Contractual Setoff and Application When Performance Bond Buys Out of its Exposure
July 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesThe theory of “setoff” is an important theory in construction disputes. Florida’s Fourth District Court of Appeal recently provided worthy discussion on contractual setoffs:
Setoffs in contract claims are governed by [Florida Statute] section 46.015(2), which provides that if a plaintiff has released “any person in partial satisfaction of the damages sued for, the court shall [setoff] this amount from the amount of any judgment to which the plaintiff would be otherwise entitled at the time of rendering judgment.” The setoff statute intends to prohibit plaintiffs from getting double recoveries.
A setoff requires that settling and non-settling parties be jointly and severally liable. The settled damages must also be the same damages for which the setoff is sought; stated differently, a setoff is not proper where the trial damages to be setoff are separate and distinct from the settled damages.
Close Construction, LLC v. City of Riviera Beach Utility Special District, 49 Fla.L.Weekly D1184d (Fla. 4th DCA 2024) (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Indictments Issued in Las Vegas HOA Scam
January 22, 2013 —
CDJ STAFFA federal grand jury has indicted eleven individuals involved in the Las Vegas homeowners association scam. Leon Benzer, Keith Gregory, and Barry Levinson were all indicted for their roles in the scam, where conspirators took over homeowners associations in order to profit from construction defect suits. According to the Las Vegas Review Journal, all eleven were charged with conspiracy to commit mail and wire fraud. Mr. Levinson's license to practice law has been suspended due to an investigation that he misappropriated client funds. Mr. Benzer has been described as the "mastermind" of the scam.
Twenty-eight defendants have plead guilty, with all but one agreeing to cooperate with investigators. The report quotes William C. Woerner, the acting special agent in charge of the FBI in Las Vegas, as saying that "today's indictment demonstrates the continued commitment of the FBI and its law enforcement partners to identify and root out public corruption at all levels."
Read the court decisionRead the full story...Reprinted courtesy of
So a Lawsuit Is on the Horizon…
August 10, 2021 —
Sean Donoghue - Construction ExecutiveAs certain as death and taxes, documents will need to be exchanged in the event of a lawsuit. Here is what to expect and a few tips for reducing costs and protecting the case.
What Needs to Be Produced?
Discovery is broad, but proportional to the needs (i.e., usually the dollar value) of the case. Cost reports, bid back up and scheduling information are often at the heart of damages issues in construction disputes. Thus, while it will depend on the nature of the dispute, these items will generally need to be produced.
It is no secret that electronically stored information (ESI) can be a big part of discovery in litigation, particularly in a document intensive industry like construction. In addition to electronically stored project files, expect that the inboxes of employees who are close to the dispute will need to be searched. How many will depend on the size of the dispute and the number of players involved. Hard-drives and text messages of those employees may also be discoverable.
Reprinted courtesy of
Sean Donoghue, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Donoghue may be contacted at
sdonoghue@eckertseamans.com
Hong Kong Buyers Queue for New Homes After Prices Plunge
July 09, 2014 —
Michelle Yun – BloombergOn a Saturday morning in mid-June, thousands wait, crammed into Hong Kong’s Fortune Metropolis mall, across Victoria Harbor from the main business district, their eyes locked on large elevated screens. Cheers erupt when numbers flash, indicating the lucky ticket holders in the crowd.
They have paid HK$150,000 ($19,354) to enter a lottery that prioritizes buyers of apartments at City Point, a seven-tower development that billionaire Li Ka-shing’s Cheung Kong Holdings Ltd. (1) is building. More than 5,000 homebuyer-hopefuls are vying for 442 units, or about 11 for every home that went on sale the weekend of June 14.
Housing sales in Hong Kong are rising after government efforts to cool soaring prices led transactions to plunge last year to the lowest since at least 2002. A drop in mortgage rates and discounts from builders are luring back buyers of new homes after their price fell as much as 20 percent since October.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Yun, BloombergMs. Yun may be contacted at
myun11@bloomberg.net
Wendel Rosen Construction Attorneys Recognized by Super Lawyers
July 30, 2018 —
Garret Murai - California Construction Law BlogWendel Rosen Construction Practice Group Co-Chairs, Garret Murai and Quinlan Tom, have been selected for inclusion as 2018 Northern California Super Lawyers in the area of Construction Litigation. Murai and Tom are among 26 other attorneys at the firm who were selected as either 2018 Northern California Super Lawyers or Rising Stars by Thompson Reuters.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Fundamental Fairness Trumps Contract Language
September 24, 2014 —
Craig Martin – Construction Contractor AdvisorThe Texas Supreme Court recently ruled that a “no-damages-for-delay” clause would not be enforced where the delay was caused by the owner. The court’s ruling flies squarely in the face of the contract language that attempted to insulate the owner from any delay claims, even those it caused.
In the case of Zachary Construction v. Port of Houston underlying contract, proposed by the Port of Houston, was heavy handed, to say the least. The contract provided:
“[Contractor] shall receive no financial compensation for delay or hindrance to the Work. In no event shall the Port Authority be liable to [Contractor] … for any damages arising out of or associated with any delay or hindrance to the Work, regardless of the source of the delay or hindrance, including events of Force Majeure, AND EVEN IF SUCH DELAY OR HINDRANCE RESULTS FROM, ARISES OUT OF OR IS DUE IN WHOLE OR IN PART, TO THE NEGLIGENCE, BREACH OF CONTRACT OR OTHER FAULT OF THE PORT AUTHORITY. [Contractor’s] sole remedy in any such case shall be an extension of time.”
Wow, that’s some one-sided language. If the contract was enforced, the contractor could not get any damages for delay, even those damages caused by the active interference of the Port of Houston.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
New York Appellate Team Obtains Affirmance of Dismissal of Would-Be Labor Law Action Against Municipal Entities
August 12, 2024 —
Lewis Brisbois NewsroomNew York, N.Y. (July 11, 2024) - In Charlot v. City of New York, ___ A.D.3d ___, 2024 NY Slip Op 03161 (2d Dep’t 2024), New York Associate Dean Pillarella, a member of the Appellate Practice, recently obtained an affirmance of the lower court’s dismissal of the plaintiff’s action against the City of New York (“the City”) for failure to timely serve a notice of claim. New York Partner Meghan Cavalieri, a member of the Construction Practice, and her team authored and argued the initial motion to dismiss.
The plaintiff alleged to have sustained injuries as a result of a construction-site accident on December 8, 2020, on City-owned property in the course of the construction of a school by the New York City School Construction Authority. N.Y. General Municipal Law (“GML”) § 50-e(1)(a), requires service of a notice of claim within 90 days after the claim arises as a condition precedent to the commencement of a tort action. The plaintiff served no notice of claim until June 2021 and commenced an action in January 2022, alleging violations of N.Y. Labor Law §§ 240(1), 241(6), and 200. Given the plaintiff’s failure to comply with GML § 50-e(1)(a), Meghan and her team rejected the notices of claim as untimely. The plaintiff then moved for leave to deem the notices of claim timely served nunc pro tunc. In response, Meghan and her team opposed the motion and cross-moved to dismiss the action.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Supply Chain Delay Recommendations
August 07, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogThis Bulletin provides guidance to contractors, subcontractors, suppliers, and others to ensure compliance with contractual change order requirements in the event work on a construction project is impacted by supply chain delays.
Contract Protection Tips:
The construction industry is being impacted substantially by inability to obtain necessary construction products due to supply chain issues. Most construction contracts do not accommodate time extensions due to supply chain impacts. To address this gap in contract terms, we recommend including language such as: “lack of or failure of or other inability to obtain necessary transportation, fuel, power, materials, machinery, equipment or facilities, delays caused by other contractors, subcontractors or their subcontractors of any tier, or any materialmen or suppliers” as part of the defined force majeure event under the contract.
This provision can be included in the Change Order section of the contract as well by including a provision such as: “If the Work is delayed by the failure of or other inability to obtain necessary transportation, fuel, power, materials, machinery, equipment or facilities, delays caused by other contractors, subcontractors or their subcontractors of any tier, or any materialmen or suppliers, contractor shall be entitled to a change order for its costs and time associated with the delay.”
Read the court decisionRead the full story...Reprinted courtesy of
Denise Motta, Gordon Rees Scully Mansukhani, LLPMs. Motta may be contacted at
dmotta@grsm.com