Anticipatory Repudiation of a Contract — The Prospective Breach
July 05, 2021 —
David Adelstein - Florida Construction Legal UpdatesThere are instances where a party can engage in the anticipatory repudiation of their obligations under a contract. In essence, this is basically a party prospectively breaching the contract by repudiating their obligations in the contract.
A prospective breach of contract occurs where there is absolute repudiation by one of the parties prior to the time when his performance is due under the terms of the contract. Such a repudiation may be evidenced by words or voluntary acts but the refusal must be distinct, unequivocal, and absolute. Moreover, repudiation can be shown where one party makes additional demands not included in the initial agreement:
The law is clear that where one party to the contract arbitrarily demands performance not required by the contract and couples this demand with a refusal to further perform unless the demand is met, the party has anticipatorily repudiated the contract, which anticipatory repudiation relieves the non-breaching party of its duty to further perform and creates in it an immediate cause of action for breach of contract.
24 Hr Air Service, Inc. v. Hosanna Community Baptist Church, Inc., 46 Fla. L. Weekly, D1344a (Fla. 3d DCA 2021) (quotations and citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Court Finds That SIR Requirements are Not Incorporated into High Level Excess Policies and That Excess Insurers’ Payment of Defense Costs is Not Conditioned on Actual Liability
April 22, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Deere & Co. v. Allstate Ins. Co. (No. A145170, filed 2/25/19), a California appeals court held that the insured was not required to pay additional self-insured retentions (SIRs) in order to trigger higher level excess coverage because the retained limits applicable to the first layer of coverage did not also apply to the higher-layer excess policies.
In Deere, the insured was sued for injuries from alleged exposure to asbestos-containing assemblies used in Deere machines. In a declaratory relief action against its umbrella and excess insurers, the case was tried on: (1) whether the higher-layer excess policies were triggered once the first-layer excess policy limits, which were subject to an SIR paid by Deere, had been exhausted; and (2) whether the insurers’ indemnity obligation extended to Deere’s defense costs incurred in asbestos claims that had been dismissed. The trial court found in favor of the insurers, concluding that the retained limits in the first layer of coverage also applied to the higher-layer excess, which was not triggered until Deere paid additional SIRs. The court also concluded that the insurers were not obligated to pay defense costs when underlying cases were dismissed without payment to a claimant either by judgment or settlement.
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Declines to Create Exception to Privette Doctrine for “Known Hazards”
September 13, 2021 —
Tracy D. Forbath - Lewis BrisboisIn Gonzalez v. Mathis (Aug. 19, 2021, S247677) __ Cal.5th___, the California Supreme Court reversed an appellate decision holding that a landowner may be liable to an independent contractor, or the contractor’s workers, for injuries resulting from “known hazards,” as running contrary to the Privette doctrine.
In Gonzalez, the contractor, who specialized in washing skylights, slipped and fell while accessing the landowner’s particularly hard to reach skylight from a narrow retaining wall that was allegedly covered in loose gravel and slippery. (Slip opn., p. 3.) While the trial court initially granted the landowner summary judgment pursuant to the Privette doctrine, the appellate court reversed and held that the landowner had a responsibility to take reasonable safety precautions where there was a known safety hazard on the landowner’s premises. (Id. at p. 6.) Whether the landowner could have taken various safety precautions also raised disputed issues of material fact precluding summary judgment. (Ibid.)
However, the California Supreme Court concluded that no broad, third exception to the Privette doctrine lies; “unless a landowner retains control over any part of the contractor’s work and negligently exercises that retained control in a manner that affirmatively contributes to the injury [citation], it will not be liable to an independent contractor or its workers for an injury resulting from a known hazard on the premises.” (Slip opn., p. 2.)
Read the court decisionRead the full story...Reprinted courtesy of
Tracy D. Forbath, Lewis BrisboisMs. Forbath may be contacted at
Tracy.Forbath@lewisbrisbois.com
ASCE Statement On White House "Accelerating Infrastructure Summit"
October 17, 2022 —
Maria Lehman, President-elect - American Society of Civil Engineers (ASCE)WASHINGTON, D.C. –We thank the Administration for convening the Accelerating Infrastructure Summit, which highlighted the possibilities stemming from the bipartisan infrastructure law. Nearly one full year since it was passed into law, this transformative legislation is beginning to kickstart vital infrastructure projects nationwide that will improve the country's economic efficiency and prioritize public health and safety.
We know that together, builders, engineers, planners, and those entrusted with infrastructure projects must meet the moment and deliver projects on time, on task, and on budget for communities to make the most of these new resources. This generational investment in infrastructure is much needed - the 2021 Report Card for America's Infrastructure assigned the nation's infrastructure a cumulative grade of "C-" across 17 categories of infrastructure.
ASCE is ready to help optimize these investments for communities across the country and make sure all will benefit, whether it is providing contract templates to expedite the process or offering peer support to smaller and rural agencies.
ASCE is also focused on education in our industry to better equip civil engineers with the knowledge and expertise to execute alternative project delivery methods with a March 2023 Construction Institute Summit in St. Louis, which will provide a dedicated track to highlight innovations that help reduce the time for construction projects.
The bipartisan infrastructure law has provided us the opportunity to transform America and bring our infrastructure into the 21st century, and we will need diverse perspectives, innovative technologies and processes, and a robust workforce to make the most of this once-in-a-generation investment.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Advisory: Mechanical Contractor Scores Victory in Prevailing Wage Dispute
September 03, 2014 —
Steven M. Cvitanovic & Jessica M. Lassere Ryland - Haight Brown & Bonesteel LLPOn August 27, 2014, the First District Court of Appeal weighed in on whether prevailing wages are required for public contracts in situations where work is performed in furtherance of the project but at a permanent offsite manufacturing facility that is not exclusively dedicated to the project. In Sheet Metal Workers' International Association, Local 401 v. John C. Duncan and Russ Will Mechanical, the project at issue was for a community college district where Russ Will was the HVAC subcontractor. The contract documents required contractors to pay prevailing wages but they did not limit where or how Russ Will would fabricate sheet metal required for the job. Russ Will used its existing fabrication facility to form the sheet metal.
An employee of Russ Will filed a complaint with the DIR alleging he should have been paid prevailing wages for work related to the project. The worker fabricated sheet metal for the project but at Russ Will’s Hayward facility, not at the site. The DIR issued a coverage determination in which it concluded that Russ Will was required to pay prevailing wages for the offsite fabrication work associated with the project. The DIR's determination turned on whether Russ Will was exempt from the prevailing wage law as a material supplier. To qualify for the material supplier exemption, the employer must sell supplies to the general public and its fabrication or manufacturing facility must not be established for the particular public works contract or be located at the site of the public work.
Following the DIR determination, Rush Will filed an administrative appeal. The department reversed its initial coverage determination, concluding that the offsite fabrication performed by Russ Will was not subject to the prevailing wage law.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Jessica M. Lassere Ryland, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Ryland may be contacted at jlassere@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Rhode Island Closes One Bridge and May Have Burned Others with Ensuing Lawsuit
October 07, 2024 —
Bill Wilson - Construction Law ZoneThe state of Rhode Island recently filed a lawsuit against 13 companies that provided design, construction, and inspection services over the past ten years (the extent allowed by the applicable statute of limitations) to the Washington Bridge, which carries I-195 between East Providence and Providence. The bridge was abruptly closed in December 2023 following the discovery of alleged fractured steel tie-downs critical to the bridge’s stability and additional deterioration in cantilever beams throughout the bridge. Before the closure, approximately 90,000 vehicles per day traveled over the bridge.
The complaint alleges that the defendants, the majority of which are experienced, industry-leading firms in their respective fields, were negligent and breached their respective contracts with the State. The State contends that every company that worked on the bridge over the past ten years missed the serious structural conditions alleged. The lawsuit also claims that the State has suffered millions of dollars of damages since the bridge was closed and seeks indemnity and contribution from all defendants to the extent that the State may be liable to third parties in the future.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLP
Toolbox Talk Series Recap - Guided Choice Mediation
November 05, 2024 —
Douglas J. Mackin - The Dispute ResolverIn the September 26, 2024 edition of Division 1's Toolbox Talk Series,
Clifford Shapiro presented on Guided Choice Mediation (“GCM”) and how it can lead to better outcomes in construction disputes.
GCM is an approach to mediation that focuses on early and efficient dispute resolution, which prominent mediators created as a public interest project.
Shapiro described his particular variant of GCM based on his experience while acknowledging that other Guided Choice Mediators’ processes may differ from his in various ways. Shapiro’s brand of GCM focuses on ensuring that parties have reasonable expectations and appropriate settlement authority prior to arriving at a mediation. Some of the strategies to help accomplish these noble goals are (i) early mediator engagement, (ii) mediator facilitation of information exchange, (iii) mediator involvement with insurance issues (particularly important in construction defect cases, especially those with multiple defendants), (iii) pre-mediation ex parte meetings, and (iv) mediator participation in risk analysis. These strategies are not typical in the more traditional/historic approach to mediation in which mediation is scheduled based on a scheduling order, mediation statements are sent to the mediator roughly a week before the scheduled mediation (and sometimes not even shared with anyone other than the mediator), and the parties speak with the mediator for the first time on the day of the mediation.
Read the court decisionRead the full story...Reprinted courtesy of
Douglas J. Mackin, Cozen O’ConnorMr. Mackin may be contacted at
dmackin@cozen.com
Court of Appeals Discusses Implied Duty of Good Faith and Fair Dealing in Public Works Contracting
August 17, 2017 —
Lindsay K. Taft - Ahlers & Cressman PLLCThe implied duty of good faith and fair dealing is implied in every contract, including construction contracts. Generally speaking, this implied duty requires parties cooperate with one another so that they each obtain the full benefit of their contracted bargain. Recently, the Court of Appeals (Division II) in Nova Contracting, Inc. v. City of Olympia discussed this duty’s application to a public works contract.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay K. Taft, Ahlers & Cressman PLLCMs. Taft may be contacted at
ltaft@ac-lawyers.com