David A. Frenznick Awarded Multiple Accolades in the 2020 Edition of The Best Lawyers in America
September 23, 2019 —
David A. Frenznick - Wilke FleuryWilke Fleury congratulates attorney David A. Frenznick on his inclusion in the 26th Edition of The Best Lawyers in America© for his work in: Litigation – Real Estate!
In addition, David was also acknowledged as a 2020 “Lawyer of the Year” award recipient. He received this accolade for his work in Litigation – Real Estate in Sacramento. Only a single lawyer in each practice area and community is honored with a “Lawyer of the Year” award.
Since it was first published in 1983, Best Lawyers® has become universally regarded as the definitive guide to legal excellence. Best Lawyers lists are compiled based on an exhaustive peer-review evaluation. Almost 94,000 industry leading lawyers are eligible to vote (from around the world), and have received over 11 million evaluations on the legal abilities of other lawyers based on their specific practice areas around the world. For the 2020 Edition of The Best Lawyers in America©, 8.3 million votes were analyzed, which resulted in more than 62,000 leading lawyers being included in the new edition. Lawyers are not required or allowed to pay a fee to be listed; therefore inclusion in Best Lawyers is considered a singular honor. Corporate Counsel magazine has called Best Lawyers “the most respected referral list of attorneys in practice.”
Read the court decisionRead the full story...Reprinted courtesy of
David A. Frenznick, Wilke FleuryMr. Frenznick may be contacted at
dfrenznick@wilkefleury.com
Canadian Developer Faces Charges After Massive Fire on Construction Site
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFA fire leveled an apartment construction site in Canada last December, which resulted in almost two dozen charges relating to fire safety precautions and lack of cooperation with the Ministry of Labour’s investigation, according to CKWS TV. The Ministry of Labour has recently “laid 22 charges against three individuals and two companies—Jay Patry Enterprises Inc. and Steimach Property Management Inc.”
CKWS TV reported that “[c]harges include failing to provide adequate space for workers to evacuate during an emergency, failing to protect the health and safety of workers and failing to inspect every fire extinguisher for defects or deterioration.” Jason Patry, Nathan Patry and Troy Stelmach have been charged with “obstructing and providing false information to a ministry of labour inspector, as well as failing to make the inspection process an easy one.”
Read the court decisionRead the full story...Reprinted courtesy of
Lump Sum Subcontract? Perhaps Not.
August 20, 2019 —
David Adelstein - Florida Construction Legal UpdatesLump sum subcontract? Perhaps not due to a recent ruling where the trial court said “No!” based on the language in the subcontract and contract documents generally incorporated into the subcontract.
This is a ruling on an interpretation of a subcontract and contract documents incorporated into the subcontract that I do not agree with and struggle to fully comprehend. The issue was whether the subcontract amount was a lump sum or subject to an audit, adjustment, and definitization based on actual costs incurred. Of course, the subcontractor (or any person in any business) is not just interested in recouping actual costs, but there needs to be a margin to cover profit and home office overhead that does not get factored into field general conditions.
In United States v. Travelers Casualty and Surety Company, 2018 WL 6571234 (M.D.Fla. 2018), a prime contractor was hired to perform work on a federal project. During the work, the Government issued the prime contractor a Modification that had a not-to-exceed value and required the prime contractor to track its costs for this Modification separate from other contract costs. In other words, based on this Modification, the prime contractor was paid its costs up to a maximum amount and the prime contractor would separately cost-code and track the costs for this work differently than other work it was performing under the prime contract.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Homeowner Protection Act of 2007 Not Just for Individual Homeowners Anymore?
March 22, 2017 —
Maggie Stewart - Colorado Construction Litigation On March 9, 2017, the Colorado Court of Appeals announced its decision in Broomfield Senior Living Owner, LLC v. R.G. Brinkmann Company, No. 16CA0101, 2017 COA 31 (Colo. App. Mar. 9, 2017). As a matter of first impression, the Court evaluated whether a senior living facility constitutes “residential property” protected by the Homeowner Protection Act of 2007 ("HPA") provision of the Construction Defect Reform Act (CDARA).
In 2007, Plaintiff Broomfield entered into a contract with Defendant Brinkmann for construction of a senior assisted and independent living facility. The contract contained warranty provisions related to the quality of construction and cautioned that Plaintiff’s failure to provide Defendant with prompt notice of any defects would result in waiver of any claim for breach. The contract also limited Defendant Brinkmann’s liability by identifying three separate accrual provisions that would determine the time period in which Plaintiff could bring a claim. The project was completed in 2009.
Read the court decisionRead the full story...Reprinted courtesy of
Maggie Stewart, Higgins, Hopkins, McLain & Roswell, LLCMs. Stewart may be contacted at
stewart@hhmrlaw.com
Damp Weather Not Good for Wood
May 10, 2013 —
CDJ STAFFCold and wet weather was not bad news for the lumber industry. The weather in the first quarter set or tied records for both precipitation and low temperatures. Not good weather for building. Construction was delayed as a result, leading to less call for lumber.
In response, there was a 15 percent drop in lumber futures, continuing a decline.
Read the court decisionRead the full story...Reprinted courtesy of
Miller Law Firm Helped HOA Recover for Construction Defects without Filing a Lawsuit
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to a press release published on the PR Newswire, The Miller Law Firm “recovered $910,000 for the 1635 California Owners' Association for construction defects without ever filing a complaint.” William Nagle, Special Master & Mediator, facilitated the settlement “a year after putting the builder on notice under SB 800, California’s Right to Repair Law.”
“Independent forensic expert inspections revealed building standard violations ranging from improperly installed gutters resulting in water intrusion in the units project wide, active leaks, standing water and inadequate gutters resulting in staining and efflorescence on the garage walls, balcony, and tile grout, discoloration and extensive cracking in the stucco project wide, inadequate weather stripping with evidence of condensation staining at windows, window frames and adjacent paint, inadequate ventilation, and ADA violations including loose glass guardrails and in regards to accessible rooftop common areas,” according to the press release.
“This case settled prior to any formal mediation and I credit the diligence of both the Association and builder counsel,” Nagle stated. “Tom Miller is one of the most knowledgeable and respected plaintiffs' lawyers in the construction defect area. And I compliment both counsel on their preparation and cost-effective handling of the case in reaching a fair and reasonable result for their respective clients."
Read the court decisionRead the full story...Reprinted courtesy of
How Small Mistakes Can Have Serious Consequences Under California's Contractor Licensing Laws.
February 15, 2018 —
Eric Reed - Myers, Widders, Gibson, Jones & Feingold, LLPIn construction, some risks have nothing to do with how well a contractor executes a project. Licensing problems is one of these risks. Even a brief lapse caused by an unintentional administrative error can give the CSLB grounds to discipline a contractor, or enable a customer to seek disgorgement and other remedies provided by Business and Professions Code section 7031. This article discusses five tips for mitigating the liabilities associated with licensing problems.
Tip 1: Take workers' compensation insurance very seriously. Workers’ compensation insurance problems can trigger license suspension in California. Business and Professions Code section 7125.4 calls for automatic suspension if a contractor cannot provide proof of workers’ compensation insurance for any period of time. This is particularly serious for residential remodelers who claim exemption for workers’ compensation but are later discovered – usually during litigation with a homeowner – to have “off the books” workers helping them. Courts can declare the contractor retroactively unlicensed under these circumstances and order it to disgorge,
i.e., to pay back, every penny paid by the customer for the entire project (even for materials). (Bus. & Prof. Code, § 7031, subd. (b);
Wright v. Issak (2007) 149 Cal.App.4th 1116.) The contractor will also find itself unable to collect any amounts owed to it by the customer. (Bus. & Prof. Code, § 7031, subd. (a).)
Tip 2: Watch out for licensing confusion after a merger or acquisition. The economic downturn of 2008 and 2009 resulted in consolidation throughout the building industry. The newly merged or acquired entities often allowed redundant licenses to expire, assuming they could complete all pending projects under the umbrella of the acquiring company's license. Many learned this was a mistake the hard way. Armed with the California Supreme Court's opinion in
MW Erectors, Inc. v. Niederhauser Ornamental & Metal Works Co., Inc. (2005) 36 Cal.4th 412, customers began refusing to pay invoices and demanding disgorgement under Business and Professions Code section 7031 because the original contractor did not maintain licensure “at all times.” Many of these customers succeeded.
Tip 3: If a license suspension has occurred or is imminent, prepare to prove substantial compliance. Section 7031(a) and (b) give a disgruntled or indebted customer every incentive to capitalize on a contractor's licensing problems. Subdivision (e) is where a contractor must turn to protect its interests if this happens. It allows the contractor to prove “substantial compliance” with licensing requirements and avoid (a)’s and (b)’s sharp edges if it can show the following:
(1) The contractor “had been duly licensed as a contractor in this state prior to the performance of the act or contract”;
(2) It “acted reasonably and in good faith to maintain proper licensure”; and
(3) It “acted promptly and in good faith to remedy the failure to comply with the licensure requirements upon learning of the failure.”
The Court of Appeal confirmed in
Judicial Council of California v. Jacobs Facilities, Inc. (2015) 239 Cal.App.4th 882 that a contractor, upon request, is entitled to a hearing on these three factors before it is subjected to disgorgement under Section 7031(b). The legislature amended Section 7031 shortly after the Court of Appeal published this case. The Assembly’s floor analysis went so far as to directly quote the opinion’s observation that penalizing a construction firm for “technical transgressions only indirectly serves the Contractors Law’s larger purpose of preventing the delivery of services by unqualified contractors.” (Assem. Com. on Bus. and Prof., Off. of Assem. Floor Analyses, analysis of Sen. Holden's No. 1793 (2015-2016 Reg. Sess.) as amended August 2, 2016, p. 2.) This echoed an industry consensus that clarifying the law was needed to ensure that properly licensed and law-abiding construction firms were not “placed at fatal monetary risk by malicious lawsuits motivated by personal gain rather than consumer protection.” (Assem. Com. on Judiciary, com. on Assem. Bill No. 1793 (2015-2016 Reg. Sess.), pp. 6-7.)
Unfortunately, existing law does not give many examples of what it means to act “reasonably and in good faith to maintain proper licensure” or to act “promptly and in good faith” to fix license problems. A practical approach is for a contractor to work backwards by assuming it will need to prove substantial compliance at some point in the future. Designated individuals within the organization should have clear responsibility over obtaining and renewing the proper licenses and should keep good records. If necessary, these designees can testify about the contractor's internal policies and their efforts to fix licensing problems when they arose. For example, if the suspension resulted from not providing the CSLB proof of workers’ compensation insurance, the designee can testify about the cause (a broker miscommunication, transmission error,
etc.) and produce documents showing how he or she worked promptly to procure a certificate of insurance to send CSLB. Saved letters, emails, and notes from telephone calls will provide designees and their successors with an important resource months or years down the line if a dispute arises and the contractor is required to reconstruct the chronology of a licensing glitch and prove its due diligence.
Tip 4: Don't sign new contracts unless all necessary licenses are active and any problems are resolved. A recently-formed contractor should not begin soliciting and signing contracts until all required licenses are confirmed as “active.” The first requirement of substantial compliance – being “duly licensed as a contractor in this state prior to the performance of the act or contract” – cannot be met by a contractor that first obtains its license mid-project. (Bus. & Prof. Code, § 7031, subd. (e)(1);
Alatriste v. Cesar’s Exterior Designs (2010) 183 Cal.App.4th 656.) A licensed contractor should also consider refraining from signing new contracts if there is any reason to believe its license might be suspended in the near future – especially if the suspension will be retroactive. Having a suspension on record at the time of contracting may complicate the question of whether the contractor was “duly licensed . . . prior to performance” for the purposes of substantial compliance.
Tip 5: Any judgment against a contractor can cause license suspension if not handled promptly and correctly. The Business and Professions Code authorizes the CSLB to suspend the license of a contractor that does not pay a construction related court judgment within 90 days. The term “construction related” is interpreted to include nearly all types of disputes involving a contractor. (16 Cal. Code Reg. 868;
Pacific Caisson & Shoring, Inc. v. Bernards Bros. Inc. (2015) 236 Cal.App.4th 1246, 1254-1255.) This means a contractor should treat a judgment against it for unpaid office rent, for example, as one carrying the same consequences as one arising from a construction defect or subcontractor claim. The contractor should also not assume that filing an appeal, or agreeing with the other side to stay enforcement, automatically excuses the 90-day deadline in the eyes of the CSLB. It does not. A contractor must notify the CSLB in writing before this period expires, then post bond for the amount of judgment, if it wishes to delay payment for any reason. (Bus. & Prof. Code, § 7071.17, subd. (d).) A suspension may result if it does not. This applies even to small claims judgments.
Recent case law and the 2016 amendments to Business and Professions Code section 7031 provide some solace to those caught in the dragnet of California's licensing laws. But avoiding these problems altogether is preferable. Consider licensing the foundation of a successful business and deserving of the same attention as the structures a contractor builds.
Eric R. Reed is a business and insurance litigator in the Ventura office of Myers, Widders, Gibson, Jones & Feingold, LLP.
Read the court decisionRead the full story...Reprinted courtesy of
Eric Reed, Myers, Widders, Gibson, Jones & Feingold, LLPMr. Reed may be contacted at
ereed@mwgjlaw.com
Fifth Circuit Rules that Settlements in Underlying Action Constitute "Other Insurance"
April 17, 2019 —
Tiffany Casanova - Saxe Doernberger & Vita, P.C.The Fifth Circuit ruled that settlements between an insured and its subcontractors qualified as “other insurance” to the extent those settlements were used to pay for damages covered by an excess insurance policy. Policyholders should note the outcome of this case as it demonstrates the significant impact that settlements can have on coverage.
Satterfield & Pontikes Construction, Inc. v. Amerisure Mutual Ins. Co.1 was the result of a construction project gone wrong. Zapata County, Texas hired Satterfield & Pontikes (“S&P”) as a general contractor for the construction of a courthouse building. When the project did not go as planned, Zapata County terminated S&P, hired new subcontractors to complete the project, and sued S&P.
S&P, in turn, sought indemnification from its subcontractors, who were contractually obligated to indemnify S&P and procure insurance for any damage the subcontractors caused at the project. S&P also sought coverage from its own primary insurers, American Guarantee and Liability Insurance Company (“AGLIC”) and Amerisure Mutual Insurance Company (“Amerisure”), and its excess insurer, U.S. Fire Insurance Company (“U.S. Fire”) who provided liability coverage for S&P’s potential liabilities at the project. The policies contained exclusions for losses arising from mold and did not provide coverage for attorney’s fees or similar legal costs.
Read the court decisionRead the full story...Reprinted courtesy of
Tiffany Casanova, Saxe Doernberger & Vita, P.C.Ms. Casanova may be contacted at