Contractor Walks Off Job. What are the Owner’s Damages?
September 25, 2018 —
David Adelstein - Florida Construction Legal UpdatesWhat are your damages as the result of a breach of the construction contract? This is an important question, right? It is probably the most important part of your case. If you didn’t have damages, you wouldn’t be in a dispute. So, I repeat, what are your damages as the result of a breach of the construction contract? The below case explains dealing with a contractor that elected to walk off the job mid-construction.
In Forbes v. Prime General Contractors, Inc., 43 Fla.L.Weekly D20194a (Fla. 2d DCA 2018), owners hired a contractor to perform a residential renovation job for $276,000. The owners were to pay the contractor in five draw payments (common for residential jobs) where the third draw payment was due upon the contractor’s completion of the dry-in (as defined in the contract). After the contractor received the first two draw payments totaling $138,000 plus an additional $6,000 for updated architectural plans, the contractor claimed the job doubled in price and demanded that the owners pay the contractor the third draw payment immediately (before it was due) plus an additional $31,450. The contractor refused to continue unless the owners agreed to its terms, and then walked off the job when the owners would not agree to these terms (nor should the owners agree to those terms). At the time the contractor walked off the job, the owners’ home was not habitable due to the construction.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Big Builder’s Analysis of the Top Ten Richest Counties
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFFBig Builder took Forbes’ 2014 top ten richest U.S. counties list (based on household median income) and researched who the top builders were in those regions, buyer requirements, among other categories. The top three richest counties according to Forbes and Big Builder are Falls Church, Virginia; Loudoun County, Virginia; and Los Alamos County, New Mexico.
Information listed for each county include the median-closing price, price per square foot, living square feet, top builders, and an examination of what makes each region unique.
Read the court decisionRead the full story...Reprinted courtesy of
Federal Contractors – Double Check the Terms of Your Contract Before Performing Ordered Changes
July 08, 2019 —
Jonathan Schirmer - Ahlers Cressman & Sleight PLLCAs federal contractors may be aware, the general rule when performing a contract for the federal government is that only the contracting officer (“CO”) can bind the government. Often, the CO delegates responsibility to a contracting officer’s representative (“COR”). While in some cases a COR may be able to bind the federal government, the contract may limit that ability exclusively to the CO.
Important for our clients, it is the responsibility of the contractor to determine whether the COR can legally bind the federal government when ordering changes to the scope of work. [1] This is true even when a COR possesses apparent authority to order changes to the work, and when the project is almost exclusively overseen by COR’s. [2]
A recent case highlights the dangers of a contractor relying on the orders of a COR when performing work outside the scope of a contract. In Baistar Mechanical Inc., a contractor was awarded a maintenance and snow removal contract with the federal government. The contract expressly stated that only the CO had contracting authority regarding additional or changed work. [3] However, Baistar, the contractor, argued it was directed by the contracting officer’s representatives to perform work outside of the contract.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan Schirmer, Ahlers Cressman & Sleight PLLCMr. Schirmer may be contacted at
jonathan.schirmer@acslawyers.com
New Jersey Supreme Court Hears Arguments on Coverage Gap Dispute
October 26, 2017 —
Austin D. Moody - Saxe Doernberger & Vita, P.C.On Tuesday, October 24, the New Jersey Supreme Court heard arguments in a 17-year-old battle over whether Honeywell International Inc. (Honeywell) will have to help cover the costs of asbestos-related injury suits that were filed against it after insurers began to universally exclude coverage for asbestos-related liabilities. The Court considered the arguments made by two excess insurers, St. Paul Fire and Marine Insurance Co. (St. Paul) and parent Travelers Casualty and Surety Co. (Travelers), that the Court should overturn a state appellate court’s ruling that Honeywell does not have to contribute to these costs.
During the course of this case, Honeywell has sought coverage under more than 300 different policies, ultimately settling with all insurers except St. Paul and Travelers, who had issued a total of 10 excess policies to Honeywell’s predecessor, Bendix Corp. (Bendix) between 1968 and 1983. Honeywell has only sought coverage for claims made by individuals who allege that they were first exposed to asbestos prior to 1987.
Read the court decisionRead the full story...Reprinted courtesy of
Austin D. Moody, Saxe Doernberger & Vita, P.C.Mr. Moody may be contacted at
adm@sdvlaw.com
Competition to Design Washington D.C.’s 11th Street Bridge Park
May 07, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Architect Magazine, eighty landscape architecture and architecture firms (forty teams) submitted proposals to design the $25-million Washington D.C. 11th Street Bridge Park project. A jury has shortlisted six design teams: “Wallace Roberts & Todd (WRT)/Next Architects, Piet Oudolf with Glenn LaRue Smith/PUSH Studio/WXY Architecture + Urban Design, OLIN/OMA, Workshop: Ken Smith Landscape/Davis Brody Bond, Stoss Landscape Urbanism/Höweler + Yoon Architecture, and Balmori Associates/Cooper, Robertson & Partners.”
The “nonprofit Building Bridges Across the River at THEARC (Town Hall Education Arts Recreation Campus) and the District's Office of Planning” launched the competition in March of this year. Architect Magazine stated that “the goal of” the project is to unify “what some call a ‘long-divided city,’ by connecting Capitol Hill and Anacostia, the neighborhoods on either side of the river.”
Read the court decisionRead the full story...Reprinted courtesy of
Appellate Attorney’s Fees and the Significant Issues Test
June 29, 2017 —
David Adelstein - Florida Construction Legal UpdatesThe significant issues test to determine the prevailing party in construction lien actions (which, by the way, also applies to breach of contract actions) applies to appellate attorney’s fees too! Under this test, the trial court has discretion to determine which party prevailed on the significant issues of the case for purposes of attorney’s fees. The trial court also has discretion to determine that neither party was the prevailing party for purposes of attorney’s fees.
In a recent decision, Bauer v. Ready Windows Sales & Service Corp., 42 Fla. L. Weekly D1417a (Fla. 3d DCA 2017), there were competing motions for appellate attorney’s fees. Both parties believed they should be deemed the prevailing party under Florida Statute s. 713.29 (statute that authorizes prevailing party attorney’s fees under Florida’s Construction Lien Law). The appellate court held that neither party was the prevailing party under the significant issues test: “[W]e conclude that each party lost on their appeal, while each party successfully defended that part of the judgment in their favor on the other party’s cross-appeal. Because both parties prevailed on significant issues, this Court finds that appellate fees are not warranted for either party.”
Bauer, supra. Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
When to use Arbitration to Resolve Construction Disputes
February 25, 2014 —
Beverley BevenFlorez-CDJ STAFFOn the blog Construction Contractor Advisor, Craig Martin answers the question of whether arbitration is always the best choice for resolving construction claims. His answer: “Some claims may benefit from arbitration, but the benefit is not always clear.”
Martin brings forth four points to consider. First, AIA Contracts do not “push Arbitration.” Second, the cost of arbitration may be expensive: “You could well spend over $5,000 just to have the arbitrator decide your case—again, not to mention your own attorneys fees.” Third, arbitration doesn’t avoid discovery. And finally, “mediation is always an option, regardless of which way you pursue your claim.”
Read the court decisionRead the full story...Reprinted courtesy of
7 Sustainability Ideas for Modular Classrooms in the Education Industry (guest post)
June 10, 2015 —
Melissa Dewey Brumback – Construction Law in North CarolinaToday, a guest post on sustainable modular classrooms from Kathy Werder, a freelance architect by profession and a researcher by nature. According to Kathy, most of her research papers focus on promoting integration that leads to sustainable and lean design and construction practices. Kathy is obsessed with the latest rage in the construction industry – modular building solutions. She is also an avid writer, and loves blogging about green buildings and portable construction units. Welcome, Kathy!
According to Wikipedia, a sustainable building refers to “ a structure and using process that is environmentally responsible and resource-efficient throughout a building’s life-cycle from sitting, to design, construction, operation, maintenance, renovation, and demolition.”
So if we accept this definition to be true, in order to make an actual sustainable building we have to consider the entire process of building right from the blueprint stage all the way to demolition, and ensure that at every step of the way there is minimal or no negative impact on the environment, especially in terms of resource efficiency.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at