BERT HOWE
  • Nationwide: (800) 482-1822    
    Medical building building expert Seattle Washington casino resort building expert Seattle Washington low-income housing building expert Seattle Washington hospital construction building expert Seattle Washington production housing building expert Seattle Washington housing building expert Seattle Washington structural steel construction building expert Seattle Washington mid-rise construction building expert Seattle Washington tract home building expert Seattle Washington multi family housing building expert Seattle Washington custom homes building expert Seattle Washington Subterranean parking building expert Seattle Washington townhome construction building expert Seattle Washington institutional building building expert Seattle Washington retail construction building expert Seattle Washington landscaping construction building expert Seattle Washington industrial building building expert Seattle Washington concrete tilt-up building expert Seattle Washington high-rise construction building expert Seattle Washington condominium building expert Seattle Washington parking structure building expert Seattle Washington custom home building expert Seattle Washington
    Seattle Washington architectural expert witnessSeattle Washington multi family design expert witnessSeattle Washington building consultant expertSeattle Washington construction code expert witnessSeattle Washington building expertSeattle Washington civil engineering expert witnessSeattle Washington hospital construction expert witness
    Arrange No Cost Consultation
    Building Expert Builders Information
    Seattle, Washington

    Washington Builders Right To Repair Current Law Summary:

    Current Law Summary: (SB 5536) The legislature passed a contractor protection bill that reduces contractors' exposure to lawsuits to six years from 12, and gives builders seven "affirmative defenses" to counter defect complaints from homeowners. Claimant must provide notice no later than 45 days before filing action; within 21 days of notice of claim, "construction professional" must serve response; claimant must accept or reject inspection proposal or settlement offer within 30 days; within 14 days following inspection, construction pro must serve written offer to remedy/compromise/settle; claimant can reject all offers; statutes of limitations are tolled until 60 days after period of time during which filing of action is barred under section 3 of the act. This law applies to single-family dwellings and condos.


    Building Expert Contractors Licensing
    Guidelines Seattle Washington

    A license is required for plumbing, and electrical trades. Businesses must register with the Secretary of State.


    Building Expert Contractors Building Industry
    Association Directory
    MBuilders Association of King & Snohomish Counties
    Local # 4955
    335 116th Ave SE
    Bellevue, WA 98004

    Seattle Washington Building Expert 10/ 10

    Home Builders Association of Kitsap County
    Local # 4944
    5251 Auto Ctr Way
    Bremerton, WA 98312

    Seattle Washington Building Expert 10/ 10

    Home Builders Association of Spokane
    Local # 4966
    5813 E 4th Ave Ste 201
    Spokane, WA 99212

    Seattle Washington Building Expert 10/ 10

    Home Builders Association of North Central
    Local # 4957
    PO Box 2065
    Wenatchee, WA 98801

    Seattle Washington Building Expert 10/ 10

    MBuilders Association of Pierce County
    Local # 4977
    PO Box 1913 Suite 301
    Tacoma, WA 98401

    Seattle Washington Building Expert 10/ 10

    North Peninsula Builders Association
    Local # 4927
    PO Box 748
    Port Angeles, WA 98362
    Seattle Washington Building Expert 10/ 10

    Jefferson County Home Builders Association
    Local # 4947
    PO Box 1399
    Port Hadlock, WA 98339

    Seattle Washington Building Expert 10/ 10


    Building Expert News and Information
    For Seattle Washington


    Event-Cancellation Insurance Issues During a Pandemic

    Anti-Fracking Win in N.Y. Court May Deal Blow to Industry

    Avoid Drowning in Data: Keep Afloat with ESI in Construction Litigation

    Damron Agreement Questioned in Colorado Casualty Insurance v Safety Control Company, et al.

    DEP Plan to Deal with Noxious Landfill Fumes Met with Criticism

    D.R. Horton Earnings Rise as Sales and Order Volume Increase

    SNC-Lavalin’s Former Head of Construction Pleads Guilty to Bribery, Money Laundering

    School Blown Down by Wind Still Set to Open on Schedule

    N.J. Governor Signs Bill Expanding P3s

    Indemnification Against Release/“Disposal” of Hazardous Materials

    An Interesting Look at Mechanic’s Lien Priority and Necessary Parties

    Back to Basics: What is a Changes Clause?

    Architect Not Responsible for Injuries to Guests

    Construction Manager’s Win in Michigan after Michigan Supreme Court Finds a Subcontractor’s Unintended Faulty Work is an ‘Occurrence’ Under CGL

    New York Court of Appeals Finds a Proximate Cause Standard in Additional Insured Endorsements

    Traub Lieberman Attorneys Recognized as 2024 “Top Lawyers” in New York by Hudson Valley Magazine

    My Construction Law Wish List

    Nebraska Joins the Ranks—No CGL Coverage for Faulty Work

    Shimmick Gets Nod for Second Pilot Pile at Settling Millennium Tower

    Unlicensed Contracting and Florida Statute S. 489.128

    Recent Third Circuit OSHA Decision Sounds Alarm for Employers and Their Officers

    Potential Construction Liabilities Contractors Need to Know

    Open & Known Hazards Under the Kinsman Exception to Privette

    North Carolina Should Protect Undocumented Witnesses to Charlotte Scaffolding Deaths, Unions Say

    Real Estate & Construction News Round-Up 04/20/22

    Ninth Circuit Reverses Grant of Summary Judgment to Insurer For Fortuitous Loss

    Judicial Panel Denies Nationwide Consolidation of COVID-19 Business Interruption Cases

    Balestreri Potocki & Holmes Attorneys Named 2020 Super Lawyers and Rising Star

    Supreme Court Grants Petition for Review Regarding Necessary Parties in Lien Foreclosure Actions

    KONE is Shaking Up the Industry with BIM

    L.A. Makes $4.5 Billion Bet on Olympics After Boston Backs Out

    Deductibles Limited to Number of Suits Filed Against Insured, Not Number of Actual Plaintiffs

    Techniques for Resolving Construction Disputes

    Performing Work with a Suspended CSLB License Costs Big: Subcontractor Faces $18,000,000 Disgorgement

    Court Addresses HOA Attempt to Restrict Short Term Rentals

    Faulty Workmanship Exclusion Does Not Bar Coverage

    Nevada Lawmakers Had Private Meetings on Construction Defects

    "Repair Work" Endorsements and Punch List Work

    Homebuilders Are Fighting Green Building. Homeowners Will Pay.

    St. Petersburg Florida’s Tallest Condo Tower Allegedly Riddled with Construction Defects

    Final Thoughts on New Pay If Paid Legislation in VA

    In South Carolina, Insurer's Denial of Liability Does Not Waive Attorney-Client Privilege for Bad Faith Claim

    Banks Loosening U.S. Mortgage Standards: Chart of the Day

    RDU Terminal 1: Going Green

    Homebuilders Opposed to Potential Change to Interest on Construction Defect Expenses

    Hurdles with Triggering a Subcontractor Performance Bond

    Brown and Caldwell Team with AECOM for Landmark Pure Water Southern California Program

    Judge Tells DOL to Cork its Pistol as New Overtime Rule is Blocked

    Congratulations to Partner John O’Meara for Being Named as One of America’s Top 100 Civil Defense Litigators for Three Consecutive Years!

    Toolbox Talk Series Recap - The New Science of Jury Trial Advocacy
    Corporate Profile

    SEATTLE WASHINGTON BUILDING EXPERT
    DIRECTORY AND CAPABILITIES

    Leveraging from more than 7,000 construction defect and claims related expert witness designations, the Seattle, Washington Building Expert Group provides a wide range of trial support and consulting services to Seattle's most acknowledged construction practice groups, CGL carriers, builders, owners, and public agencies. Drawing from a diverse pool of construction and design professionals, BHA is able to simultaneously analyze complex claims from the perspective of design, engineering, cost, or standard of care.

    Building Expert News & Info
    Seattle, Washington

    Damages or Injury “Likely to Occur” or “Imminent” May No Longer Trigger Insurance Coverage

    January 05, 2017 —
    Washington Courts allow an insurer to determine its duty to defend an insured against a lawsuit based only on the face of the complaint and the limitations of the insurance policy. This is otherwise known as the “eight corners” rule (four corners of the complaint plus the four corners of the policy). In other words, the insurance company is not permitted to rely on facts extrinsic to the complaint in order to deny its duty to defend an insured. See Truck Ins. Exch. v. VanPort Homes, Inc., 147 Wn.2d 751, 763 (2002). The laws in Washington provide greater protection to the insured over the insurer when it comes to the insurer’s duty to defend. The duty to defend a claim is triggered if a claim could “conceivably” be covered under the policy. See Woo v. Fireman’s Insurance, 161 Wn.2d 43 (2007). If there is any ambiguity in a policy with regard to coverage, the ambiguity is interpreted in favor of the insured. As a result, contractors in Washington regularly tender claims or potential claims to their insurers even when damage has not occurred but will occur in the imminent future. Especially in the context of construction defect cases, a contractor will tender such a claim to its insurer to trigger the broad duty of the insurer to provide a defense. We also regularly recommend this to our contractor clients. For example, if a building owner serves a contractor with a claim that the construction and installation of a window system will imminently cause leaks and corrosion, we would recommend that the contractor tender the claim to its commercial general liability insurer. Washington courts have found a duty to defend when there are allegations in the complaint that covered damages will occur in the imminent future. Read the court decision
    Read the full story...
    Reprinted courtesy of Masaki J. Yamada, Ahlers & Cressman PLLC
    Mr. Yamada may be contacted at myamada@ac-lawyers.com

    US Supreme Court Backs Panama Canal Owner in Dispute with Builders

    May 20, 2024 —
    A long-running legal battle over the concrete used in construction of the Panama Canal's third lane expansion locks has reached its end in U.S. courts—with the U.S. Supreme Court on March 26 upholding a $271.8-million award to the project owner, the Panama Canal Authority, against its contractor group, Grupo Unidos por el Canal. Reprinted courtesy of C.J. Schexnayder, Engineering News-Record Mr. Schexnayder may be contacted at schexnayderc@enr.com Read the full story... Read the court decision
    Read the full story...
    Reprinted courtesy of

    Practical Pointers for Change Orders on Commercial Construction Contracts

    December 31, 2014 —
    Construction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule. “Changes” Clauses in Construction Contracts Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible. In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts. While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract. Practice Pointers for Change Orders In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
    • Carefully Negotiate and Draft Change Order Provisions in the Original Contract. A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
    • Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures. Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
    • Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work. Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
    • Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative. When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
    • Avoid Vague and Open-Ended Change Orders. Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
    • Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable. When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
    About the Author: John E. Bowerbank, Newmeyer & Dillion Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com Read the court decision
    Read the full story...
    Reprinted courtesy of

    New Change Order Bill Becomes Law: RCW 39.04.360

    July 08, 2024 —
    A new statute (RCW 39.04.360) became effective on June 6, 2024, and it applies to extra work performed by contractors and subcontractors on public and private projects in Washington State. The intent of the original bill was to allow contractors and subcontractors to get paid sooner for undisputed additional work. The statute does not apply to private residential projects of 12 units or less. The statute allows for recovery of interest for contractors/subcontractors at 1% per month (12% per year) on the value of the additional work if the statute is violated. Here are the requirements of the new statute:
    • Public and private owners must issue a change order for the undisputed amount of additional work performed by a contractor, subcontractor, or supplier no later than 30 days after the work is satisfactorily completed and the change is requested by the contractor.
    • General contractors, and subcontractors with lower-tier subs, must issue a change order to their subcontractors impacted by the change within 10 days after receipt of the approved change order from the owner/upper-tier contractor.
    Read the court decision
    Read the full story...
    Reprinted courtesy of Brett M. Hill, Ahlers Cressman & Sleight PLLC
    Mr. Hill may be contacted at brett.hill@acslawyers.com

    Third Circuit Affirms Use of Eminent Domain by Natural Gas Pipeline

    November 28, 2018 —
    On October 30, the U.S. Court of Appeals for the Third Circuit decided the case of Transcontinental Gas Pipe Line Co., LLC v. Permanent Easements for 2.14 Acres, et al. , affirming the District Court’s grant of a preliminary injunction to Transcontinental Gas Pipe Line Company, LLC (Transcontinental). This case involves the construction of the “Atlantic Sunrise Expansion Project,” a natural gas pipeline that runs through Pennsylvania, Maryland, Virginia, North Carolina and South Carolina. Under the Natural Gas Act (NGA), pipeline companies can exercise powers of eminent domain when they are acting in the public interest. The Third Circuit cautions that this is a “standard” eminent domain power, and not a “quick take” that is permitted under another statute. Read the court decision
    Read the full story...
    Reprinted courtesy of Anthony B. Cavender, Pillsbury
    Mr. Cavender may be contacted at anthony.cavender@pillsburylaw.com

    Detect and Prevent Construction Fraud

    August 28, 2018 —
    With construction ramping up in many markets, construction firms plan to hire more workers, indicating the industry's continued optimism about a healthy economy. It's news that is both exciting and perhaps a little daunting: hiring competent, qualified tradespeople is challenging under any conditions. No one wants to hire a poor employee—or worse, someone who turns out to be a thief. While no industry is immune to occupational fraud, the construction industry is one of the harder hit. The average construction fraud scheme costs business owners $227,000 before it is detected. Worse, the fraudster is very often someone the employer implicitly trusts, making it even harder to believe the company has been the victim of insider theft. Fraud can hurt a business's reputation, cost thousands and betray trust. It may seem uncontrollable and unforeseeable unless employers know how to detect and deter fraudulent behavior. Reprinted courtesy of Tiffany Couch, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved. Read the court decision
    Read the full story...
    Reprinted courtesy of
    Ms. Couch may be contacted at tcouch@acuityforensics.com

    Nevada Construction Defect Lawyers Dead in Possible Suicides

    March 28, 2012 —

    A number of news sources have reported on the recent death of Nevada construction defect attorney, Nancy Quon. Ms. Quon was implicated in a recent scandal in which a group conspired to control homeowner associations in order to divert construction defect lawsuits to the members of the conspiracy.

    Ms. Quon was found dead in her bathtub. The details are still under investigations. She and her boyfriend were accused of a failed arson/suicide scheme in 2010. Ms. Quon survived an attempt to burn down her home. Subsequently, her boyfriend obtained some gamma-hydroxybutyric acid (GBH) for her, as part of another failed suicide attempt.

    Subsequent to Ms. Quon’s death, David Amesbury was found in California dead by hanging. Mr. Amesbury took a plea deal in the case, and he had admitted his role in providing legal and construction contracts to firms in the conspiracy. He was accused of fixing HOA elections.

    Read the full story…

    Read the full story…

    Read the full story…

    Read the full story…

    Read the court decision
    Read the full story...
    Reprinted courtesy of

    When Is a Project Delay Material and Actionable?

    January 11, 2022 —
    Welcome to 2022! This year, the construction industry will undoubtedly reflect on the last two years as unprecedented times plagued by construction project delays. The COVID-19 pandemic contributed to suspension of work and closure of construction projects worldwide in 2020. The end of 2021 brought additional delays caused by an inexplicable clog in the supply chain of construction materials. The combined impact of these events on project milestones and completion deadlines led our clients to ask, with unusual and particular urgency, who is liable for such delays and how do contracting parties lessen the consequences from such unexpected and uncontrollable delays. Granted that project delays are nothing new or unusual. They were common enough before inflation caused shipping complications and pandemic decimated the construction labor force. All delays, whatever the source, variably cause loss to all players on a construction project. But not all delays matter when it comes to claims and remedies available to the contracting parties in dispute resolution, where the determinative focus is on material delays impacting the entire project and on delays the claimant can credibly prove. Most, if not all, jurisdictions interpret actionable delays from the contract documents for the project. The contract is definitely where you should start before pursuing any delay remedies. Delay remedies may be a time extension only, or a time extension plus your additional general conditions. Some delay remedies may be barred by the contract’s express terms and may be enforced adversely by the courts when such contract terms are indisputable. See Quinn Constr. v. Skanska USA Bldg., Inc., 730 F. Supp. 2d 401, 411 (D.C. Pa. 2010) (enforcing the subcontractor’s contractual waiver of claims for delay and disruption damages). On the other hand, delay damages that are expressly allowed by the contract—like overtime necessitated by the delays—are usually actionable and recoverable. Id. However, not only the contract terms, but applicable law, may affect the outcome. Read the court decision
    Read the full story...
    Reprinted courtesy of Rick Erickson, Snell & Wilmer
    Mr. Erickson may be contacted at rerickson@swlaw.com