More Clear, But Not Yet Crystal: Virginia Amends its Prompt Payment Law and Legislation Banning “Pay-If-Paid Clauses in Construction Contracts Effective July 1, 2023
November 16, 2023 —
Hanna Lee Blake - ConsensusDocsThe Virginia General Assembly has joined a minority of jurisdictions that ban pay-if-paid clauses in construction contracts on public and private projects. Senate Bill 550 went into effect applying to contracts executed after January 1, 2023, and most recently has been amended effective July 1, 2023. This update highlights the recent amendments to Virginia’s prohibition against pay-if-paid provisions, of which owners and contractors should be aware to ensure that their contracts comply with developing law in the Commonwealth.
Recap on Senate Bill 550
On April 27, 2022, the Virginia General Assembly passed Senate Bill 550, which amended Virginia Code §§ 2.2-4354 and 11-4.6, which govern both public and private sector contracts. In short, SB 550 (as the bill is commonly known) prohibited pay-if-paid clauses, and established fixed deadlines for the payment of invoices on private projects. Previously, Virginia’s Prompt Payment Act only applied to public projects.
Read the court decisionRead the full story...Reprinted courtesy of
Hanna Lee Blake, Watt TiederMs. Blake may be contacted at
hblake@watttieder.com
No Coverage for Faulty Workmanship Based Upon Exclusion for Contractual Assumption of Liability
August 06, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Supreme Court for West Virginia determined the policy's contractual assumption exclusion barred coverage for the general contractor based upon claims of faulty workmanship. J.A. St & Assocs. v. Bitco Gen. Ins. Corp., 2019 W. Va. LEXIS 205 (May 1, 2019).
J.A. Street & Associates, Inc. entered a contract with the developer, Thundering Herd Development, L.L.C., to build a commercial shopping center on seventy-eight acres of land. Street agreed to oversee the site preparation for the development and the construction of many of the buildings. Thundering Herd retained an engineering firm, S&ME, Inc. to do geotechnical exploration and to provide advice regarding land preparation for the shopping center. Thundering Heard also entered an agreement with the Target Corporation to construct a store on a pad to be prepared at the shopping center.
Street hired subcontractors to prepare the site by grading the land and installing fill material. A slope was constructed at the rear of the proposed Target site, but it failed, causing a landslide, damage to the pad, and damage to adjacent property owned by a third party. Thundering Heard incurred $721,875 in additional costs to repair this slope, reconstruct the Target site, and compensate the neighbor for the damage to the adjacent property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
FIFA Inspecting Brazil’s World Cup Stadiums
March 26, 2014 —
Beverley BevenFlorez-CDJ STAFFRepresentatives from FIFA have returned to Brazil to conduct inspections of the World Cup stadiums, according to the San Francisco Chronicle. Even though Brazil had told FIFA they would have all twelve done by the end of 2013, only nine are finished. Furthermore, “infrastructure work in many of the 12 host cities remains far from completed.”
“This is the last occasion for the organizers to take stock of the operational preparations before the respective FIFA World Cup installations begin to be implemented in all 12 host cities,” FIFA said in a statement, as quoted in the San Francisco Chronicle.
Read the court decisionRead the full story...Reprinted courtesy of
Ninth Circuit Construes Known Loss Provision
August 19, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Ninth Circuit reversed the district court's award of summary judgment to the insurer after analyzing the known loss provision in the insured subcontractor's policy. Kaady v. Mid-Continent Cas. Co., 2015 U.S. App. LEXIS 10754 (9th Cir. June 25, 2015).
The insured was awarded a subcontract to install manufactured stone at the residential project. The stone was affixed to the wall sheathing. The insured also wrapped deck posts with manufactured stone and installed masonry caps on the toe of the stone that was wrapped around the deck posts.
After construction was completed, the insured was called back to the project to inspect cracks in the manufactured stone and masonry caps he installed. The insured told the general contractor that the cracks were likely due to settling. Three months after inspecting the cracks, the insured purchased a CGL policy from Mid-Continent.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Professional Liability Alert: California Appellate Courts In Conflict Regarding Statute of Limitations for Malicious Prosecution Suits Against Attorneys
April 28, 2014 —
David W. Evans & Stephen J. Squillario – Haight Brown & Bonesteel LLPIn conflict with an earlier decision by a different division within the same District, and with a prior decision of another District which followed the earlier case, Division Three of the Second Appellate District has concluded, contrary to established precedent, that the general two-year limitations period set forth in Code of Civil Procedure section 335.1 (“Section 335.1”) applies to malicious prosecution claims against attorneys, rather than the specific one-year statute of limitations for claims against attorneys codified in Code of Civil Procedure section 340.6 (“Section 340.6”).
In Roger Cleveland Golf Co., Inc. v. Krane & Smith, APC (filed April 15, 2014, Case No. B237424, consolidated with Case No. B239375), Roger Cleveland Golf Co., Inc. (“Cleveland Golf”), filed a malicious prosecution action against Krane & Smith (“the Attorneys”), who had unsuccessfully prosecuted the underlying breach of contract matter for their client against Cleveland Golf. In that action, on April 26, 2010, the trial court entered its order granting a motion for nonsuit and dismissing the complaint in favor of Cleveland Golf. On May 24, 2011, or approximately 13 months after the trial court had dismissed the underlying complaint, Cleveland Golf commenced a malicious prosecution action against the Attorneys. In the interim, the Attorneys initiated an appeal of the underlying judgment, which was eventually dismissed approximately seven months later. In response to the complaint, the Attorneys filed a special motion to strike, commonly referred to as an anti-SLAPP motion, which included the argument that the malicious prosecution claim was time-barred under the one-year limitations period of Section 340.6. The trial court granted the Attorneys’ motion based on the statute of limitations (and Cleveland Golf’s failure to demonstrate a probability of success on the merits) and dismissed the case. Cleveland Golf’s appeal followed.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com, Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
How a Robot-Built Habitat on Mars Could Change Construction on Earth
October 14, 2019 —
Drew Turney - Engineering News-RecordAccording to a 2018 report by the International Energy Agency and UN Environment, the global construction industry is responsible for 39% of energy-related carbon-dioxide emissions. That is a huge, scary number—but one that comes with an equally large opportunity to mitigate climate change. The 2015 Paris climate talks revealed that by using existing technology, construction could cut global carbon emissions by up to a third.
Read the court decisionRead the full story...Reprinted courtesy of
Drew Turney, ENRENR may be contacted at
ENR.com@bnpmedia.com
Construction and Contract Issues Blamed for Problems at Anchorage Port
August 27, 2013 —
CDJ STAFFA third-party audit of the construction at the Port of Anchorage has found fault with the design provided by the engineers. In response, PND, the engineering firm involved, has claimed that it was not their design, but faulty construction of it that lead to an interruption in the construction project.
Separately, the Office of the Inspector General has called into question how MARAD, the agency which oversaw the port construction, handled the planning and contracts for the project.
Control of the project has been taken over by the Municipality of Anchorage, and they have called into question PND’s open cell sheet pile design and PND’s design of the dock infrastructure. Simpson, Gumpertz and Heger reviewed the design, comparing it to a design provided by CH2M Hill, and found that the PND design was inadequate. A contract was subsequently awarded to CH2M Hill.
Read the court decisionRead the full story...Reprinted courtesy of
Safeguarding the U.S. Construction Industry from Unfair Competition Abroad
November 07, 2022 —
Ric Macchiaroli - Gravel2Gavel Construction & Real Estate Law BlogIn April 2015, the U.S. International Trade Commission (ITC) issued an exclusion order prohibiting the importation of certain foreign-made crawler cranes into the United States for a period of at least 10 years. That order was the result of a 20-month investigation by the ITC, initiated by a Wisconsin-based crane manufacturer based on allegations of patent infringement and trade secret misappropriation by a China-based company. Defined by powerful injunctive remedies, unique rules, and a lightning-fast docket, the ITC can help protect American industry from unfair acts in the importation of articles into the United States. This post explores the traits that make the ITC an attractive venue for potential complainants.
ITC Site Plan
The ITC is a specialized trade court located in Washington, D.C., that has broad authority to investigate and remedy unfair trade practices. One of the ITC’s primary functions is to conduct unfair import investigations, also known as “section 337” investigations, after the authorizing statute. A section 337 investigation can be instituted based on any number of unfair acts, including, but not limited to, patent infringement (utility and design), registered and common law trademark infringement, copyright infringement (including violations of the Digital Millennium Copyright Act), trade dress infringement, and trade secret misappropriation. Business torts such as passing off, false advertising, and tortious interference with business relations have also formed the bases of investigations.
Read the court decisionRead the full story...Reprinted courtesy of
Ric Macchiaroli, PillsburyMr. Macchiaroli may be contacted at
ric.macchiaroli@pillsburylaw.com