5) and j (6). Exclusion j (5), which the court referred to as the "Ongoing Operations Exclusion," provided the policy did not apply to,
Property Damage to . . . [t]hat particular part of real property on which you or any contractors or subcontractors working directly or indirectly on your behalf are performing operations, if the property damage arises out of those operations.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
NAHB Reports on U.S. Jobs Created from Home Building
May 05, 2014 —
Beverley BevenFlorez-CDJ STAFFThe National Association of Home Builders’ Eye on Housing reported that for every “average single-family home” built in the U.S., almost three full-time jobs are created.
“A substantial share of this is employment for construction workers,” according to the NAHB article. “But also included is employment in firms that manufacture building products, transport and sell products, and provide professional services to home builders and buyers (e.g., architects and real estate agents).”
Read the court decisionRead the full story...Reprinted courtesy of
Separation of Insureds Provision in CGL Policies
August 31, 2020 —
David Adelstein - Florida Construction Legal UpdatesCGL policies contain a “Separation of Insureds” provision. This provision oftentimes states:
Except with respect to the Limits of Insurance, and any rights or duties specifically assigned this Coverage Part to the first Named Insured, this insurance applies:
- As if each named insured were the only Named Insured; and
- Separately to each insured against whom claim is made or “suit” is brought.
This provision is designed to “create separate insurable interests in each individual insured under a policy, such that the conduct of one insured will not necessarily exclude coverage for all other insured.” Evanson Ins. Co. v. Design Build Interamerican, Inc., 569 Fed.Appx. 739 (11th Cir. 2014). This provision also allows one insured under the policy (e.g., additional insured) to sue another (e.g., named insured) without violating potential coverage because there are separate insurable interests. This is a valuable provision in CGL policies.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Default Should Never Be An Option
June 19, 2023 —
Christopher G. Hill - Construction Law MusingsEvery time I think that the construction industry has learned that failure to respond to a lawsuit is never the correct response, another case of default judgment comes out. I’ve discussed on multiple occasions that failure to respond can only lead to disaster. Aside from being barred from making any substantive response to the allegations against you, there are other consequences including the inability to seek a reasonable settlement because the other side has no reason to negotiate.
One of the more disastrous results recently came about in the Norfolk Division of the Eastern District of Virginia District Court. The case of L & W Supply Corp v. Driven Construction et. al. involved a supplier that sought to enforce its credit agreement against both the corporate entity of the contractor, Driven, and the guarantor, a principal of the company. Needless to say, there was no response to the lawsuit and the Plaintiff filed for default judgment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
When is Mediation Appropriate for Your Construction Case?
May 07, 2015 —
Christopher G. Hill – Construction Law MusingsHere at Construction Law Musings, I have often discussed mediation as a good alternative to the expense and headaches of litigation. What I have discussed less often are the circumstances in which it is most appropriate to consider or even push for mediation.
The obvious and clearest time that mediation must be used is where the contract requires it. Many construction contracts, including those from the AIA (when the parties check the appropriate box) require mediation as a prerequisite to arbitration or litigation. As is almost always the case in Virginia, this clause will be enforced. In short, if your construction contract has such a clause, and despite my reservations about “mandatory mediation,” you need to at least go through the process before moving forward with your construction claim.
The more interesting case is where no such clause exists and the parties reach an impasse, sometimes prior to litigation and often after the filing of a construction complaint or demand for arbitration. What questions should you as a construction attorney be asking both to and about your construction clients before attempting mediation?
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Green Energy Can Complicate Real Estate Foreclosures
November 30, 2016 —
Bob L. Olson – Snell & Wilmer Real Estate Litigation BlogA quick drive through almost any newer residential community in the Southwest will show that a lot of residents are embracing “Green Energy” or renewable energy by placing solar panels on their properties. While most people would agree that increasing the use of alternative energy is socially responsible, there are a number of real estate investors that may view it as an opportunity to make additional profits by purchasing distressed properties with solar panels and then reselling those properties for more than they would be worth without solar panels. The theory is relatively straight forward as many believe that foreclosure of a deed of trust that was recorded before the solar panels were installed would extinguish any liens in favor of the vendor that sold or financed the sale of the solar panels. After all, it is generally held that “a valid foreclosure of a mortgage terminates all interest in the foreclosed real estate that are junior to the mortgage being foreclosed.” See SFR Investments Pool 1, LLC v. U.S. Bank, N.A., 130 Nev. Adv. Op. 75, 334 P.3d 408, 412 (2014) (quoting Restatement (Third) of Property, Mortgages §7.1 (1997)).
NOT SO FAST! While the general rule is that foreclosure of a senior lien terminates junior liens, most purveyors of solar panels do not encumber the property with mortgages or deeds of trust to secure payment of amounts they are owed. Rather, they typically either lease the solar panels to the property owner or secure repayment of the purchase price of the solar panels with a fixture filing under the Uniform Commercial Code (the “UCC”).