Competitive Bidding Statute: When it Applies and When it Does Not
April 15, 2024 —
Mason Fletcher - Ahlers Cressman & Sleight PLLCThe University of Washington (UW), a public university, aimed to secure a real estate developer for a new building on its campus. The proposal involved an 80-year ground lease (the “Lease”), and developers submitted bids. The selected developer would demolish an existing building, construct a new one, own it during the Lease at its own cost, and UW would lease back a portion, with ownership reverting to UW at the Lease’s end. Alexandria Real Equities, Inc. (ARE) was a finalist but ultimately was not selected, and the Lease was awarded to Wexford Science and Technology, LLC (Wexford). As a result, ARE filed suit against UW asserting three claims: 1) UW lacked authority to execute the Lease, 2) UW didn’t follow required competitive bidding procedures, and 3) UW’s developer selection process was arbitrary and capricious. None of these claims were successful and ARE appealed.
Division II of the Washington Court of Appeals affirmed in Alexandria Real Estate Equities Inc. v. Univ. of Wash., __ Wn. App. __, 539 P.3d 54 (2023), a published decision. The Court concluded, based on the facts in that case, that because construction was not publicly funded, UW did not have to follow competitive bidding requirements that were laid out in a statute relevant to state universities. Still, the Court applied the “bright-line cutoff point” that prohibits disappointed bidders from challenging an award once a contract has been executed. See Dick Enterprises, Inc. v. Metro. King County, 83 Wn. App. 566, 572, 922 P.2d 184 (1996).
Read the court decisionRead the full story...Reprinted courtesy of
Mason Fletcher, Ahlers Cressman & Sleight PLLCMr. Fletcher may be contacted at
mason.fletcher@acslawyers.com
Louisiana District Court Declines to Apply Total Pollution Exclusion
December 15, 2016 —
William S. Bennett – Saxe Doernberger & Vita, P.C.The United States District Court for the Eastern District of Louisiana recently decided that a broad total pollution exclusion in a marine general liability policy did not bar coverage.
The insurer could not unambiguously establish, based on the facts of the underlying case, that waste from a shipyard’s sandblasting activities met the requirements of the exclusion.
The court found that the insurer could not meet Louisiana’s three-part test to determine whether the policy’s total pollution exclusion applied. The Doerr test requires an insurer to refer to the allegations in the underlying complaint to prove 1) the insured is a “polluter”, 2) the injury-causing substance is a “pollutant,” and 3) there was a “discharge, dispersal, seepage, migration, release or escape” of the pollutant.
Total pollution exclusions are extremely prohibitive for policyholders because they eliminate coverage for virtually all pollution incidents, but this decision reinforces that policyholders may still have a path to coverage.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
How to Challenge a Project Labor Agreement
May 24, 2018 —
Wally Zimolong – Supplemental Conditions Building and Construction Trades Council of Metropolitan District v. Associated Builders and Contractors of Massachusetts Rhode Island, Inc Massachusetts Water Resources Authority v. Associated Builders and Contractors of Massachusetts Rhode Island, Inc, 507 U.S. 218, 113 S.Ct. 1190, 122 L.Ed.2d 565 (1993) , affectionately knows as Boston Harbor, is the seminal Supreme Court decision that held that the National Labor Relations Act (“NLRA”) does not preempt government mandated project labor agreements (“PLAs”) if the government entity is acting as a market participant rather than a market regulator. Boston Harbor has led to many believing that virtually all PLAs are legal when the government agency is a project owner or if the PLA involves a private project. However, does Boston Harbor really cut that far?
In short, no. The primary issue in Boston Harbor was one of preemption. The Supreme Court addressed whether the NLRA preempted state and local laws and ordinances mandating PLAs. On that narrow issue, the Supreme Court said there is no preemption if the government is acting as a market participant. What the Court did not address is whether other federal statutes invalidate PLAs. Specifically, whether PLA’s can run afoul of Section 8(e), the so called “hot cargo” provisions, of the NLRA.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Location, Location, Location—Even in Construction Liens
October 28, 2015 —
Craig Martin – Construction Contractor AdvisorWe all know the importance of filing a construction lien within 120 days of your last work. Nebraska Construction Lien Act, § 52-137. But, equally, if not more important is filing the construction lien on the correct property.
Often times on a construction project, the exact address of the project may not be known. And, if there are a few buildings going up on the same general site, it is difficult to determine which property or building address you are working on.
Sometimes you can look at the contract. For example, the AIA family of documents lists the address on the first page. But, what if the wrong address is listed? What if the wrong owner is listed?
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Trade Contract Revisions to Address COVID-19
August 23, 2021 —
David R. Cook Jr. - Autry, Hall & Cook, LLPMany trade contracts contain a clause that may protect trade contractors from catastrophic events like pandemics. These clauses are known as force-majeure clauses (covering acts of God). They basically say if these unavoidable events happen, the contractor is relieved of its obligations to the extent of the impact.
However, many common industry forms have not been updated to specifically address COVID-19. (They may be waiting to see how the courts treat their existing language first.) So to ensure impacts from COVID-19 are covered, a trade contractor should consider expressly adding it to the force-majeure clause. See the example below.
Notably, typical force-majeure clauses do not say the trade contractor gets more money. So an escalation clause could be added to the force-majeure clause.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Recent Bribery and Anti-Corruption Enforcement Trends in Global Construction Industry
August 26, 2019 —
Ralph A. Finizio & Anthony Finizio - ConsensusDocsBribery and corruption have long plagued the construction industry, particularly in the developing world and emerging markets. Large contracts often trickle down through layers of subcontractors, presenting opportunities for corruption at each level. The risk is enhanced in certain foreign jurisdictions, where large corporations may be wholly or partially state-owned enterprises and public officials may expect payment in exchange for state-issued licenses or government contracts.
Recent enforcement trends indicate that both the U.S. Department of Justice (DOJ) and the Securities and Exchange Commission (SEC) are increasingly targeting the construction industry for anti-bribery and corruption actions under the Foreign Corrupt Practices Act (FCPA). Several former DOJ officials also recently commented that the construction industry has become a focus of anti-corruption enforcement efforts.
The FCPA is a formidable tool for regulators, making it unlawful to influence a foreign government official with any type of payment or personal reward. While certain safe harbors apply — including de minimis payments made to expedite routine governmental action or the payment being lawful in the foreign jurisdiction — these exceptions are construed narrowly and can be difficult to apply in practice.
Reprinted courtesy of
Ralph A. Finizio, Pepper Hamilton LLP and
Anthony Finizio, Pepper Hamilton LLP
Mr. Finizio may be contacted at finizior@pepperlaw.com
Mr. Finizio may be contacted at finizioa@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Pa. Contractor Pleads No Contest to Prevailing-Wage Charges, Pays Workers $20.7M
September 20, 2021 —
Tom Ichniowski - Engineering News-RecordPennsylvania construction contractor Glenn O. Hawbaker Inc. has pleaded no contest to counts of theft of worker pay—in alleged violation of state prevailing-wage laws—and will pay 1,267 workers restitution of $20.7 million in unpaid wages, Pennsylvania Attorney General Josh Shapiro said.
The company entered its plea to four felony counts of “theft by failure to make required disposition of funds received” on Aug. 3 before President Judge Pamela A. Ruest of the Centre County Court of Common Pleas in Bellefonte, Pa.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
School District Settles Over Defective Athletic Field
December 11, 2013 —
CDJ STAFFThe Hillsboro, Oregon School District has settled a lawsuit with Mahlum Architects of Portland, one of the four companies sued by the school district over problems with a soccer field. The total lawsuit was for $1.7 million. The architects have settled for $25,000. The manufacturer of Astro Turf also settled with the school for an as-yet undisclosed amount.
What the school describes as the “primary defendants” have yet to settle. The school had to close the soccer field when drainage problems lead to large holes in the playing field.
Read the court decisionRead the full story...Reprinted courtesy of