Difficulty in Defending Rental Supplier’s Claim Under Credit Application
October 11, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn construction, one of the easiest claims to prove from a burden of proof standpoint is that of a supplier, particularly a rental equipment supplier. Oftentimes, these claims are more in the realm of a collection claim because a rental supplier will generally be able to establish that a party opened an account with them, signed a credit application and personal guaranty, and equipment was rented and even delivered to a specific jobsite during set dates. Defending these claims is not so easy. And even if there is a defense as it relates to some amounts, there needs to be an upside challenging those amounts when factoring in the attorney’s fees, costs, and interest on the other amounts and on continuing the dispute.
An example of the difficulty in defending these claims from rental suppliers can be found in the recent case of Custom Design Expo, Inc. v. Synergy Rents, Inc., 2021 WL 4125806 (Fla. 2d DCA 2021). Here, a contractor rented equipment (e.g, forklifts) from a supplier. The equipment was rented on an open account and the contractor signed a personal guaranty. The supplier sued the contractor for about $81,000 that remained unpaid. The supplier appeared to waste no time and moved for summary judgment with an affidavit from its credit manager. The credit manager affirmed that the contractor executed a credit application for purposes of renting equipment on an open account, the application contained a personal guaranty, and the credit application formed the basis of a contract. The credit manager authenticated the credit application and affirmed that the contractor owed it about $81,000 in unpaid amounts for rental equipment that was furnished under the credit application.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
What to do about California’s Defect-Ridden Board of Equalization Building
October 01, 2014 —
Beverley BevenFlorez-CDJ STAFFJerry Brown recently signed into law a bill requiring the state of California “to assess its properties in the Sacramento area and develop long-term plans for renovating, replacing or selling the most troublesome buildings,” according to SF Gate. Some say the Board of Equalization building, which was built for $80 million and then repaired for $60 million has construction defects, is “jeopardizing the health and safety of public employees.”
Current problems include “[f]looding, mold, falling windows and free-falling elevators,” reported SF Gate. Furthermore, recently, “three employees filed a $75 million lawsuit against the state, alleging toxic mold in the building is causing extreme fatigue, skin rashes, persistent flu-like symptoms, respiratory illnesses, frequent headaches, memory lapses and fears of cancer.”
“This is a disaster,” Assemblyman Roger Dickinson, D-Sacramento, who authored the bill regarding assessing state capitol buildings, told SF Gate. “It endangers the health and safety of employees and the public alike. And it is costing state taxpayers tens of millions of dollars.”
Read the court decisionRead the full story...Reprinted courtesy of
Another Smart Home Innovation: Remote HVAC Diagnostics
June 17, 2015 —
Beverley BevenFlorez-CDJ STAFFBuilder magazine reported that “smart home technology manufacturer Nexia Home Intelligence now offers monitoring of a home’s HVAC system even when owners are away. If an issue arises, it can be fixed quickly, sometimes without a service call, the company says.”
The service is available “with Trane and American Standard Wi-Fi-enabled thermostats” and requires a free Nexia account. System alerts are automatically transmitted to the dealer.
Read the court decisionRead the full story...Reprinted courtesy of
Manhattan Vacancies Rise in Epicenter Shift: Real Estate
August 20, 2014 —
David M. Levitt – BloombergThe luster is fading on some of midtown Manhattan’s shiniest skyscrapers.
Buildings in Midtown, from 30th Street to Central Park South at 59th Street, have more vacant blocks of contiguous office space than at the height of the recession in 2009, as landlords face increased competition from buildings downtown and at Hudson Yards on the far west side, according to a study by Savills Studley Inc., a New York-based real estate brokerage.
“The epicenter of this city has shifted several times before and is in the process of shifting again,” Michael Cohen, tri-state region president of brokerage Colliers International, said in an interview. Midtown is “the hole in the doughnut,” where landlords are vulnerable to extended vacancies and rents that probably won’t rise dramatically.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Levitt, BloombergMr. Levitt may be contacted at
dlevitt@bloomberg.net
Angelo Mozilo Speaks: No Regrets at Countrywide
September 03, 2014 —
Max Abelson – BloombergSix years after he lost control of the largest mortgage lender in the U.S., and days after news that the U.S. Attorney’s Office in Los Angeles plans to sue him, the Countrywide Financial Corp. founder is baffled by a new effort to punish him, proud of past triumphs and incensed by criticism.
“You’ll have to ask those people, ‘What do you have against Mozilo, what did he do?’” he said in a 30-minute call with Bloomberg News before Labor Day, one of his few interviews since the firm’s downfall. “Countrywide didn’t change. I didn’t change. The world changed.”
Interviews with Mozilo, 75, and three friends show what retirement looks like for a chief executive officer linked to the worst financial crisis since the Great Depression. Remaining out of public view like Lehman Brothers Holdings Inc.’s Richard Fuld or Jimmy Cayne of Bear Stearns Cos., Mozilo has submitted plans for Old West-style offices in California, taught students in Italy about finance, invested in a building in the Arizona desert that houses a Taco Bell and written about his life so that his grandchildren will “know the truth.”
Read the court decisionRead the full story...Reprinted courtesy of
Max Abelson, BloombergMr. Abelson may be contacted at
mabelson@bloomberg.net
Virginia Civil Engineers Give the State's Infrastructure a "C" Grade
December 13, 2022 —
American Society of Civil Engineers (ASCE)VIRGINIA BEACH, Va. — The Virginia Section of the American Society of Civil Engineers (ASCE) released the 2022 Report Card for Virginia's Infrastructure today, with 11 categories of infrastructure receiving an overall grade of a 'C'. That means Virginia's infrastructure is in mediocre condition and requires attention. Virginia is a step ahead of the national average of 'C-' given in the 2021 Report Card for America's Infrastructure. Nine of the 11 categories ranked higher than the national grades, as only rail ('C-' compared to the national 'B' grade) and wastewater (tied with the national grade of 'D+') ranked the same or lower, a testament to the state's prioritization of its built environment. Virginia has implemented ambitious plans to improve each of its infrastructure systems and additional resources from the state level and the bipartisan infrastructure law will help these efforts. Civil engineers graded bridges (B), dams (C+), drinking water (C+), public parks (C), rail (C-), roads (C-), schools (C-), solid waste (B-), stormwater (C-), transit (C-), and wastewater (D+).
Virginia's transportation sector has performed better than the national average. Roughly 3% of the state's bridges are in poor condition – less than half the national average of 7.5% -- and the percentage of roads in 'good' condition rose from 48% in 2018 to 51% in 2022. Virginia is also a regional leader in transit services with connection to the Washington, D.C. Metro system and with 41 transit systems across the state, some of which have already surpassed pre-pandemic ridership levels. However, wastewater systems, despite making progress by reducing sewage overflows, face more than $6 billion in needs over 20 years and will need significantly more resources to improve systems and protect water quality for communities and the natural environment.
The Report Card was created as a public service to citizens and policymakers to inform them of the infrastructure needs in their state. Civil engineers used their expertise and school report card-style letter grades to condense complicated data into an easy-to-understand analysis of Virginia's infrastructure network. ASCE State and Regional Infrastructure Report Cards are modeled after the national Infrastructure Report Card, which gave America's infrastructure an overall grade of 'C-' in 2021.
To view the report card and all five categories, visit https://infrastructurereportcard.org/state-item/Virginia/.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Arbitration: For Whom the Statute of Limitations Does Not Toll in Pennsylvania
June 03, 2019 —
Gus Sara - The Subrogation StrategistIn Morse v. Fisher Asset Management, LLC, 2019 Pa. Super. 78, the Superior Court of Pennsylvania considered whether the plaintiff’s action was stayed when the trial court dismissed the plaintiff’s complaint after sustaining the defendants’ preliminary objections seeking enforcement of an arbitration clause in the contract at issue. The Superior Court—distinguishing between a defendant who files a motion to compel arbitration and a defendant who files preliminary objections based on an arbitration clause—held that, in the latter scenario, if the defendant’s preliminary objections are sustained, the statute of limitations is not tolled. This case establishes that, in Pennsylvania, plaintiffs seeking to defeat a challenge to a lawsuit based on a purported agreement to arbitrate need to pay close attention to the type of motion the defendant files to defeat the plaintiff’s lawsuit.
In Morse, the plaintiff entered into a contract with Fisher Asset Management (Fisher) in 2008 for investment-advisor services. The contract included a provision stating that any dispute, claim or controversy arising out of the agreement between the parties shall be determined by arbitration. In June 2009, the plaintiff filed a complaint against Fisher and two of its employees in the Court of Common Pleas of Allegheny County, alleging breach of fiduciary duty, breach of contract, negligence, and other claims. The defendants filed preliminary objections to the complaint seeking dismissal on grounds that the contract between the plaintiff and Fisher required that the dispute be determined by arbitration. The court sustained the preliminary objections and dismissed the complaint. The plaintiff did not appeal the court’s ruling.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Beyond Inverse Condemnation in Wildfire Litigation: An Oregon Jury Finds Utility Liable for Negligence, Trespass and Nuisance
July 10, 2023 —
Marisa Miller, John Yacovelle & Kazim Naqvi - Sheppard MullinOn June 10, 2023, a jury in Portland, Oregon found PacifiCorp and Pacific Power (collectively, “PacifiCorp”) liable for negligence, trespass, and nuisance based on a series of four wildfires that occurred during Labor Day weekend in 2020. PacifiCorp prevailed against the plaintiffs on the claim of inverse condemnation. With respect to the tort-based claims, the jury awarded approximately $72 million in compensatory damages to 17 plaintiffs. The jury later found PacifiCorp liable for $18 million in punitive damages, or one quarter of the compensatory damages that the jury awarded to the 17 plaintiffs. The jury’s liability findings apply to a broader class of owners, whose damages will need to be individually proven in a yet-to-be defined second phase of proceedings. Post-verdict motion practice and appeals may affect the jury’s findings.
Reprinted courtesy of
Marisa Miller, Sheppard Mullin,
John Yacovelle, Sheppard Mullin and
Kazim Naqvi, Sheppard Mullin
Ms. Miller may be contacted at mmiller@sheppardmullin.com
Mr. Yacovelle may be contacted at jyacovelle@sheppardmullin.com
Mr. Naqvi may be contacted at knaqvi@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of