Burden to Prove Exception to Exclusion Falls on Insured
April 19, 2022 —
Tred R. Eyerly - Insurance Law HawaiiIn a dispute between two insurers, the Ninth Circuit relied upon Nevada law in finding that the burden of proving that an exception to the exclusion applies was on the insured. Zurich Am. Ins. Co. v. Ironshore Specialty Ins. Co., 2022 U.S. App. LEXIS 1626 (9th Cir. Jan. 20, 2022).
Ironshore insured seven subcontractors. The policy included an exclusion providing there was no coverage for any property damage for the subcontractors' for "work performed prior to the policy inception." An exception to the exclusion provided that the exclusion did not apply to property damage that was "sudden and accidental and takes place within the policy period."
The seven subcontractors were sued for work they had performed. Zurich defended and indemnified the subcontractors. Zurich then sued Ironshore seeking contribution and indemnification for defense and settlement costs. The parties stipulated that all construction work at issue had been completed before the inception of Ironshore's policy and that none of the complaints against the subcontractors alleged that sudden and accidental damage had occurred after the inception of Ironshore's policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Turner Construction Selected for Anaheim Convention Center Expansion Project
May 21, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Anaheim, California city council selected Turner Construction Company “to manage a $180 million expansion of the Anaheim Convention Center, a venue that hosted 238 tradeshows, conventions, meetings and consumer events in 2013,” according to Construction Digital.
“Turner’s Southern California office calls Anaheim home, and we are pleased to be working on such a great project in our own backyard,” Kevin Dow, Vice President and General Manager of Turner’s Southern California office told Construction Digital.
Read the court decisionRead the full story...Reprinted courtesy of
Avoid Drowning in Data: Keep Afloat with ESI in Construction Litigation
May 15, 2023 —
Steve Swart - The Dispute ResolverMaybe it is another lawyer on your team, a client, the Court. Maybe it is you. Almost every lawyer has heard (or thought, felt, or anguished over) the following: Wait — What? Discovery is going to cost how much?
The concern is real. Per a 2019 Southern District of New York opinion:
- The average case can involve collection, review and production of 100 gigabytes of data (or 6.5 million pages of Word documents).
- At a typical rate of review of 40-60 documents per hour, assuming 100,000 documents are collected, that is about 2,000 hours of attorney review time.
- Adding in fees for forensic collection, storage, and processing to maintain metadata can result in a bill totaling $500,000.
Brown v. Barnes & Noble, Inc., 474 F. Supp. 3d 637, 645 & n.3 (S.D.N.Y. 2019).
What's counsel to do? The following four points can help counsel streamline and reduce costs in discovery: (1) know your case, (2) know your data — understand it and document collection, (3) cooperate with counsel, and (4) implement a protocol for electronically-stored information ("ESI").
Read the court decisionRead the full story...Reprinted courtesy of
Steve Swart, Williams MullenMr. Swart may be contacted at
sswart@williamsmullen.com
Firm Pays $8.4M to Settle Hurricane Restoration Contract Case
December 13, 2022 —
James Leggate - Engineering News-RecordAn electricity distribution infrastructure contractor that worked for the U.S. Army Corps of Engineers on hurricane restoration in Puerto Rico has agreed to pay the government $8.4 million to resolve allegations that it improperly withheld pricing data. The company denies the charges, agreeing to the settlement in order to avoid lengthy litigation.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Know When Your Claim “Accrues” or Risk Losing It
August 20, 2019 —
Christopher G. Hill - Construction Law MusingsI have discussed statutes of limitation on construction claims in various contexts from issues with a disconnect on state projects to questions of continuous breach here at Construction Law Musings. For those that are first time readers, the statute of limitations is the time during which a plaintiff can bring its claim, whether under the Virginia Consumer Protection Act (VCPA), for breach of contract, or for any other legal wrong that was done to him, her or it by another. The range of limitations runs the gamut of times, for instance it is 5 years for breach of a written contract and 6 months for enforcement of a mechanic’s lien. This time period is calculated from the “accrual” of the right of action. “Accrual” is, in general terms, when the plaintiff was originally harmed or should have known it was harmed (depending on the particular cause of action).
A recent case out of the Circuit Court of Norfolk, Virginia examined when a cause of action for a construction related claim under the VCPA accrued and thus whether the plaintiff’s claim was timely. In Hyde Park Free Will Baptist Church v. Skye-Brynn Enterprises Inc., the Court looked at the following basic facts (pay attention to the dates):
The Plaintiff, Hyde Park Baptist Church, hired the Defendant, Skye-Brynn Enterprises, Inc., to perform certain roof repairs that were “completed” in 2015. Shortly after the work was done, in 2015, the Plaintiff informed Defendant that the roof still leaked and that some leaks were worse than before. The Defendant unsuccessfully attempted repair at the time. 14 months later in 2017, the church had other contractors examine the roof and opine as to its faulty installation. Also in 2017, the church submitted roof samples to GAF, the roof membrane manufacturer and in February 2018 GAF responded stating that the leaks were not due to manufacturing defects. The church filed its complaint on October 1, 2018 breach of contract, breach of warranty of workmanship and fraud in violation of the VCPA. Defendant responded with a plea in bar, arguing that the statute of limitations barred the claim.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
More Musings on Why I Mediate
November 18, 2024 —
Christopher G. Hill - Construction Law MusingsWhew! I’m back. And yes, I know it’s been a while (it has been a busy year, both personally and professionally). Hopefully, this will be the first of at least a few more consistent posts here at Construction Law Musings. Now, on with the post:
Over the last few weeks, I’ve had a surge in mediation, both in my capacity as a mediator and as counsel for construction industry clients. These recent events have reaffirmed what I have always believed to be true, namely that no construction case is impossible to settle and avoid the cost and expense of litigation. I was also reminded of why I became a certified mediator and of the satisfaction that I get from helping individuals and construction companies find a business solution and closure.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Biggest Trials Coming to Courts Around the World in 2021
January 04, 2021 —
Anthony Lin - BloombergSeveral former world leaders, a Hong Kong media tycoon, the CEO of Theranos and Jeffrey Epstein’s confidante — all are scheduled to have their day in court next year.
With vaccinations heralding a return to normalcy, the next year should see courtrooms around the world coming back to life. Ghislaine Maxwell, China critic Jimmy Lai and Samsung heir Jay Y. Lee are among those facing high-profile criminal cases in 2021. Some proceedings, including the fraud trial of Theranos founder Elizabeth Holmes, are resuming after being postponed by the pandemic. Another delayed case, UBS’s appeal of its $4.9 billion French government tax penalty, is among the many that will be heard by higher-level and supreme courts.
There are also a number of cases against former world leaders, including France’s Nicolas Sarkozy, Malaysia’s Najib Razak and South Africa’s Jacob Zuma. One of the most tantalizing questions will be whether a certain former U.S. president could find himself facing trial as well.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony Lin, Bloomberg
A Court-Side Seat: Flint Failures, Missed Deadlines, Toad Work and a Game of Chicken
October 05, 2020 —
Anthony B. Cavender - Gravel2GavelThe last few weeks have yielded a number of interesting developments in the Federal courts.
FEDERAL COURTS OF APPEAL
In re Flint Water Cases
Several local and State of Michigan officials, including the former governor, requested dismissal from the civil litigation seeking damages for the massive failure of Flint, Michigan’s public drinking water system. On August 5, 2020, the U.S. Court of Appeals for the Sixth Circuit agreed that the plaintiffs, residents of Flint, have successfully pled a case that the conduct of the defendants so “shocked the conscience” that a claim for a violation of their substantive due process rights was appropriately alleged. The defendants, including the former governor, argued that they were entitled to a qualified immunity defense. The court rejected this argument on the basis of the earlier decisions made by the court in this matter. Judge Sutton concurred because he was bound by this precedent, but remarked that the evidence for the governor’s culpability was very thin; he was not intimately connected to the extraordinary error in judgment. The majority was very upset with this concurrence as indicted by their own opinion.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com