Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
March 05, 2015 —
William L. Porter – Porter Law Group, Inc.The “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Completion will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
What commonly occurs however is that early in the process the owner authorizes or even requires its tenant to perform beneficial tenant improvements on the property. This authorization is often set forth in a tenant lease or other written document. The dispositive factor for determining whether the Notice of Non-Responsibility will be enforceable though is that the owner knows that these improvements will be made to the property and intends that they be made, usually long before the work begins. Indeed, the owner has usually negotiated these very terms into the lease contract. The owner then mistakenly believes that once work on the property commences it has 10 days to post and record a Notice of Non-Responsibility and thereby protect itself from a mechanics lien.
The usual error is two-fold. First, the statute states that the Notice is available when the owner “did not contract for the work of improvement”. The fact though is that the owner did contract for the work of improvement. It did so through the lease contract. This is true even though the owner’s contract was not with the contractor or supplier directly. Secondly, the 10 day period to post and record the Notice begins when the owner first “has knowledge” of the work of improvement. This knowledge was of course gained when the lease was negotiated and signed, providing knowledge typically many days before the work has begun. Thus, the 10 day period can also seldom be met. The Notice of Non-Responsibility will therefore fail both rules because the owner has in fact contracted for the improvement and because he does not act within 10 days of gaining this knowledge.
The next event in the typical scenario occurs when the tenant does not pay its contractor. The contractor then has nothing to pay its subcontractors. Material suppliers also go unpaid. Mechanics liens are then recorded by the unpaid claimants, followed by foreclosure actions within ninety days thereafter. Owners will typically point to the Notice of Non-Responsibility they posted and recorded, claiming its protection. Claimants then in turn point to the lease or other evidence that the owner knew of the pending improvements and contracted in some way that the improvements be performed, often also more than 10 days before they posted the Notice. Judges generally agree with the unpaid mechanics lien claimants and the Notice of Non-Responsibility is deemed ineffective.
The fact that the Court does not enforce the Notice of Non-Responsibility under these circumstances is not an unfair result. Since the owner authorized the work to be performed and it received a substantial benefit in the form of those improvements, it is not unfair that the owner should pay for those benefits. It would be inequitable for the owner to obtain the benefit of the improvements which it authorized but for which it did not pay, while allowing those who provided the benefit to go unpaid. Moreover, without such a system in place the door would be open to owners setting up sham “tenants” who would enter into contracts to have work performed, only to disappear when the work is completed, leaving the contractor without a source of payment. The system in place as described above prevents such duplicity. Owners would do well to arm themselves with proper knowledge of when the Notice of Non-Responsibility will and will not protect them and then responsibly use the Notice of Non-Responsibility.
For the legal eagles among you, the following cases illustrate the view of the courts, consistent with the above: Baker v. Hubbard (1980) 101 Cal.App.3d 226; Ott Hardware v. Yost (1945) 69 Cal. App.2d 593 (lease terms); Los Banos Gravel Co. v. Freeman (1976) 58 Cal.App.3d 785 (common interest); Howard S. Wright Construction Co. v. Superior Court (2003); 106 Cal.App.4th 314 (participating owner).
William L. Porter of
Porter Law Group, Inc. located in Sacramento, California may be contacted at (916) 381-7868 or bporter@porterlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Breath of Fresh Air
February 14, 2023 —
Rachel E. Pelovitz - Construction ExecutiveFor the first time since 2012, the Environmental Protection Agency updated and strengthened air quality standards. Construction sites are responsible for 14.5% of particulate matter in the air and 8% of total emissions in the United States.
With that in mind, Construction Executive has spoken with Serene Al-Momen, Ph.D. and chief executive officer of
Attune, in an exclusive interview. Al-Momen is an expert in air quality and offers her opinion on standards, consequences and the impact on the construction industry—which she has specific experience with due to Attune’s relationship with
Clark Construction, a member of
Associated Builders and Contractors.
CONSTRUCTION EXECUTIVE: What is important about air quality standards in general?
Serene Al-Momen: Air quality standards regulate the amount of pollution that's allowed to be emitted into the atmosphere.
Reprinted courtesy of
Rachel E. Pelovitz, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
In All Fairness: Illinois Appellate Court Finds That Arbitration Clause in a Residential Construction Contract Was Unconscionable and Unenforceable
August 22, 2022 —
Gus Sara - The Subrogation StrategistIn Bain v. Airoom, LLC, No. 1-21-001, 2022 Ill. App. LEXIS 241, the Appellate Court of Illinois (Appellate Court) considered whether the lower court erred in enforcing an arbitration clause in a construction contract between the parties and, as a result, dismissing the plaintiff’s lawsuit. The Appellate Court found that even if the arbitration clause was enforceable, the appropriate action would have been for the court to stay the lawsuit, as opposed to dismissing the case entirely. The Appellate Court then considered the language of the arbitration clause and found that several provisions were substantively unconscionable, which rendered the entire arbitration clause unenforceable. The Appellate Court reversed the lower court’s decision compelling arbitration and reinstated the plaintiff’s complaint.
In 2018, the plaintiff, Ms. Bain, a disabled senior citizen, hired the defendant, Airoom, LLC (Airoom), to renovate her home. Airoom provided its “Cash Sales Contract,” which included a binding arbitration clause. The clause required that any dispute arising or relating to the contract be resolved by binding arbitration through the American Arbitration Association (AAA), using the Construction Industry Arbitration Rules and Mediation Procedures (Construction Industry Rules).
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
New California Standards Go into Effect July 1st
July 01, 2014 —
Beverley BevenFlorez-CDJ STAFFGarret Murai on his California Construction Law Blog reminded readers that the California Building Energy Efficiency Standards and the New Listing Law Requirements goes into effect on July 1st of this year.
According to Murai, the new “California Building Energy Efficiency Standards include: (1) the 2013 California Energy Code, Part 6, (2) the 2013 California Administrative Code, Chapter 10, Part 1 and (3) the energy provisions of the 2013 CALGreen, Part II, Title, 25, of the California Code of Regulations.”
Furthermore, Murai pointed out that “Assemby Bill 44, which amended the Subletting and Subcontracting Fair Practices Act, also known as the Listing Law, was signed into law,” which requires prime contractors "to disclose the contractors license numbers of subcontractors performing work in excess of 0.5% of the prime contractor’s total bid or, in the case of bids for the construction of streets, highways, or bridges, in excess of 0.5% of the prime contractor’s total bid or $10,000, whichever is greater.”
Read the court decisionRead the full story...Reprinted courtesy of
Superior Court Of Pennsylvania Holds Curb Construction Falls Within The Scope Of CASPA
September 17, 2014 —
Jerrold Anders & Michael Jervis – White and Williams LLPIn Prieto Corp. v. Gambone Construction Co., the Superior Court of Pennsylvania recently considered three issues arising out of a construction dispute, including whether construction of a curb falls within the scope of the Contractor and Subcontractor Payment Act (CASPA), 73 P.S. §§ 501-516. CASPA is a Pennsylvania statute which is intended to protect contractors and subcontractors from abuses in the building industry and which establishes certain rules and deadlines for payments between owners, contractors, and subcontractors. Failure to abide by the act’s payment requirements subjects an owner or contractor to liability for interest, penalties and attorneys fees. In this case, Prieto was a subcontractor hired by Gambone to construct concrete or Belgian block curbs at Gambone’s property developments. Prieto sued Gambone under CASPA for failure to pay its invoices for four projects. After the trial court entered judgment for Prieto, Gambone appealed, arguing that CASPA did not encompass the work at issue, i.e. the construction of curbs, because curbs did not constitute an improvement to real property.
Reprinted courtesy of
Jerrold Anders, White and Williams LLP and
Michael Jervis, White and Williams LLP
Mr. Anders may be contacted at andersj@whiteandwilliams.com; Mr. Jervis may be contacted at jervism@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to Las Vegas Partner Jeffrey W. Saab and Associate Shanna B. Carter on Obtaining Another Defense Award at Arbitration!
January 14, 2025 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPThe case arose from an incident at Plaintiff’s residence where she alleged that a failure to properly diagnose an issue with her HVAC unit led to its destruction, displacement from her home, and damage to her roof and kitchen, resulting in a diminution of value to her house. Jeff and Shanna represented the HVAC contractor, who denied any wrongdoing during the two-day arbitration at which a total of six witnesses were examined. Jeff and Shanna utilized Plaintiff’s own experts’ testimony to successfully challenge liability and bring forth a motion for spoliation, resulting in a complete defense award for Jeff and Shanna’s client, which included an award of costs.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
The Unthinkable Has Happened. How Should Contractors Respond?
May 11, 2020 —
Bruce Orr - AEC BusinessAny construction veteran expects the economy to contract and expand. However, the global pandemic presents contractors with a challenge unlike any in recent memory.
How should they respond in an environment of such uncertainty? For some perspective, I chatted with Dr. John Killingsworth, a construction management professor at Colorado State University who has conducted extensive research on how contractors can weather economic downturns.
BRUCE ORR: John, let’s say you’re in IT or are a c-suite executive at a contracting firm. This event has occurred. What are some of the questions you should be asking right now?
JOHN KILLINGSWORTH: For starters, we have to acknowledge that the uncertainties are so tremendous that many contractors have no choice but to be reactive in the short term. They’re literally not sure whether particular job sites will be open or closed tomorrow or whether they’ll go to work next week. They’re also looking at predictions—from highly qualified statisticians, public health officials and others—that are just all over the map due to the limited nature of the data we have at hand.
Read the court decisionRead the full story...Reprinted courtesy of
Bruce Orr, AEC BusinessMr. Orr may be contacted at
bruce@pronovos.com
Breach of Contract Exclusion Bars Coverage for Construction Defect Claim
March 19, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined the policy's breach of contract exclusion precluded coverage for a claim against the general contractor insured for construction defects. Mt. Hawley Ins. Co. v. McAtamncy, 2024 U.S. Dist. LEXIS 497 (N. D. Cal. Jan. 2, 2024).
McAtamney, a general contractor dong business as Kilrea Construction, was hired by Jeffrey Horowitz for a home-renovation project. After completion of the project, Horowitz discovered defects in the work. He filed a complaint alleging that Kilrea breached obligations to construct and complete the work in an expeditious and workmanlike manner, free from any faults and defects. He brought claims for breach of contract, breach of implied warranty, negligence, neglignet supervision, and declaratory relief.
Kilrea's insurer, Mt. Hawley, agreed to defend, but reserved the right to later deny coverage for any uncovered claims. The breach of contract exclusion provided there was no duty to defend a claim for property damage arising from breach of an express or implied contract or warranty.
Read the court decisionRead the full story...Reprinted courtesy of