How a 10-Story Wood Building Survived More Than 100 Earthquakes
June 26, 2023 —
Todd Woody - BloombergOne sunny morning last month, an earthquake jolted northeast San Diego. Minutes later, another temblor hit, causing a 10-story wood building to sway.
The quakes, though, were triggered by a computer and the shaking was confined to a 1,000-square-foot platform on which the building — a full-size test model — stood.
The structure is the tallest ever subjected to simulated earthquakes on the world’s largest high-performance “shake table,” which uses hydraulic actuators to thrust the steel platform through six degrees of motion to replicate seismic force. The shake-table trials at a University of California at San Diego facility are part of the TallWood Project, an initiative to test the seismic resiliency of high-rise buildings made of mass timber. An engineered wood building material, mass timber is increasingly popular as a more sustainable alternative to carbon-intensive concrete and steel.
Read the court decisionRead the full story...Reprinted courtesy of
Todd Woody, Bloomberg
Issue and Claim Preclusion When Forced to Litigate Similar Issues in Different Forums: White River Village, LLP v. Fidelity and Deposit Company of Maryland
October 10, 2013 —
Brady Iandiorio — Higgins, Hopkins, McLain & Roswell, LLC.Often in construction litigation the parties wish to move the case to arbitration. However, there are certain circumstances in which such change of litigation forums should be carefully analyzed. The case of White River Village, LLP v. Fidelity and Deposit Company of Maryland, serves as an example of one of those circumstances.
In March 2013, U.S. District Court Judge Blackburn ruled on a motion for summary judgment filed by Fidelity and Deposit Company of Maryland (“F&D”). The order grants the motion in part and denies it in part. White River Village, LLP (“White River”) was the owner of the project which hired S&S Joint Venture (“S&S”), the contractor, to build two similar developments, directly adjacent to each other. The contracts between Whiter River and S&S for the two projects were so substantially similar that the court referred to them as the S&S Contracts. F&D issued payment and performance bonds guarantying the obligations of S&S under the S&S Contracts.
After S&S defaulted on the construction contracts, F&D, as the surety, undertook to complete performance on the contracts. White River alleged that F&D was liable for construction defects and delays in completing the project, and failed to fulfill its obligations under the performance bonds after it overtook the construction of the projects.
Read the court decisionRead the full story...Reprinted courtesy of
Brady IandiorioBrady Iandiorio can be contacted at
Iandiorio@hhmrlaw.com
Colorado Finally Corrects Thirty-Year Old Flaw in Construction Defect Statute of Repose
March 29, 2017 —
Jesse Howard Witt - The Witt Law FirmThe Colorado Supreme Court has finally settled a decades-old conundrum surrounding the state’s construction defect statute of repose.
A statute of repose is similar to a statute of limitations insofar as both restrict the time a party can bring a claim. A statute of repose period begins on a fixed date (such as the day someone finishes work on a project), while a statute of limitations period begins when someone discovers an injury (such as a defectively installed window).
In 1986, at the height of the so-called “tort reform” movement, the Colorado General Assembly voted to shorten both the statute of repose and the statute of limitations for construction defect claims. Historically, Colorado’s statute of repose had given a homeowner ten years following construction to file an action, and its statute of limitations had required that any such action be filed within three years of the date that the claimant discovered a defect. After 1986, however, these time periods changed; the new statute of repose required suits to be filed within six years of the end of construction, and the new statute of limitations gave claimants only two years following discovery of the physical manifestation of a defect to seek legal relief.[1]
Reprinted courtesy of
Jesse Howard Witt, Acerbic Witt
Mr. Witt may be contacted at www.witt.law
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Unpaid Subcontractor Walks Off the Job and Wins
September 01, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCMake the following inquiry of your constructional lawyer, watch him/her sit up in his/her chair and give your question immediate attention: “I haven’t been paid, can I walk off the job?” The answer to this question is a strong “maybe, but it’s risky.” Walking off the project has a significant downside. The risk is that the judge who reviews your decision, sometimes years after the event, may not agree that the non-payment was a material breach and, thus, suspension of performance (walking off) is not justified.
A breach of contract occurs where, without legal justification, a party fails to perform any promise that forms a whole or part of the contract. Not all breaches are equal. Some failures to perform a promise are “nominal,” “trifling” or “technical.” These breaches do not excuse performance under the contract by the non-breaching party. If the breach is “material,” that is, goes to the essential purpose of the agreement, is a question that only a judge decides, and only after the decision was made as to whether to walk off the job or not. Therefore, before deciding whether to walk off the job, you have to second guess what a judge may decide under the circumstances. Since not all judges see things the same way, the decision is fraught with uncertainty and risk.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Contractors: Revisit your Force Majeure Provisions to Account for Hurricanes
September 20, 2017 —
David Adelstein - Florida Construction Legal UpdatesWe now know and can appreciate the threat of hurricanes. Not that we did not appreciate the reality of hurricanes–of course we did–but Hurricane Harvey and Hurricane Irma created the type of actual devastation we fear because they hit close to home. The fear came to life, creating panic, anxiety, and uncertainty. It is hard to plan for a force majeure event such as a hurricane because of the capriciousness of Mother Nature. But, we need to do so from this point forward. No exception! And, I mean no exception!!
A force majeure event is an uncontrollable event that cannot be anticipated with any degree of definitiveness. The force majeure event will excusably delay or hinder performance obligations under a contract. One type of force majeure event is a hurricane—an uncontrollable and unforeseen act of Mother Nature.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Does the Recording of a Mechanic’s Lien Memorandum by Itself Constitute Process? Read to Find Out
August 04, 2021 —
Christopher G. Hill - Construction Law MusingsAs a Virginia construction attorney representing those in the construction industry, mechanic’s liens are near and dear to my heart. The enforcement of mechanic’s lien rights in Virginia is a two-step process. The first step is the recording of a properly-timed memorandum of lien that includes all of the statutorily required information. The second step is a suit to enforce that memorandum of lien filed in Circuit Court. A recent case out of Norfolk, VA examined the first of these steps.
In Central Radio Co. v. Warwick Builders, et al., and as Count III of a three-count Complaint, the Plaintiff, Central Radio Co., alleged that the Defendant, Warwick Builders, recorded a memorandum of lien that Warwick knew to be without merit and therefore committed an abuse of process. However, Warwick did not file any Circuit Court suit to enforce that lien. Central Radio Co. essentially alleged that the filing of the memorandum by itself constituted an attempt to extort payment and therefore was an abuse of process.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Do Not File a Miller Act Payment Bond Lawsuit After the One-Year Statute of Limitations
November 01, 2022 —
David Adelstein - Florida Construction Legal UpdatesUnder the Miller Act, a claim against a Miller Act payment bond must be commenced “no later than one year after the date on which the last of the labor was performed or material was supplied by the person bringing the action.” 40 U.S.C. s. 3133(b)(4). Stated another way, a claimant must file its lawsuit against the Miller Act payment bond within one year from its final furnishing on the project.
Filing a lawsuit too late, i.e., outside of the one-year statute of limitations, will be fatal to a Miller Act payment bond claim. This was the outcome in Diamond Services Corp. v. Travelers Casualty & Surety Company of America, 2022 WL 4990416 (5th Cir. 2022) where a claimant filed a Miller Act payment bond lawsuit four days late. That four days proved to be fatal to its Miller Act payment bond claim and lawsuit. Do not let this happen to you!
In Diamond Services Corp., the claimant submitted a claim to the Miller Act payment bond surety. The surety issued a claim form to the claimant that requested additional information. The claimant returned the surety’s claim form. The surety denied the claim a year and a couple of days after the claimant’s final furnishing. The claimant immediately filed its payment bond lawsuit four days after the year expired. The claimant argued that the surety should be equitably estopped from asserting the statute of limitations in light of the surety’s letter requesting additional information. (The claimant was basically arguing that the statute of limitations should be equitably tolled.) The trial court dismissed the Miller Act payment bond claim finding it was barred by the one-year statute of limitations and that equitable estoppel did not apply.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Insurance Policies Broadly Defining “Suits” May Prompt an Insurer’s Duty to Defend and Indemnify During the Chapter 558 Pre-Suit Notice Process
May 30, 2018 —
Daniel Garcia - Gordon & Rees Construction Law BlogIn Altman Contractors, Inc. v. Crum & Forster Specialty Insurance Company, No. SC16-1420, 2017 WL 6379535 (Fla. Dec. 14, 2017), the Florida Supreme Court addressed whether the notice and repair process set forth in chapter 558, Florida Statutes, constitutes a “suit” within the meaning of a commercial liability policy issued by Crum & Forster Specialty Insurance Company (“C&F”) to Altman Contractors, Inc. (“Altman”). The Court found that because the chapter 558 pre-suit process is an “alternative dispute resolution proceeding” as included in the definition of “suit” in the policy by C&F to Altman, C&F had a duty to defend Altman during the chapter 558 process, prior to the filing of a formal lawsuit.
Chapter 558, titled “Construction Defects,” sets forth procedural requirements before a claimant may file a construction defect action. It requires a claimant to serve a written notice of claim on the applicable contractor, subcontractor, supplier, and/or design professional prior to filing a construction defect lawsuit. The legislature intended for Chapter 558 to be an alternative dispute resolution mechanism in certain construction defect matters allowing an opportunity to resolve the claim without further legal process.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Garcia, Gordon & Rees Scully MansukhaniMr. Garcia may be contacted at
daniel.garcia@grsm.com