Insurer Fails to Establish Prejudice Due to Late Notice
October 17, 2022 —
Tred R. Eyerly - Insurance Law HawaiiSummary judgment awarded to the insurer was reversed because the insurer presented no evidence of prejudice caused by untimely notice. Perez v. Citizens Prop. Ins. Corp., 2022 Fla. App. LEXIS 5435 (Fla. Ct. App. Aug. 10, 2022).
The insureds' home suffered water damage due to Hurricane Irma around September 10, 2017. A claim was submitted to Citizens on November 27, 2018. Citizens had an independent adjuster inspect, but then denied the claim due to untimely notice.
The insureds sued and Citizens moved for summary judgment. Citizens argued it was prejudiced because it could not confirm the cause of the loss or the property damage attributed to it.
The court agreed that the insureds' notice was untimely. The insureds were notified by tenants renting the property that leaks appeared around the time of Hurriane Irma. The policy language, however, placed the burden to rebut the presumption of prejudice caused by late notice on Citizens. Whether the insurer was prejudiced was a question of fact. Citizens failed to demonstrate any prejudice due to the untimely notice.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Berkeley Researchers Look to Ancient Rome for Greener Concrete
June 28, 2013 —
CDJ STAFFWhile modern concrete often crumbles after fifty years, some concrete laid down during the Roman Empire is still strong, even after 2,000 years. Researchers at UC Berkeley have been puzzling over the secrets of Roman concrete, using samples from a breakwater near Naples. The breakwater was built about 37 BC, and the concrete is still strong. Unlike modern concrete, the Romans made theirs with a mixture of lime and volcanic ash.
Paulo Monteiro, a professor of civil and environmental engineering at Berkeley, noted that one of the drawbacks of Roman cement was that it hardens more slowly than modern concrete. An advantage is that it is more environmentally friendly, and the researchers are trying to determine if volcanic ash cement would be a good substitute. Professor Montiero hopes that fly ash and volcanic ash cements “could replace 40 percent of the world’s demand for Portland cement.”
Read the court decisionRead the full story...Reprinted courtesy of
GSA Releases Updated Standards to Accelerate Federal Buildings Toward Zero Emissions
August 12, 2024 —
The U.S. General Services AdministrationWASHINGTON — The U.S. General Services Administration (GSA) is advancing progress toward the Biden-Harris Administration's federal sustainability goals by releasing updated standards for federal buildings. P100 Facilities Standards for the Public Buildings Service establish mandatory design and construction standards and performance criteria for 300,000 federal buildings nationwide. The updated standards will help advance the adoption of cleaner, more efficient technologies for buildings; lead the way towards realizing the goals of the Federal Sustainability Plan to achieve net-zero emissions from all federal buildings by 2045; and promote the use of American-made, low carbon construction materials.
P100 requires that facilities adopt advanced energy conservation strategies and eliminate on-site fossil fuel use, directives that align with federal sustainability goals and will accelerate the transition to a clean energy economy. The industry-leading standard calls for grid-interactive efficient buildings, leverages innovative technologies through GSA's Green Proving Ground, requires the use of low-embodied carbon materials, and directs potable water reuse. These comprehensive measures ensure that new and renovated federal facilities achieve peak performance while minimizing environmental impact.
The 2024 P100 establishes exceptional benchmarks for:
- Electrification: New standards for building equipment and systems to be powered by clean energy sources.
- Embodied Carbon: Requirement to utilize low-embodied carbon materials, including salvaged, reused, regenerative, and biomimetic options.
- Energy Efficiency: Enhanced building envelope performance to minimize energy loss and improve overall efficiency.
- Grid-Interactive Efficient Buildings: New measures to support a more resilient, responsive grid.
- Water Reuse: Mandating that buildings have a 15% potable water reuse rate.
- Construction Decarbonization: Ground breaking new low-carbon methods for constructing federal buildings including clean energy operations, material salvage, and offsite assemblage.
- Labor Practices: New standards protecting workers from unfair or unsafe labor practices, ensuring supply chains are free from child and forced labor and that workers are protected from the impacts of extreme heat.
P100 is updated and published every three years. For more detailed information on the 2024 P100 and other GSA initiatives, visit www.gsa.gov/p100.
Read the court decisionRead the full story...Reprinted courtesy of
Covenant of Good Faith and Fair Dealing Applied to Pass-Through Agreements
June 19, 2023 —
Scott D. Cessar - Construction ExecutivePass-through claims are claims by a party that has suffered damages but does not have a contractual relationship with the entity that caused the damages. In the construction industry, subcontractors commonly have claims for additional costs based on actions or inactions by the owner. However, since the subcontractor is not in privity of contract with the owner, it has no direct cause of action against the owner other than, perhaps, on a nongovernment project, a lien claim. In such cases, subcontractors may seek to pass the claim through the general contractor, who is in privity with the owner, to the owner.
Indeed, many construction contracts require the subcontractor, in such cases of owner-caused damages, to pass the claim through the general contractor to the owner. And since the harm visited on a subcontractor by the owner usually also affected the general contractor, the subcontractor’s claim is packaged together with the general contractor’s claim, which is usually greater, for presentation to the owner and, if not resolved, litigation with the owner.
Reprinted courtesy of
Scott D. Cessar, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Late Notice Defense Fails on Summary Judgment
December 13, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion for summary judgment to dismiss the claim because the insurer did not provide notice "as soon as practicable" was denied. Vintage Hospitality Group LLC v. Nat'l Trust Ins. Co., 2021 U.S. Dist. LEXIS 192651 (M.D. Ga. Oct. 6, 2021).
Vintage owned hotels, one of which was struck by a severe hailstorm on July 21, 2018. Vintage was not aware of roof damage until two months after the storm, and did not make the connection between the hailstorm and roof damage until February 2020, when it reported the damage to National. The claim was denied because it was not reported "as soon as practicable" as required by the policy.
Vintage sued and National moved for summary judgment.
Vintage did not notice the leaks until September 2018. The focus was on fixing the leaks, and connection to the hailstorm did not register. The leaks persisted over the next year and a half. A construction company was called in to evaluate the leaking roof. The construction company advised that the roof had experienced previous hail damage which was causing the leaks. At this point, Vintage connected the damage to the hailstorm. A claim was promptly submitted to National, which denied the claim.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Contract Void Ab Initio: Key Insights into the KBR vs. Corps of Engineers Affirmative Defense
February 12, 2024 —
Matthew DeVries - Best Practices Construction LawIn a recent Board decision dated December 13, 2023, the United States Army Corps of Engineers sought to amend its answer in the case of APPEALS OF – KELLOGG BROWN & ROOT SERVICES, INC., under Contract No. W912GB-13-C-0011. The proposed amendment introduces an affirmative defense, contending that Kellogg Brown & Root Services, Inc. (KBR) made material misrepresentations in its proposal, rendering the fully-performed contract void ab initio.
Background: The contract in question, executed on July 9, 2013, was for the construction of an Aegis Ashore Missile Defense System site in Deveselu, Romania, with a firm, fixed-price amount of $134,211,592. The Corps moved to amend its answer to allege that KBR’s material misrepresentations induced the Corps to enter the contract, justifying the voiding of the contract. The alleged misrepresentations include issues related to subcontractor quotes, firm fixed prices, subcontracting plans, and more.
Motion to Amend and Legal Defense: The Corps, despite delays in formally amending its answer, argued that KBR was aware of the potential affirmative defense before the conclusion of fact discovery. The proposed affirmative defense asserts that KBR made eight material misrepresentations in its proposal, upon which the Corps relied in awarding the contract and defending against a GAO protest.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, Burr & Forman LLPMr. DeVries may be contacted at
mdevries@burr.com
First-Time Buyers Shut Out of Expanding U.S. Home Supply
August 13, 2014 —
Prashant Gopal – BloombergThe four-bedroom house that Ilia Nielsen-Dembe purchased in west Denver earlier this year wasn’t her top choice. The first-time buyer had to settle on a home in a neighborhood with a high crime rate after losing out on bids for five properties in more desirable areas.
“I definitely sacrificed in terms of location,” said Nielsen-Dembe, 33, who lives with her husband and two daughters in the house she bought in April for $184,500. “I had to cross streets that were not ideal in order to get a house.”
While the supply of U.S. homes for sale is at an almost two-year high and price gains are moderating, buyers such as Nielsen-Dembe wouldn’t know it. An inventory crunch for entry-level houses has only worsened during the past year as discounted foreclosures become scarce and cash-paying investors snap up affordable listings to convert to rentals. Properties at the lower end of the market are also the most likely to have underwater mortgages, keeping would-be sellers from moving.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
Attorneys Fees Under California’s Prompt Payment Statutes. Contractor’s “Win” Fails the Sniff Test
October 02, 2015 —
Roger Hughes – California Construction Law BlogThis past month, the California Court of Appeals for the Third District, in James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc., Case No. C072169 (August 27, 2015), handed down a decision in a construction contract battle that has raged since 2007. And, once again, the winner is . . . in the words of Justice Andrea Lynn Hoch who authored the opinion . . . . “no prevailing party in [the] case” and hence “no prevailing party attorney’s fees [ ] awarded.”
Background
In Harris, subcontractor James L. Harris Painting & Decorating, Inc. (“Harris”) sued general contractor West Bay Builders, Inc. (“West Bay”) for extra work performed on a school construction project in Stockton, California. Among its claims, Harris asserted that West Bay was liable under California’s prompt payment statutes for failure to timely pay Harris.
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at