Miller Act Statute of Limitations and Equitable Tolling
July 11, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to a Miller Act payment bond claim, there is a one-year statute of limitations—“The Miller Act contains a statute of limitations provision that requires actions to ‘be brought no later than one year after the day on which the last of the labor was performed or material was supplied by the person bringing the claim.’” U.S. f/u/b/o Techniquex Specialty Flooring, Inc., v. Philadelphia Indemnity Ins. Co., 2022 WL 169070, *3 (M.D.Penn. 2022) (citing the Miller Act).
There is an argument, albeit a difficult one, to support an equitable tolling of the one-year statute of limitations. This would be an argument filed when the one-year statute of limitations expires, but there is reason for missing the statute of limitations caused typically by the overt misleading of the defendant (surety/bond-principal):
“Equitable tolling functions to stop the statute of limitations from running where the claim’s accrual date has passed.” “Equitable tolling is appropriate in three situations: (1) when the defendant has actively misled the plaintiff respecting the facts which comprise the plaintiff’s cause of action; (2) when the plaintiff in some extraordinary way has been prevented from asserting his rights; and (3) when the plaintiff has timely asserted his rights in the wrong forum.” The first ground for equitable tolling“appears to be the same, in all important respects” to equitable estoppel, which “excuses late filing where such tardiness results from active deception on the part of the defendant” and “what courts describe as ‘equitable tolling’ is encompassed by the latter two parts of our Circuit’s doctrine.” The extraordinary circumstances standard may be met “where the defendant misleads the plaintiff, allowing the statutory period to lapse; or when the plaintiff has no reasonable way of discovering the wrong perpetrated against her …”
Tehniquex, supra, at *5 (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Congratulations to San Diego Partner Alex Giannetto and Senior Associate Michael Ibach on Settling a Case 3 Weeks Into a 5-Week Trial!
April 15, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPPartner Alex Giannetto and Senior Associate Michael Ibach of BWB&O’s San Diego office started a trial in San Diego set to last at least five weeks. Plaintiffs alleged causes of action of negligence, trespass and nuisance against BWB&O’s client, arguing the owner/property manager did not properly handle alleged overwatering of the front yard, allegedly resulting in a landslide impacting 8 homes on a City slope in Carlsbad. Cross-Complainant City alleged independent negligence to fix the slope it owned and controlled as well as various indemnity-based causes of action against BWB&O’s client. Plaintiffs claimed over $24 million in damages, while Cross-Complainant placed sole blame for the incident on BWB&O’s client around $6 million.
Heading into trial, it was made clear that neither Plaintiffs nor Cross-Complainant would accept anything less than 7-figures to settle BWB&O’s client out of the case. In the first week of trial, BWB&O was able to leverage motions in limine, opening statements, and cross-examinations to secure a dismissal of three of the four causes of action alleged by Plaintiff that were associated with pain & suffering. In the second week of trial, BWB&O secured a dismissal of Cross-Complainant’s negligence cause of action paving the way for a settlement with Plaintiffs. Leveraging the threat of a non-suit when Plaintiffs rested, BWB&O secured resolution of Plaintiffs’ complaint for a fraction of what had previously been sought. Finally, BWB&O was able to secure a dismissal of the remaining indemnity-based causes of action in the cross-complaint and fully extract the client from the matter.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
The Utility of Arbitration Agreements in the Construction Industry
December 30, 2019 —
Brian L. Gardner & Jason R. Finkelstein - Construction ExecutiveIn today’s ever-evolving world of employment law, it is far from an easy task for construction industry employers to operate their business while successfully navigating all of the potential legal potholes that continue to abound and multiply seemingly with every passing day. This is particularly true in the face of the onslaught of claims lodged by current and former employees in recent years for alleged unpaid wages. While there may not be a “sure bet” way of avoiding such claims, one tool that employers should strongly consider in their arsenal are arbitration and class action waiver agreements.
To that end, last year, the United States Supreme Court rendered its ground-breaking decision in Epic Systems Corp. v. Lewis, 584 U.S. ___ (2018). In Epic Systems, the Supreme Court held that arbitration agreements containing class and collective action waivers of wage and hour disputes are enforceable. At the time of the decision, a split of authority existed among courts across the country as to whether such agreements were viable. On the one hand, several courts contended that class waivers unfairly violated employees’ rights to collectively bargain under the National Labor Relations Act. On the other hand, many other courts were finding that such agreements were fully enforceable and supported by the policies promoted under the Federal Arbitration Act. The Epic Systems Court sided with this latter viewpoint, concluding that the FAA’s clear policy promoting arbitration as a dispute resolution mechanism and private parties’ rights to freely negotiate contracts outweighed any potential arguments against such agreements under the NLRA.
With wage and hour lawsuits being filed against construction industry employers practically daily, the Epic Systems decision is critically important. Construction employers can now freely enter into arbitration and class waiver agreements with their laborers and thereby potentially limit the cost, expense and exposure of fighting such actions in a public forum on a collective or class-wide basis. To be clear, such agreements will not eliminate employees from bringing such wage and hour claims entirely, nor should the use of those agreements signal to employers that they need not make every good-faith effort to comply with their obligations under the Federal Labor Standards Act and/or any applicable state wage and hour laws. But the reality is that arbitration and class waiver agreements can work to avoid tens or hundreds or even thousands of employees from banding together in some of the massive wage and hour lawsuits being filed across the country. Instead, employers can require that those legal battles be conducted by a single plaintiff in a more controlled environment before an arbitrator (or panel of arbitrators).
Reprinted courtesy of
Brian L. Gardner & Jason R. Finkelstein, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Gardner may be contacted at bgardner@coleschotz.com
Mr. Finkelstein may be contacted at jfinkelstein@coleschotz.com
Read the court decisionRead the full story...Reprinted courtesy of
Do Engineers Owe a Duty to Third Parties?
June 10, 2015 —
Craig Martin – Construction Contractor AdvisorA Texas Court of Appeals, in USA Walnut Creek, DST v. Terracon Consultants, Inc., recently ruled that an engineer owed a duty to the buyer of an apartment complex, even though the engineer had no contractual relationship with the buyer. This is an expansion of the duty professionals owe on construction projects and could signal a change in the law.
In the case, Walnut Creek purchased a three year old apartment complex. A few years after taking possession, Walnut Creek noticed problems with the apartments, including cracking foundations, walls, breaking windows, and out of square door frames. Walnut Creek sued the developer and general contractor, alleging construction defects. The developer claimed that the engineer, Terracon, was at fault and Walnut Creek added Terracon to the lawsuit, asserting that Terracon was negligent in performing engineering services during construction. Terracon asked the court to dismiss the claim, arguing that it did not owe a duty to Walnut Creek. Walnut Creek in turn argued that engineers do owe a duty to subsequent owners. The trial court dismissed the case against the engineer and Walnut Creek appealed.
The appellate court reversed the trial court, finding that the engineer did owe a duty to subsequent purchasers. The court seemed persuaded by the allegations that the engineer actually created the construction defects which were the basis for the litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
A Guide to California’s Changes to Civil Discovery Rules
April 29, 2024 —
Lewis Brisbois NewsroomSan Diego, Calif. (April 10, 2024) - California legislators have changed the rules of discovery in civil cases through the passage of amendments to Code of Civil Procedure sections 2016.090 and 2023.050, effective January 1, 2024.
Section 2016.090 creates a new set of rules for civil litigators in cases filed on or after January 1, 2024, which permits any party to the litigation to demand initial disclosures be provided within 60-days. Such a demand can be made any time after a party has filed a responsive pleading, including a demurrer or motion to strike.
Notably, this rule requires production of all information relevant to any causes of action that are pled at the time of the demand, meaning the parties may be required to disclose information related to claims that are being challenged on demurrer or a motion to strike, such as claims for punitive damages. This statute is only implicated when one of the parties to the action makes a demand and may be modified by stipulation of the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Candlebrook Adds Dormitories With $230 Million Purchase
November 05, 2014 —
John Gittelsohn - BloombergCandlebrook Properties LLC, a closely held company with about 5,000 apartments in the eastern U.S., is diversifying into student housing with the $230 million acquisition of five off-campus properties.
Candlebrook joined with Lubert-Adler Partners on the purchase of buildings with about 3,400 beds near colleges in Georgia, Indiana, Kentucky and Virginia. Formerly known as Vantage Properties LLC, Candlebrook began as an investor in New York City apartments in 2005 and later expanded to New Jersey and the Philadelphia area.
“Student housing is a natural extension of our pre-existing business line,” Neil Rubler, president of New York-based Candlebrook, said in a telephone interview. It’s “a business that’s far less crowded than multifamily, which has been our core business.”
Capitalization rates on apartments, a measure of profitability, have dropped as investors drive up property prices. Student housing has become an attractive alternative, luring homebuilder Toll Brothers Inc. (TOL) and private-equity firm Colony Capital LLC to an industry already home to real estate investment trusts American Campus Communities Inc. (ACC), Campus Crest Communities Inc. (CCG) and Educational Realty Trust Inc. (EDR)
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, BloombergMr. Gittelsohn may be contacted at
johngitt@bloomberg.net
Tennessee Court of Appeals Holds Defendant Has the Burden of Offering Alternative Measure of Damages to Prove that Plaintiff’s Measure of Damages is Unreasonable
July 18, 2018 —
Gus Sara - The Subrogation StrategistIn Durkin v. MTown Construction, LLC, 2018 Tenn. App. LEXIS 128, the Court of Appeals of Tennessee considered whether the lower court properly took judicial notice of an alternative measure of damages to the measure of damages advanced by the plaintiff. The Court of Appeals held that the defendant has the burden of offering evidence of alternative measures of damages if it seeks to argue that the plaintiff’s measure of the damages is unreasonable. The Court of Appeals found that the lower court erred in taking judicial notice of alternative measures of damage when the defendant failed to meet its burden of proof. The court’s holding establishes that, if the defendant does not offer evidence of alternative measures of damage, then the measure of damages introduced by the plaintiff will apply.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com
Texas Court Requires Insurer to Defend GC Despite Breach of Contract Exclusion
December 19, 2018 —
Ashley L. Cooper - Saxe Doernberger & Vita, P.C.In Mt. Hawley Insurance Co. v. Slay Engineering, et al.,1 a Texas federal court ruled in favor of a general contractor, finding that its insurer had a duty to defend it in a construction defect case filed by the owner. The decision adds more clarity to the interpretation of the subcontractor exception to the “Damage to Your Work” exclusion as well as the Breach of Contract exclusion, which has been the subject of several cases coming out of Texas over the past decade.
Read the court decisionRead the full story...Reprinted courtesy of
Ashley L. Cooper, Saxe Doernberger & Vita, P.C.Ms. Cooper may be contacted at