Standard For Evaluating Delay – Directly from An Armed Services Board Of Contract Appeal’s Opinion
October 04, 2021 —
David Adelstein - Florida Construction Legal UpdatesSometimes, it is much better to hear it from the horse’s mouth. That is the case here. The Armed Services Board of Contract Appeal’s (ASBCA) opinion in Appeals of -GSC Construction, Inc., ASBCA No. 59402, 2020 WL 8148687 (ASBCA November 4, 2020) includes an informative discussion of a contractor’s burden when it encounters excusable delay and, of importance, the standard for evaluating delay. It’s a long discussion but one that parties in construction need to know, appreciate, and understand. EVERY WORD IN THIS DISCUSSION MATTERS.
Construction projects get delayed and with a delay comes money because time is money. Many claims are predicated on delay. These can be an owner assessing liquidated damages due to a delayed job or a contractor seeking its costs for delay. Either way, the standard for evaluating delay and the burdens imposed on a party cannot be understated and, certainly, cannot be overlooked. For this reason, here is the discussion on evaluating delay directly from the horse’s mouth in the Appeal of-GSC Construction, Inc.:
The critical path is the longest path in the schedule on which any delay or disruption would cause a day-for-day delay to the project itself; those activities must be performed as they are scheduled and timely in order for the project to finish on time. Wilner v. United States, 23 Cl. Ct. 241, 245 (1991). In Yates-Desbuild Joint Venture, CBCA No. 3350 et al., 17-1 BCA ¶ 36,870, our sister board compiled an excellent and very helpful synopsis of the standards for evaluating delay claims, which I adopt nearly verbatim among the discussion that follows.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Pulte’s Kitchen Innovation Throw Down
December 10, 2015 —
Beverley BevenFlorez-CDJ STAFFPulte Group’s national purchasing director, Kellee Hansen, created a kitchen competition where six unaffiliated manufacturers competed against each other to build a kitchen vignette based on three consumer segments, reported Builder Online.
On October 19th, each team had fifteen minutes to present their vignettes to about 100 people.
“In our industry, I think we lack some collaboration, historically,” Hansen told Builder Online. “Listening to our suppliers just makes us better and it makes us better as an industry. I think it raises the level for all our peers as well when we listen to our manufacturers.”
Read the court decisionRead the full story...Reprinted courtesy of
Designing the Process to Deliver Zero-Carbon Construction – Computational Design in Practice
January 04, 2023 —
Peter Debney - AEC BusinessComputational Design is generating increasing interest in the construction industry as well as a certain amount of confusion. It is not parametric design; instead it takes parametric design to the next level. It is a set of methods that will define how we design structures over the next decades.
With Computational Design, you don’t design the building; you design the automated process to find the best building design.
Why use Computational Design?
Computational Design is enabling us to create buildings that are far more efficient than we can manage using more traditional methods. Some architects are indeed using it to produce novel building forms, but its great advantage is in helping us towards efficient, zero-carbon construction.
Read the court decisionRead the full story...Reprinted courtesy of
Peter Debney, AEC Business
Venue for Miller Act Payment Bond When Project is Outside of Us
December 02, 2019 —
David Adelstein - Florida Construction Legal UpdatesThe proper venue for a Miller Act payment bond claim is “in the United States District Court for any district in which the contract was to be performed and executed, regardless of the amount in controversy.” 40 U.S.C. s. 3133(b)(3)(B).
Well, there are a number of federal construction projects that take place outside of the United States. For these projects, where is the correct venue to sue a Miller Act payment bond if there is no US District Court where the project is located? A recent opinion out of the Southern District of Florida answers this question.
In U.S. ex. rel. Salt Energy, LLC v. Lexon Ins. Co., 2019 WL 3842290 (S.D.Fla. 2019), a prime contractor was hired by the government to design and construct a solar power system for the US Embassy’s parking garage in Burkina Faso. The prime contractor hired a subcontractor to perform a portion of its scope of work.
The subcontractor remained unpaid in excess of $500,000 and instituted a Miller Act payment bond claim against the payment bond surety in the Southern District of Florida, Miami division. The surety moved to transfer venue to the Eastern District of Virginia arguing that the Southern District of Florida was an improper venue. The court agreed and transferred venue. Why?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
New York's Highest Court Says Asbestos Causation Requires Evidence Of Sufficient Exposure To Sustain Liability
May 10, 2022 —
Rafael Vergara & Jhonattan N. Gonzalez - White and WilliamsOn April 26, 2022, the New York Court of Appeals described that in toxic tort cases a plaintiff can only establish liability-creating causation for an adverse health effect with “expert testimony based on generally accepted methodologies.” See
Francis Nemeth v. Brenntag North America (N.Y. Apr. 26, 2022). The suit involved alleged asbestos exposure from talc.
The plaintiff alleged liability for talc contaminated with asbestos that was ultimately used in a commercial talcum powder, Desert Flower, which the decedent applied daily from 1960 to 1971. At trial, the plaintiff proffered two expert witnesses, a geologist, Sean Fitzgerald, who testified about the “glove box test” and a doctor of internal medicine, Dr. Jacqueline Moline. Fitzgerald’s glove box test consisted of agitating a sample of Desert Flower in a Plexiglas chamber. Fitzgerald concluded that the asbestos fibers in the sample of Desert Flower were “significantly releasable” and that the decedent was exposed to thousands to trillions of fibers through repeated use. Dr. Moline concluded Desert Flower was “a substantial contributing factor” to the decedent’s peritoneal mesothelioma. The jury returned a verdict in the plaintiff’s favor.
Reprinted courtesy of
Rafael Vergara, White and Williams and
Jhonattan N. Gonzalez, White and Williams
Mr. Vergara may be contacted at vergarar@whiteandwilliams.com
Mr. Gonzalez may be contacted at gonzalezj@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Harmon Tower Construction Defects Update: Who’s To Blame?
August 17, 2011 —
CDJ STAFFReporting on the site VegasInc.com, Liz Benton notes that “nobody wants to take the fall for what happened at Harmon.” Work on the Harmon hotel building in Las Vegas’s CityCenter stopped in 2008 after 26 of the planned 49 stories were completed. Lorence Slutzky, a construction law professor at John Marshall Law School and a partner with the Chicago firm Robbins Schwartz Nicholas Lifton & Taylor told Benton that while inspectors and others are complicit, “the real responsibility rests with Perini, which has an obligation to comply with the plan specifications.” Perini’s claim is that they were given faulty design drawings. MGM disputes this.
Perini has offered to repair the building defects, however MGM has released a statement that they have “zero confidence or trust that Perini can and will properly fix a building it has so badly constructed thus far.” One MGM spokesperson likened these requests from Perini to “the director of ‘Ishar’ demanding a sequel.” “Ishtar,’ cost Columbia Pictures $55 million dollars and earned only $4.2 million in its initial run. Perini claims that MGM halted work because of the economy.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
What Counts as Adequate Opportunity to Cure?
June 13, 2022 —
Christopher G. Hill - Construction Law Musingsqimono @ PixabayHere at Musings, we like to discuss (likely more than readers would like) the fact that in Virginia, the contract is king and its terms will be looked at carefully by the courts. One of those provisions that will be looked at carefully is the so-called “cure period.” The “cure period” is the time that a subcontractor has to fix any non-compliant construction after receiving notice of any deviation from the contract documents that must be fixed.
In United States ex rel Allan Myers VA, Inc. v. Ocean Construction Services, Inc. the federal court for the Eastern District of Virginia examined what it means to grant a proper opportunity to cure. The Ocean Construction Services case arises from a contractual dispute between Allan Myers VA Inc. and Ocean Construction Services Inc., or OCS, involving renovation work performed in sections of Arlington National Cemetery. Presently before the court is Myers’ motion for partial summary judgment, arguing that the undisputed facts demonstrate that it was not provided with a three-day cure period, a contractual prerequisite to OCS terminating the subcontract for default.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Illusory Insurance Coverage: Real or Unreal?
August 24, 2017 —
David Adelstein - Florida Construction Legal UpdatesIn insurance coverage declaratory relief actions, there are times an insured will argue that the insurance policy coverage is illusory. Typically, an insured will raise this illusory argument if its insurer is denying coverage based on an exclusion or limitation in the policy. If a court agrees and deems the coverage illusory, the court will construe the policy to afford coverage to the insured. This is the obvious value of the argument: coverage!
“A policy is illusory only if there is an internal contradiction that completely negates the coverage it expresses to provide.” The Warwick Corp. v. Turetsky, 42 Fla.L.Weekly D1797a (Fla. 4th DCA 2017). Thus, if a policy grants coverage in one section but then excludes the same coverage in another section, the coverage would be deemed illusory. Id. quoting Tire Kingdom, Inc. v. First S. Ins. Co., 573 So.2d 885, 887 (Fla. 3d DCA 1990). An illusory policy was found in the following examples: (a) a policy covered certain intentional torts but then excluded intended acts; (b) a policy covered advertising injury but elsewhere excluded advertising injury; and (c) a policy covered parasailing but excluded watercrafts. Id. (citations omitted). In all examples, coverage in the policy was completely swallowed up by an exclusion rendering the coverage illusory. Stated differently, coverage was completely contradicted by an exclusion in the policy rendering the policy absurd.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com