Be Proactive, Not Reactive, To Preserve Force Majeure Rights Regarding The Coronavirus
March 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesIf you are involved in construction, NOW is the time to consider the potential force majeure impacts associated with the pandemic Coronavirus. Things are beginning to drastically change on a minute-by-minute basis. From travel restrictions, to the suspension or cancellation of events on an international level, to company-wide policies and restrictions, the global uncertainty has led to the possibility that a force majeure delay will occur. Thinking otherwise is not being proactive. The Coronavirus, and the impacts / delays associated therewith, is beyond anyone’s control. Due to the uncertainty, it is hard to fathom at this time a reasonable challenge to someone’s reaction to this concern or their companywide response to the concern.
If you are a contractor, subcontractor, or even a supplier, my suggestions would be as follows:
- Revisit your contracts and see what type of force majeure language it has – anything relating to delays beyond your control or epidemics;
- Examine to see whether you have a basis for additional compensation AND additional time;
- Examine what type of notice you are required to provide for force majeure events;
- Be proactive – send notice now of the potentiality that this pandemic can impact / delay the job –no one should take offense to this letter as this pandemic has impacted all walks of life;
- If an impact occurs, send follow-up notice accordingly to ensure rights under the contract are preserved; and
- For future contracts, incorporate language that specifically addresses epidemics and pandemics now that the occurrence of this issue has become real.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Are COVID-19 Claims Covered by Builders Risk Insurance Policies?
May 04, 2020 —
Jason M. Adams, Gibbs Giden Locher Turner Senet & Wittbrodt LLP and Cheryl L. Kozdrey, Saxe Doernberger & Vita, P.C.If you are an attorney, insurance broker, or other professional representing developers and contractors, then your clients have likely reached out with concerns about losses related to COVID-19. One common question is whether there is potential coverage under builders risk insurance policies.
The short answer is: It depends. As with most questions pertaining to insurance coverage, the answers depend on the specific policy language and underlying facts required to trigger coverage. Builders risk policies are even more fact specific due to the lack of uniformity of base policy forms and endorsements between insurance carriers.
The first step in any analysis is to gather facts and carefully document any impending and potential damages or delays. The facts are crucial because the coverage analysis may vary depending on the specific reason the project was shut down. For example, the analysis would be different if the project was shut down as a result of an express government order, such as those in Northern California and Washington, versus the project shutting down as a result of workers testing positive for COVID-19. Properly analyzing builders risk coverage involves a granular account of the facts and damages, and can require a great deal of hair splitting with respect to specific policy language.
Regardless of the strength of the insured’s facts and damages, or the breadth of its policy language, the policyholder still likely faces an uphill battle in finding coverage for COVID-19 related claims. The unfortunate reality of most builders risk policies is that they are property policies that require some evidence of physical loss or damage to trigger coverage. Whether or not COVID-19 claims constitute property damage will be the subject of great debate and litigation over the coming months and years. The outcome will likely depend on how the insured’s jurisdiction ultimately rules on the litany of COVID-19 cases that have already been filed – specifically, how broadly each court interprets the meaning of “physical loss or damage.”
Although these key issues have yet to be clearly defined by the courts, some policies are better than others and there are specific variables that could affect the likelihood of coverage. For example, some of the more policyholder-friendly insurance programs may contain coverage extensions for delay in completion, business interruption, loss of rental income, or civil authority that may not be tied to the property damage requirement, and which would tend to support coverage for COVID-19 claims.
Even if the insured crosses the initial threshold and can demonstrate a covered claim, the following common endorsements and exclusions may require additional analysis depending on the facts.
- Virus or Pandemic Exclusions: Virus or pandemic exclusions are not as common on builders risk policies as they may be on other forms of coverage. However, they do exist and, if present, result in a significant barrier to coverage. As with the policy itself, every endorsement is different and should be analyzed in terms of the express language contained in the endorsement and the facts.
- Abandonment or Cessation of Work: Most builders risk policies include provisions that preclude coverage in the event of the abandonment of the project or a lengthy cessation of work. As a result, the insured should take steps to articulate to the carrier that the project has not been abandoned, and that there exists an intent to return as soon as possible. The insured should also maintain a record of ongoing project oversight and protection efforts taken during the period when construction operations are suspended.
- Security and Safety Requirements: Many builders risk policies contain provisions requiring the insured to maintain protective safeguards and security protocols throughout the pendency of the project. Safety fencing, lighting and security guards are common examples. The policy should be analyzed to ensure that the policyholder can meet any such requirements during a COVID-19 related shutdown. For example, can the insured continue to staff a security guard? If not, arrangements will likely need to be made with the carrier depending on the language of the policy.
- Insurable Limits: Builders risk policies are typically underwritten based upon the total completed value of the structure, including materials and labor. The insured will need to analyze the policy to consider whether increased material or labor costs as a result of COVID-19 will alter the terms of coverage, trigger any escalation clauses, or result in an increase in premium due. If increased cost projections become apparent, the insured should report these changes to the carrier immediately.
- Extensions of Coverage: The insurance industry was facing a hard market even before the COVID-19 pandemic, which resulted in higher premiums and limited coverage options. The COVID-19 pandemic has only exacerbated these issues and it may be difficult to obtain coverage extensions on projects that have been shut down. The insured should work with its risk management team (risk manager, insurance broker and lawyer) to engage the carriers to negotiate any necessary coverage extensions resulting from COVID-19 related project delays.
To summarize, builders risk coverage for COVID-19 claims is far from certain, but not impossible. Insureds should provide notice of a claim to all potentially applicable carriers in order to preserve their rights. The insured should also report increased construction cost and articulate its intent to return to the project to preserve their escalation clause and avoid arguments that they have abandoned the project. The insured should continue to document its claims and damages, and be ready to substantiate its claims and push back on any coverage denial. Throughout the entirety of this process, the insured should work with its risk management team to get out in front of any extensions it may need to complete the project. In a climate where insurance carriers are receiving an insurmountable number of claims, the insured should be prepared to fight for coverage and not simply throw up its hands in the face of a denial. Given the intense social, legislative and executive pressure to cover COVID-19 claims, there may be a tendency for the courts to find coverage in gray areas, particularly if the insured was fortunate enough to have purchased one of the broader coverage forms referenced above.
About the Authors
Jason M. Adams, Esq. (jadams@gibbsgiden.com) is a partner at Gibbs Giden representing construction professionals in the areas of Construction Law, Insurance Law and Risk Management and Business/Civil Litigation. Adams is also a licensed property and casualty insurance broker and certified Construction Risk & Insurance Specialist (CRIS). Jason represents developers, contractors, public entities, investors, lenders, REITs, design professionals, and other construction professionals at all stages of the construction process. Jason is a published author and sought-after speaker at seminars across the country regarding high level construction risk management and insurance topics. Gibbs Giden is nationally and locally recognized by U. S. News and Best Lawyers as among the “Best Law Firms” in both Construction Law and Construction Litigation. Chambers USA Directory of Leading Lawyers has consistently recognized Gibbs Giden as among California’s elite construction law firms.
Cheryl L. Kozdrey, Esq. (clk@sdvlaw.com) is an associate at Saxe Doernberger & Vita, P.C., a national insurance coverage law firm dedicated exclusively to policyholder representation and advocacy. Cheryl advises insurance brokers, risk managers, and construction industry professionals regarding optimal risk transfer strategies and insurance solutions, including key considerations for Builder’s Risk, Commercial General Liability, D&O, and Commercial Property policies. She assists clients with initial policy reviews, as well as renewals and modification(s) of existing policies to ensure coverage needs are satisfied. Cheryl also represents policyholders throughout the claims process, and in coverage dispute litigation against insurance carriers. She is currently working on some of the largest construction defect cases in the country. Cheryl is a published author and is admitted to practice in the State of California and all federal district courts within the State.
Read the court decisionRead the full story...Reprinted courtesy of
Heavy Rains Cause Flooding, Mudslides in Japan
July 31, 2023 —
Associated Press - BloombergTOKYO (AP) — Torrential rain pounded southwestern Japan, triggering floods and mudslides and leaving two people dead and at least six others missing, officials said Monday.
Rain falling in the regions of Kyushu and Chugoku since the weekend caused flooding along many rivers, triggered mudslides, closed roads, disrupted trains and cut the water supply in some areas.
The Japan Meteorological Agency issued an emergency heavy rain warning for Fukuoka and Oita prefectures on the southern main island of Kyushu, urging residents in riverside and hillside areas to take maximum caution. More than 1.7 million residents in vulnerable areas were urged to take shelter. The emergency warning was downgraded later Monday to a regular warning.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Beyond the Statute: How the Colorado Court Upheld Modified Accrual in Construction Contracts
November 13, 2023 —
Hal Baker - Colorado Construction Litigation BlogIn a case of first impression, the First Division of the Colorado Court of Appeals recently reviewed whether parties may contractually alter the accrual time established by Colorado’s statute of limitations for construction defect actions, C.R.S. § 13-80-104, in South Conejos Sch. Dist. RE-10 v. Wold Architects, Inc., 2023 COA 85 (2023), decided on September 21, 2023. The Court held that sophisticated parties may contractually alter the accrual time standards, enlarging the accrual time as was the issue in this case. Notably, the Court’s decision was made in the context of commercial construction, not residential.
The issue in South Conejos Sch. Dist. RE-10 arose from the construction of a school in Antonito, Colorado. Prior to construction, the South Conejos School District RE-10 (the “School District”) and Wold Architects, Inc. (“Wold”) entered a contract that provided:
Unless a longer period is provided by law, any action against [Wold] brought to recover damages for deficiency in the design, planning, supervision, inspection, construction or observation of construction or for injury to person or property shall be brought within two years after the claim for relief arises and is discovered by [the District]; … “Discovered” as used herein means detection and knowledge by [the District] of the defect in the improvement that ultimately causes the injury, when such defect is of a substantial or significant nature.
Read the court decisionRead the full story...Reprinted courtesy of
Hal Baker, Higgins, Hopkins, McLain & Roswell, LLCMr. Baker may be contacted at
baker@hhmrlaw.com
3D Printing: A New Era in Concrete Construction
April 11, 2022 —
Zoey Zhao - Construction ExecutiveThe construction of buildings using concrete has been around since the time of the Romans. In all those centuries, concrete structures have been built using essentially the same method: forms, reinforcement, mixing, pouring, setting, repeat.
The process is costly and time-consuming. The construction of the forms alone demands dozens of workers and requires a substantial amount of lumber, keeping labor and materials costs high. Builders might save some time using prefabricated concrete blocks, but such materials are not appropriate for every construction project and carry their own expenses.
For the first time in history, builders have an alternative to traditional concrete construction methods that are more cost-effective, less expensive, more environmentally friendly and allow for a wide range of possible construction projects. Three-dimensional concrete printing for construction has emerged in the building field as a viable and efficient alternative.
Reprinted courtesy of
Zoey Zhao, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Zhao may be contacted at
zoey@aictbuild.com
Liability Insurer Precluded from Intervening in Insured’s Lawsuit
September 17, 2018 —
David Adelstein - Florida Construction Legal UpdatesThere are cases where I honestly do no fully understand the insurer’s position because it cannot have its cake and eat it too. The recent opinion in Houston Specialty Insurance Company v. Vaughn, 43 Fla. L. Weekly D1828a (Fla. 2d DCA 2018) is one of those cases because on one hand it tried hard to disclaim coverage and on the other hand tried to intervene in the underlying suit where it was not a named party.
This case dealt with a personal injury dispute where a laborer for a pressure washing company fell off of a roof and became a paraplegic. The injured person sued the pressure washing company and its representatives. The company and representatives tendered the case to its general liability insurer and the insurer–although it provided a defense under a reservation of rights—filed a separate action for declaratory relief based on an exclusion in the general liability policy that excluded coverage for the pressure washing company’s employees (because the general liability policy is not a workers compensation policy). This is known as the employer’s liability exclusion that excludes coverage for bodily injury to an employee. The insurer’s declaratory relief action sought a declaration that there was no coverage because the injured laborer was an employee of the pressure washing company. The pressure washing company claimed he was an independent contractor, in which the policy did provide limited coverage pursuant to an endorsement.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
City of Pawtucket Considering Forensic Investigation of Tower
October 08, 2014 —
Beverley BevenFlorez-CDJ STAFFPawtucket, Rhode Island’s mayor, Donald Grebien, has asked their city council to approve “a forensic investigation of the Pawtucket City Hall tower to determine whether the city should sue the contractor that repaired it eight years ago,” the Valley Breeze reported.
Back in 2011, “city officials had been unable to locate a signed contract for the tower project as they sought to hold NER responsible for continued leaking into the structure just five years after the company's $3 million renovation project was complete,” according to the Valley Breeze. “The costs of that project grew to $4.6 million once interest was factored in.”
Documents have recently been discovered that Grebien believes may open the possibility to sue NER.
Read the court decisionRead the full story...Reprinted courtesy of
Policing Those Subcontractors: It Might Take Extra Effort To Be An Additional Insured
June 14, 2011 —
Douglas Reiser, Builders Council BlogI just came across a case that I think truly paints the insurance dilemma for contractors. Thanks to this recent Illinois case, I don’t have to make up any factual scenarios—so kudos to Attorney Robert Boylan for posting it.
In reading over my RSS feeds this weekend, I noticed a great writeup on long-time blogger Josh Glazov’s Construction Law Today. Attorney Robert Boylan’s post describes a recent Illinois case where a general contractor was denied its additional insured status on a second-tier subcontractor’s insurance. The reason for the denial: the general contractor failed to procure an agreement in writing with the second-tier subcontractor, requiring it to be listed as an additional insured.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of